Project : BROWNS OXIDE PROJECT - PROCESSING PLANT/ LEACHING FACILITIES
|
Mining - Primary And Secondary Processing
Minerals Processing
|
|
Estimated Project Value
$
69,000,000
|
|
|
Address
|
South East of
|
Suburb
|
Darwin
|
State
|
NT
|
Council
|
Darwin City
|
Postcode
|
0800
|
|
Project Type
|
Processing Plant/Leaching Facilities
|
Development Type
|
New
|
Status
|
Firm
|
Stage
|
Site Preparation in Progress
|
Ownership
|
Private
|
Notes
|
Civil Works In Progress Construction Manager Named
|
|
Commence Date
|
1/4/2007
|
Completion Date
|
1/7/2007
|
|
|
Details
|
|
-
The plant will treat 1.3 million tonnes per year.
- All major items of equipment for the plant have been acquired including grinding and classification circuit, Cawse solvent extraction, electrowinning plant, thickners and tanks have also been acquired.
- Other equipment is being custom designed and fabricated offsite.
- Detailed engineering design works of the plant are in progress.
- Finalisation of processing plant flowsheet and confirmatory metallurgical testwork are also in progress.
- Testwork has already shown that the valuable copper, cobalt and nickel minerals are dissolved in acid.
- Once the metals are in the solution, the liquor is separated from the leached solids which are then washed and sent to the tailings storage facility.
- Testwork is confirming solvent extraction design criteria for concentrating metals in solution ahead of copper electrowinning of high purity cathode product.
- The facility will comprise a solvent extraction plant, electrowiring plant, tankage and product filtering equipment.
-
Excavation and concreting works have commenced for the plant.
- There are still tender packages available for the project.
- These are available by sending an expression of interest to Bradley Granger.
- Construction of the plant is to commence when the wet season of 2006 is completed and to be commissioned mid 2007.
- Relocation of equipment is being done by Eureka Mine Constructions.
|
|
|
|
|
We’ve been providing the Australian construction industry with comprehensive project
information and construction leads for over 45 years to help people like you get
involved and get specified in projects. From the very early stages of a project
right through to construction we’ve got it covered, helping you stay one step ahead
of your competitors. So if you want to find out about more projects with Australia’s
most trusted construction information, then contact us now to grow your business,
and find out about more activity than ever before.
|
|
More Projects by States
More Projects by Categories
|
|