BEAUTY POINT EFFLUENT RE-USE SCHEME
New project of Civil Engineering (Dams) project at West Arm Road, Beauty Point, TAS 7270. Construction of a 38 megalitre storage dam and associated pipework and fencing. Click for more details...

RAILTON EFFLUENT REUSE SCHEME
Native Plains Rd, Railton, TAS 7305 Has Railton Effluent Reuse Scheme currently at Construction stage. Construction of a 109 megalitre clay lined effluent storage dam. Click for more details...

LAKE LLEWELLYN DAM
Civil Engineering (Dams) project at North West Tasmania, Sisters Beach, TAS 7321 of Spillway Upgrade type of New development. Construction of a reinforced concrete spillway and associated earthworks. The upgrade requirement includes a 37 metre long x 15 metre (maximum) wide reinforced concrete side entry spillway and associated earthworks. Click for more details...

LAUNCESTON FLOOD PROTECTION SCHEME
Earthen Flood Levee - Stage 1 - Scottsdale Levee project at Bounded by North Esk River and Tamar River, Invermay, TAS 7248 in the Civil Engineering (Dams). Construction of an earthen flood levee. Click for more details...

NORTH EAST DAMS
North East Dams is currently at the Planning stage, valued at about $ 75000000 it is The new dam will have a volume of 70,000 ML and will benefit the communities of Scottsdale, Bridport and Ringarooma with an irrigable area of 40,000 ha. Click for more details...

HEADQUARTERS ROAD DAM
Civil Engineering (Dams) project at Headquarters Road, Scottsdale, TAS 7260 of Dam type of New development. The new dam will deliver 2,000 ML p.a. to the community of Scottsdale with an irrigable area of 1,800 ha. Click for more details...

UPPER SOUTH ESK DAM
Civil Engineering (Dams) project In The Northern Midlands Council Area of State ownership. The new dam will deliver 10,000 ML p.a. to the communities of Llewellyn, Conara, Cleveland, Powranna and Claredon with an irrigable area of 10,000 ha. Click for more details...

MEADSTONE DAM
From ROYAL GEORGE to, Cleveland, TAS 7211 Has Meadstone Dam currently at Planning stage. The new dam will deliver 30,000 ML to the communities of Royal George, Apslawn, Cranbrook, Llewellyn, Conara and Cleveland with an irrigable area of 8,000 ha. Click for more details...

SCOTTSDALE LEVEE
Civil Engineering (Dams) project at ., Launceston, TAS 7250 of Consultants type of New development. Consultants for the Scottsdale Levee geotechnical investigation, t-bar testing and associated works. Geotechnical studies carried out to date have identified the need for additional, sensitive testing to be undertaken in order to assess the stability of the soils in the Inveresk Precinct for levee remedial works assessment. Click for more details...

MOUNT PLEASANT DETENTION BASIN DAM
Dam project at ., Launceston, TAS 7250 in the Civil Engineering (Dams). Removal of an existing farm dam, supply of fill and construction of a new stormwater detention basin dam, construction of precast inlet structure and outlet works. All works will be within private property. Click for more details...

TREVALLYN DAM VALVE REPLACEMENT
Civil Engineering (Dams) project In The Meander Valley Council Area of State ownership. Replacement of dam valve and track works for vehicle access and construction of a car park. Click for more details...

SWAN VALLEY IRRIGATION SCHEME DAM
State ownership Civil Engineering (Dams) project In The Glamorgan-Spring Bay Council Area for New development. Construction of a 2,000 ML scheme to pump water from the Swan River in periods of higher river flows & store it in a dam adjacent to the river, close to the township of Cranbrook on the Melrose property. Click for more details...

THE DUCK IRRIGATION SCHEME/MILL CREEK DAM
Currently at the Construction stage In Circular Head is a project estimated to be $ 9000000. This project Design & construction of the Duck Irrigation Scheme. It is a 5,200 megalitre (ML) scheme proposed to be built in the states north-west centered around the municipality of Smithton. The scheme will extract water from the Duck River and Mill Creek during the winter period and store in the proposed Mill Creek Dam. This water will be distributed to scheme participants during the summer irrigation period via a 61 kilometer underground pipeline network, facilitated by two pump stations and utilizing a section of the Duck River. Click for more details...

ROMAINE DAM UPGRADE
A project in the TAS Within Burnie. Construction of the Romaine Dam Upgrade. Click for more details...