State

Categories

Sub Categories

Click Here to Find Current Projects

List of Dams Projects


EPA MINOR CIVIL WORKS
various btwn Camden & Windsor, ., NSW 2999 Has Epa Minor Civil Works currently at Tenders & Building stage. Installation/construction of various nutrient reduction measures in western Sydney between Camden & Windsor. Typical work requires small dam construction, trenched pipe installation, concreting, minor electrical installation & pump installation. Click for more details...

DARGALONG RD EARTHWORKS/DAM
Civil Engineering (Dams) project In The Strathbogie Council Area of Private ownership. Earthworks and the creation of a dam. Revegetation following completion of dam construction. The fill is then to be used by the contractor in the Goulburn Valley Highway Murchison East Deviation Click for more details...

FAIRWAY WATER RETIREMENT VILLAGE
Currently at the Construction stage In Cardinia is a project estimated to be $ 33000000. This project Construction of a retirement village, brick veneer and large feature lake with associated wetlands on 17 Ha. of vacant land. 380 2 bedroom units comprising attached and detached and combination of 1 and 2 storey but mostly single storey. 350 Independent living units and 30 serviced apartments. Concrete slab steel frame and metal roof. Click for more details...

ERARING POWER STATION
Rocky Point Rd, Eraring, NSW 2264 Has Eraring Power Station currently at Tenders & Building stage. Capping & rehabilitation of approx 30 hectares of the Eraring Power Station Ash Dam. Using nominated materials & further construction of associated drainage works as & when required for period of 18 months from the date of issue of the Principal's Purchase Order. Click for more details...

THE ENTRANCE SEAWALL REHABILITATION PROGRAM
Cathodic Protection System New project In The Wyong Council Area. Design & construction of the seawall rehabilitation contract works which will include the following: investigate, design & construct a Cathodic Protection System to approx 135 lineal metres of existing contiguous driven reinforced concrete piles; demolish & reconstruct approx 135 lineal metres of existing concrete capping beam to the Principal's design; expose for inspection, assessment & replacement as directed, existing the back connections between the seawall capping beam & deadman anchors. Click for more details...

BROU LAKE LANDFILL SITE
Local Govt ownership Civil Engineering (Dams) project In The Eurobodalla Council Area for New development. Design & construction of waste cell & leachate dam. The work will include the detailed design of dams, waste cells, stormwater drains & leachate pipes as well as cell construction. Click for more details...

VASSE AND WONNERUP WATERWAYS - MARINE FLOODGATES
New project of Civil Engineering (Dams) project at Vasse & Wonnerup Estuaries via Layman Rd & Floodgate Rd, Wonnerup, WA 6280. It is proposed to construct two new floodgates of concrete & steel in waterways of Vasse & Wonnerup Estuaries. New floodgates will be built in close proximity to existing timber floodgates, which have reached end of their design life. Existing timber floodgates to be kept operational while new work is being built. Generally scope of works shall comprise construction & commissioning of replacement floodgates, along with completion of all interfaces between new & existing elements. It includes civil, electrical, instrumentation, mechanical, telemetry & structural works. Scope includes, but is not necessarily limited to design & construction of temporary works such as coffer dams & dewatering facilities so that works can be undertaken in dry conditions; design & construction of measures to limit environmental impacts such as turbidity, odour & noise (it is envisaged that turbidity control measures will include detention basin, clearwater discharge facilities & silt curtains); demolition of remnants of Old Ballarat Railway Bridge & extraction of any associated timber piles that conflict with proposed position of cut-off sheet piles on new floodgates (this work includes backfilling of each extraction site); excavation, disposal & earth filling for floodgates & abutments; supply & installation of permanent sheet piling, cast in-situ reinforced concrete, pre-cast culverts, revetment mattresses, fibreglass stopboards & associated works; supply & installation of mechanical, electrical instrumentation & telemetry works for monitoring & actuation of floodgates; removal & modification of existing stainless steel flap gates from old timber structures & mounting on new structures; road & drainage works; testing & commissioning of new floodgates; demolition of old floodgates, including preservation of south abutment & infill wall of Wonnerup Floodgates. Click for more details...

LOGAN RIVER CATCHMENT EARLY WORKS
New project of Civil Engineering (Dams) project at Bromelton, Wyaralong Dam and, Cedar Grove, QLD 4285. For the Cedar Grove Weir (on Logan River, 5km downstream of Teviot Brook), to construct and commission steel shet pile weir, incorporating fish lock and associated works. For the off-stream storage at Bromelton (four potential sites off Logan River, 2 near Sandy Creek & two near Bromelton), to design, construct and commission water storage and associated works, likely to be a "turkeys nest" design and hold between 7500ML and 15000ML). For the Wyaralong Dam Access Road (route to proposed Dam from Boonah-Beaudesert Road or Mount Lindesay Highway), to design, construct and commission dam access road (4.5km to 7.5km length) and associated works. Click for more details...

MIDDLE RIVER DAM
Renovations, Refurbishments etc. project of Civil Engineering (Dams) project at Middle River north west of, Parndana, SA 5220. Construction services for rehabilitation work. Services include: earthworks, pipeworks (various materials), concrete (pre-cast & insitu), cathodic protection works & specialist concrete works such as concrete repair injection & grouting. Click for more details...

KEEPIT DAM UPGRADE - WORK PACKAGE 1
Civil Engineering (Dams) project for New development. Design of 600 metres of fuse plug spillways, 3 saddle dams & ancillary works Click for more details...

TANJANNERUP DAM
Civil Engineering (Dams) project at Tanjannerup Rd, approx 5 km east of townsite of, Nannup, WA 6275 of Downstream Outlet Works For Dam type of Renovations, Refurbishments etc. development. Works comprise upgrade to downstream outlet works at Tanjannerup Dam. Click for more details...

FITZGERALD EMERGENCY WATER SUPPLY DAM
Fitzgerald Emergency Water Supply Dam is currently at the Tenders & Building stage, valued at about $ 100000 it is Works comprise construction of Fitzgerald emergency water supply dam. Click for more details...

SCA BLUE MOUNTAINS STORAGES
Water Storages - Maintenance project at Cascade Dams Katoomba Greaves Creek Dam Medlow Bath Woodford Dam Woodford & Fish River Pipeline, Leura, NSW 2780 in the Civil Engineering (Dams). Single, long term contract for the provision of grounds, building & abutment & embankment maintenance services. Click for more details...

DRY CREEK - KINGFISHER RESERVE WETLANDS
Wetlands For Dry Creek Area New project In The Tea Tree Gully Council Area. Construct wetlands for Dry Creek area of Kingfisher Reserve. Click for more details...

MAYFIELD TERRACE STORMWATER DETENTION WETLANDS
New project of Civil Engineering (Dams) project at Lot 101 Mayfield Tce (Vol 5448 Fol 166), Victor Harbor, SA 5211. Construction stormwater detention wetlands. Click for more details...

WASTE TREATMENT PLANT WINTER STORAGE DAM
New project of Civil Engineering (Dams) project at Carrolls Ln, Shepherds Flat, VIC 3461. Buildings and works for a utility installation (waste treatment plant winter storage dam)on public use zone land covered by an environmental significance overlay. Click for more details...

GLENNIES CREEK DAM
Glennies Creek Dam is currently at the Early Planning stage, valued at about $ 9400000 it is Proposed major upgrade of existing dam. Click for more details...

NORSEMAN TIN DAM - ROOF & FENCING WORKS
Civil Engineering (Dams) project for Renovations, Refurbishments etc. development. Works to comprise of removal of dam roofing & repairs to surrounding fencing at Norseman Tin Dam. Click for more details...

QUEENSLAND ALUMINA RED MUD DAM REDEVELOPMENT
Dam/Pipeline/Roadworks/Processing Plant project at ., Boyne Island, QLD 4680 in the Civil Engineering (Dams). Containment walls, processing plant, roads & pipes. Click for more details...

WUNDOWIE RECREATIONAL GROUNDS WATER STORAGE UPGRADE
Currently at the Construction stage In Northam is a project estimated to be $ 100000. This project Works include refurbishment of current dam for Wundowie Recreational Grounds water storage upgrade. Click for more details...

DALRYMPLE BAY COAL TERMINAL EXPANSION - SITE DAMS
Civil Engineering (Dams) project In The Mackay Regional Council Area of Site Dams - Construction type. To construct two dams. Click for more details...

ALBANY TREATED WASTEWATER STORAGE DAM 2
New project of Civil Engineering (Dams) project at Timewell Rd, Albany, WA 6330. Works for construction of Albany Treated Wastewater Storage Dam 2 comprises: construction of earthfill embankment dam of approx 10 m in height with 4 m wide vehicular access road at crest of dam with embankments slopes of 1V:3H upstream & 1V:2:5H downstream. Dam also includes central clay core, vertical sand filter on downstream side, blanket sand filter & rock toe; compacted upstream clay blanket & clay liner with gravel cover layer to be constructed covering entire reservoir basin; small spillway drop structure on upper ridge of left abutment that allows flow into existing dam reservoir; construction of outlet works comprising floating offtake arrangement & reinforced concrete encased DN600 MSCL pipe installed through foundations underneath embankment; extension of new inlet works consisting of v-shaped 1.5 m wide HDPE lined open channel, approx 370 m in length with rockfill lining at end of channel upstream of floating offtake outlet works; construction of access road on dam crest; dam instrumentation - v-notch weir, water level measurement & installation of piezometers; minor realignment of existing dam embankment at top end of right abutment; concrete lined spillway down right abutment of existing dam TWSD 1; site restoration & rehabilitation of disturbed areas. Click for more details...

MUCHEA MULTI SPECIES LIVESTOCK CENTRE
Civil Engineering (Dams) New project at Muchea Rd East, Muchea, WA 6501. This type is Forward Works Package with State ownership. Construction of 1 km access road, drainage basin and dam. Click for more details...

WELLINGTON DAM REMEDIAL WORKS - COLLIE RIVER
Dam - Remedial Works project at Located on Collie River, approx 170km s/se of Perth, Burekup, WA 6227 in the Civil Engineering (Dams). Wellington Dam is 34m high gravity structure. Works comprise of demolition works, construction of new bridge structure, installation of post-tensioned ground anchors & other ancillary works. A series of high-tensile steel cables would be installed vertically through the wall into the bedrock below to enhance the dam's stability. An operations bridge will be built along the crest of the dam to provide access to install the steel cables & enable future maintenance & monitoring. Click for more details...

SA WATER CORPORATION - DAMS ENGINEERING/RELATED SERVICES (PANEL CONTRACT)
Civil Engineering (Dams) project at Within, South Australia, SA 5999 of Panel Contract For Dam Engineering/Related Services type of New development. Provision of dams engineering & related services (panel contract). Click for more details...

SPLIT ROCK DAM
Split Rock Dam is currently at the Construction stage, valued at about $ 5637000 it is Construction of the Split Rock Dam Stage 1 safety upgrade - Parapet wall crest raising Click for more details...

TORRENS LAKE WEIR CONTROL SYSTEM & SCADA UPGRADE
Civil Engineering (Dams) project In The Adelaide Council Area of Weir Control System/Scada - Upgrade type. Design & construction of control system & SCADA upgrade to replace the whole or components of the Torrens lake Weir Control System. Works include: undertake a risk assessment of all the possible causes of a control system disabling fault resulting in the malfunction of Torrens Lake Weir during normal operating conditions & major & minor flood events; proposed appropriate methods & equipment (including possible duplication) for the Weir control system to reliably open & close the Weir gates in response to the water level in Torrens Lake & minimise the risk of malfunction resulting in water loss or overtoppping; installation of appropriate equipment to reliably control the operation of the Torrens lake Weir gates during normal operating conditions & major & minor flood events. Click for more details...

AWOONGA DAM
Civil Engineering (Dams) project In The Gladstone Regional Council Area of State ownership. Removal and refurbishment of 6 No DN 1500 butterfly valves from the outlet tower, DN 1400, DN 900 and DN 1900 sleeve valve from the toe of the dam and other minor valves and associated infrastructure, including hydraulic equipment used to operate valves. Click for more details...

SCRIVENER DAM
Currently at the Construction stage In Act is a project estimated to be $ 15000000. This project Upgrade of Scrivener Dam. Remediation of the remaining 4 gates (1,2,3 & 5). The flap gates are opened in flood to regulate the water level at Lake Burley Griffin Click for more details...

LEACHATE DAM - ALBURY LANDFILL
Civil Engineering (Dams) project at 565 Mudge St, Hamilton Valley, NSW 2641 for New. Construction of a Leachate Dam. Click for more details...

CRAIG ROAD DAM
A project in the VIC Within Casey. Development of a dam. Click for more details...

COPETON DAM FUSEPLUG SPILLWAY
State ownership Civil Engineering (Dams) project In The Inverell Council Area for New development. Copeton Dam upgrade works. The Consultant is required to fulfil 3 roles on site for the Copeton Dam Safety Upgrade Stage 1 contract site management services. The roles are: Principal?s Authorised Person?s Delegate (PAPD). Assistant Principal?s Authorised Person?s Delegate (Asst PAPD) & Administration Officer Click for more details...

SPLIT ROCK DAM
Civil Engineering (Dams) New project at on the Manilla River near, Tamworth, NSW 2340. This type is Consultancy For Contract Site Management Services - Upgrade with State ownership. The Consultant will be engaged to undertake Contract Site Management Services for the Split Rock Dam Stage 1 Safety upgrade works PID904213 to fulfill the role of Principals Authorised Person's Delegate (PAPD) Click for more details...

KILLARA GOLF CLUB
Golf Course/Dam/Bridge project at 556 Pacific Hwy, Killara, NSW 2071 In The Council Area Of Ku-Ring-Gai of Private. Proposed works include: new practice fairway, construction of 2 new holes (2nd & 4th holes), new par 3 spare hole & various hole modifications including redesign of greens, bunkers & minor fairway realignments. Construction of a new water storage dam in Bradfield paddock. Enlargement (by deepening) of Honeysuckle dam. Selected areas of tree removal, new cart paths. New steel bridge over Honeysuckle dam. Installation of new irrigation equipment Click for more details...

LOSTOCK DAM
Civil Engineering (Dams) New project at Patterson River, Maitland, NSW 2320. This type is Dam - Outlet Works with State ownership. Lostock dam - outlet works - replace asbestos cable duct. Scope of work includes: remove existing asbestos cable duct & replace with an appropriate enclosure system. The enclosure system will contain the existing electrical hydraulic & water services between the outlet works control building & the outlet valves. The existing duct is attached to a stairway between the 2 structures which is at height above the dam outlet water channel. Disconnect existing services & remove & dispose of the asbestos duct. A new enclosure system is to be installed that provides full mechanical & UV protection to all services installed within the enclosure. The electrical cables should be re-used, the hydraulic pipes may be modified using stainless steel pipe & the water pipes may be replaced. Click for more details...

SHIRE OF MERREDIN - DAM NO 4
A project in the WA Within Merredin. To include the construction of a lined dam, a pump house & associated mechanical & electrical equipment. Click for more details...

SHIRE OF MERREDIN - DAM NO 2
Civil Engineering (Dams) project at West of the townsite of, Merredin, WA 6415 of Evaporation Control Device - Supply, Installation & Testing type of New development. To include the supply, installation & testing of evaporation control device at dam no 2. Click for more details...

MOUNT PLEASANT DETENTION BASIN DAM
Dam project at ., Launceston, TAS 7250 in the Civil Engineering (Dams). Removal of an existing farm dam, supply of fill and construction of a new stormwater detention basin dam, construction of precast inlet structure and outlet works. All works will be within private property. Click for more details...

DUMARESQ DAM
Civil Engineering (Dams) project at Dumaresq Dam Rd, Dumaresq, NSW 2350 of Consultancy For Investigation/Preliminary Design/Detailed Design/Documentation type of New development. Upgrade of Dumasresq Dam Click for more details...

BURNS LANE & BLACKHILL ROAD DAM & TROTTING TRACK
New project of Civil Engineering (Dams) project at 1-95 Burns Ln & 188-264 Blackhill Rd, Toolern Vale, VIC 3337. Construction of a dam and horse trotting track. Click for more details...

ELCHO BASIN CONSTRUCTION STAGE 1
Civil Engineering (Dams) project at Btwn McManus Rd & Broderick Rd, Lara, VIC 3212 of Basin Construction type of New development. Major earthworks which include the construction of a Drainage Detention Basin between McManus Road and Broderick Road, Lara. The works include the 1st stage construction of a major stormwater runoff treatment facility that comprises construction of sedimentation basins. The 1st stage work comprises the sedimentation basin which is the entry to the future Elcho basin/wetland system and any extension of these works or associated structures as directed by the Superintendent. Excavated material from the basin will be transported to industrial allotments adjacent to this site. Exported clay will be placed and compacted under Level 1 Inspection & Testing (refer to Clause 4.7 in Specification T1300043) on the industrial allotments to finished surface levels as detailed in the drawings. The works under this contract, as described in the drawings and specified herein, include but are not limited to: broad-scale clay extraction operations within the site; excavating, shaping and trimming the basin and part of the inlet & outlet channels; loading approved excavated clay material and transporting to the external allotment; soil treatment (clay and topsoil) and import of non-dispersive topsoil all as required and/or directed; construct compacted clay liner in the basin as required; finished surface protection works including topsoiling and grass cover of all exposed clay areas; engineered fill to 98% standard compaction on industrial allotments - Lots 1 & 2; Broderick Road channel and piped drain outlet assembly/works; and ancillary basin and external allotment works. Click for more details...

BURRENDONG DAM SAFETY UPGRADE - SADDLE DAM A SPILLWAY
A project in the NSW Within Wellington. Installation of temporary fencing around the work area. Design and construction of the access/haul roads to the Works area, and other temporary Works required to undertake the Works and to comply with WHS, environmental and quality requirements. Clearing, grubbing and stripping topsoil from the Works area. Excavation of the auxiliary spillway channel. This will involve excavation of overburden soils, extremely weathered to slightly weathered meta-siltstones and meta-sandstones by mechanical means and blasting (if required). Hauling and depositing excavated material to nearby stockpiles and spoil disposal areas, including formation and final shaping of the spoil disposal areas. Stabilisation of the auxiliary spillway channel cut slopes including rock bolting and shotcrete where required. Placement of geotextile and rockfill on the spillway floor in the location of an extremely weathered shear zone to provide additional erosion protection. Design and construction of permanent unsealed access roads for long-term inspection and maintenance of the auxiliary spillway and other ancillary items. Provision of environmental control measures during construction. Provision of environmental offsets in accordance with the REF. Supply and installation of permanent security fencing and signage. Provision of permanent site drainage, safety bunds, site cleanup, landscaping, revegetation and disestablishment of all temporary facilities, and removal of construction debris/waste on completion. Click for more details...

GLADSTONE PRAWN FARM REHABILITATION
Civil Engineering (Dams) project at Gladstone Benaraby Prawn Farm, Gladstone, QLD 4680 of Prawn Farm - Rehabilitation type of New development. Construction of Stage 2 rehabilitation of the abandoned Gladstone Benaraby Prawn Farm, Gladstone. Works to include pond water treatment, acid sulfate soil treatment, bulk earthworks & erosion & sediment control, end of remediation clean up & monitoring. Click for more details...

SHEPPARTON COMMUNITY FOOTBALL COMPLEX EARTHWORKS & DRAINAGE
Earthworks & Drainage project at Brauman St, Shepparton, VIC 3630 in the Civil Engineering (Dams). Earthworks & drainage works for the Community Football Complex (CFC) area of the Greater Shepparton Regional Sports Precinct. The works consist of earthworks over the entire CFC site, construction of stormwater drainage & retardation basin. Click for more details...

HAMILTON WATER TREATMENT PLANT BASIN NO 1 EMBANKMENT UPGRADE
Currently at the Construction stage In Southern Grampians is a project estimated to be $ 540000. This project Embankment upgrade works include the construction of an earth filled stabilising berm with filters & drainage, dismantling of an access bridge & existing overflow structure, construction of a new overflow structure, relining of the existing outlet pipe, & associated civil, drainage & pipe works at Hamilton Water Treatment Plant (WTP) Basin No 1. Click for more details...

SPYGLASS BEEF RESEARCH FACILITY MAYNE DAM RECONSTRUCTION
Civil Engineering (Dams) project at Spring Gully 110km North of, Charters Towers, QLD 4820 for New. Reconstruction of Mayne Dam at Spyglass Beef Research Facility. To include construction of access roads, design & construction of earth dam walls & two spillways. Click for more details...

TORRUMBARRY WEIR ELECTRICAL CUBICLES & SITE INSTALLATION WORKS
Civil Engineering (Dams) project In The Campaspe Council Area of Electrical Cubicles (6) - Supply, Test & Install type. Supply, test & install eight (8) electrical control cubicles, including PLCs & other equipment, used to control the river flow through six river flow control gates at the weir. Torrumbarry Weir is located at the Murray River 40 km north-east of Echuca. Click for more details...

DEEP CREEK DAM
New project of Civil Engineering (Dams) project at off Princes Hwy 10km South of, Batemans Bay, NSW 2536. Reinstate, repair & replace an existing bitumen access & other associated works located on the berm of the Deep Creek Dam wall. Click for more details...

TARWIN STREET DAM WALL
Civil Engineering (Dams) project In The Baw Baw Council Area of Dam Wall type. The works involve the supply of all necessary labour, plant, equipment, materials & expertise for the construction of a dam wall at the retardation basin in Tarwin Street, Warragul. Click for more details...

ETIWANDA SPURLINE BASIN
New project of Civil Engineering (Dams) project at Etiwanda Spurline Basin, Mildura, VIC 3500. Construction of Etiwanda Spurline to provide storage & further developments. Click for more details...

Copyright © CoreLogic. All rights reserved. Powered by Cordell Connect