ALCAN GOVE BAUXITE OPERATIONS - CIVILS/PRELIMINARY WORKS
Mining - Primary And Secondary Processing (Civil works at processing facilities) project In The East Arnhem Shire Council Area of Civil Works type. Preliminary works to include roads, laydown areas. Click for more details...

ALCAN GOVE BAUXITE OPERATIONS - CIVILS/PRELIMINARYWORKS
Civil Works Packages project at At, Gove, NT 0880 In The Council Area Of East Arnhem Shire of Private. Various. Civil works likely to include a wharf. Click for more details...

DARWIN EAST ARM WHARF - BULK MATERIALS HANDLING INFRASTRUCTURE PROJECT
Mining - Primary And Secondary Processing (Civil works at processing facilities) project In The Darwin City Council Area of Private ownership. Expressions of interest are sought to design, procure and construct common user bulk materials handling facilities for the export of bulk ore. The package includes rail and road bottom dump facilities, including an associated conveyor system to a stockpile area and headworks and a ship loader and associated headworks. Click for more details...

BATCHELOR SUBSTATION - CIVIL/EARTHING WORKS
A project in the NT Within Darwin City. Work comprises civil and drainage works, earth grid and connection tails, fencing, installed certified and fully serviced crib room, new poles, nominated structures, and foundations for HV structures. All structures to include hold down bolts measured to ensure they will accommodate the future installation of electrical equipment that will be relocated from the Edith River substation. Click for more details...

ICHTHYS GAS PROJECT - MAIN CIVIL WORK (CVL3) - TEMPORARY WORKS DESIGN REV1 CONSULTANCIES
Ichthys Gas Project - Main Civil Work (Cvl3) - Temporary Works Design Rev1 Consultancies is currently at the Construction stage, valued at about $ 250000 it is For the provision of Temporary Works Design along with Construction Methodologies associated with CVL3 Main Civil Works project on the Ichthys Project Onshore LNG facilities. Click for more details...