LIDDELL COAL COLLIERY - RESOURCE
Mine - Coal New project In The Singleton Council Area. Existing operation produces 4.5 Mtpa of Rom coal and the CHPP processes 700 tonnes per hour. A proposal has been approved to increase ROM coal production to 8 Mtpa. Associated development will comprise the construction of a new Coal Handling Plant, establishment of a new supplementary stockpile with capacity of 450,000 tonnes, alter the planned 1500 ML Dam 13B footprint, construct a bridge over the main Northern Railway to improve transport between existing coal pits, alter an access road to the CHPP, relocation of offices, workshop and storage area and an associated access road, and the construction of a desalination unit within the CHPP area for the treatment of mine water. Capital expenditure on the Washplant upgrade alone was approx $100 million. Click for more details...

BLAIR NICKEL MINE - RESOURCE
Operating Mine project at North of, Kambalda, WA 6442 In The Council Area Of Coolgardie of Private. Resource estimate is 109,000 tonnes of ore @ 5.19% Ni for 5,660 tonnes of contained nickel. Excavation of new decline to access the ore on the 460 level and below. Click for more details...

YARRANDALE ROAD INDUSTRIAL STORAGE
Local Govt ownership Mining - Support Facilities (Industrial buildings) project In The Dubbo Council Area for New development. Construction of an industrial shed for storage, preparation & manufacture of furniture. Click for more details...

CENTURY ZINC MINE
Buildings project at North west of, Mount Isa, QLD 4825 In The Council Area Of Mt Isa City of Private. Change-house, workshop, laboratory & administration. 36 week contract period. Click for more details...

RAVENSWOOD GOLD OPERATIONS - MOUNT WRIGHT - GOLD RESOURCE
Mining - Support Facilities (Industrial buildings) project for New development. Design work and equipment procurement is to commence shortly with major site works scheduled to start July 2006. The project is expect to cost $77 million with $28.8 million for underground facilities and equipment, $21.7 million for surface facilities and equipment and $26.4 million for capitalised mine development. During the first two years $42 million will be spent on development. Production cost is expected to be $34 per tonne of ore processed. The project will develop in two stages with phase one involving decline development and exploration access for the drill program, while providing a platform for production from the upper levels of the resource. Phase two will extract the remaining resources identified in phase one. The feasibility study completed a comprehensive metallurgical test work, processing strategy using the existing plant, options study on different mining methods, environmental issues connected to tailing storage have been addressed. Underground mining is the method of mining. The Mount Wright prospect is located 10 km northwest of the Sarsfield open pit and is proposed to be developed as a decline accessed underground mine. Mining is to be by open stoping with 50 metre sub-levels at an extraction rate of 1 million tonnes per annum. An extensive underground DC drilling program will be undertaken in conjunction with mine development to upgrade the resource status. Inferred and indicated resource estimate is 1,054,722 ounces of gold. An eight year production life to 2015 and production rate of 1 MTPA. Click for more details...

GROSVENOR COAL PROJECT
via, Moranbah, QLD 4744 Has Grosvenor Coal Project currently at Construction stage. Underground longwall mining at a rate of 7 million tonnes a year (Mtpa) for 26 years. Run-of-mine (ROM) coal to be transported by new conveyor to the adjacent Moranbah North Mine from where 5 Mtpa of product export coking coal to be transported by existing rail facilities to the Abbot Point Coal Terminal. Mining infrastructure to include a new portal entrance to the underground mine access drift, ventilation shafts, water management infrastructure, gas drainage boreholes, underground communication cables, services & boreholes for supply of materials from the surface. Associated surface infrastructure to include administration & warehouse buildings, workshop & vehicle servicing facilities, bath house & employee facilities. Also required at Moranbah North new ROM & product stockpiles at its Coal Handling & Preparation Plant (CHPP) & expansion of the Co-disposal Area (CDA) to accommodate the increase tailings & coarse rejects. Possible relocation of a section of the Blair Athol rail line in the event of subsidence. Click for more details...

FLINDERS RANGES PROJECT - BELTANA - ZINC RESOURCE
Mining - Support Facilities (Industrial buildings) project In The Far North Council Area of Resource - Zinc type. Mining operation will be 150-180,000 tonnes per annum. Indicated-Inferred resource is 941,000 tonnes @ 30.6% zinc for 300,000 tonnes of zinc. Beltana deposit resource is 365,200 tonnes @ 31.2% zinc for 57,400 tonnes of zinc. The Beltana deposit will be mined first with the existing pit to be deepened from 65 metres by another 30 metres. Click for more details...

BATCHELOR MAGNESIUM PROJECT
Infrastructure project at Rum Jungle district 85 km south of, Darwin, NT 0800 in the Mining - Support Facilities (Industrial buildings). Following completion of the Stage one Feasibility study, locations were selected for each of the facilities necessary for development of the Project. All available technical data relating to each site was compiled and reviewed. Some further exploration drilling was carried out. Based on this review it has been concluded that the sites seem suitable for the assigned purpose. Click for more details...

PENRICE SODA OPERATIONS
Shed - Construction project at Via, Osborne, SA 5017 in the Mining - Support Facilities (Industrial buildings). 63 metres by 73 metres. Click for more details...

KOGAN CREEK POWER PROJECT - ELECTRICAL INSTALLATION/WORKSHOP
South of, Brigalow, QLD 4412 Has Kogan Creek Power Project - Electrical Installation/Workshop currently at Construction stage. Erection of 1 Siemens Steam Turbine, 1 Siemens Generator THDF 125/67, Condenser, Tanks, Pumps, Compressors, Assembly of Workshop and Store, Electrical and I & C installation Click for more details...

MILLENNIUM MORANBAH COAL PROJECT - MINING CONTRACT
New project of Mining - Support Facilities (Industrial buildings) project at North of Poitrel via, Moranbah, QLD 4744. Includes infrastructure, administration facilities, workshops etc. Click for more details...

BOOTU CREEK MANGANESE PROJECT - INFRASTRUCTURE
Infrastructure project at 130 km north of, Tennant Creek, NT 0860 in the Mining - Support Facilities (Industrial buildings). 75 person accommodation village, office, stores, laboratory, heavy vehicle workshop, diesel fuelled power generating plant. Click for more details...

KOOLYANOBBING IRON ORE OPERATIONS - EXPANSION - SHED
Private ownership Mining - Support Facilities (Industrial buildings) project In The Esperance Council Area for New development. Includes an additional 300,000 tonne capacity shed at the Port of Esperance. Click for more details...

ENSHAM CENTRAL EXPANSION PROJECT - DRAGLINE ASSEMBLY WORKSHOP
Mining - Support Facilities (Industrial buildings) project at (Lot 34 RP 864576) Duckponds Road, Emerald, QLD 4720 of Dragline Assembly Workshop type of New development. Construction comprises an assembly workshop (450 sqm), abultion block, crib room, office, 8 metre wide sealed road and 2 buses & 15 vehicle parking spaces. Click for more details...

EMILY ANN INFRASTRUCTURE EXPANSION
Infrastructure Expansion project at 140 kM West of, Norseman, WA 6443 In The Council Area Of Dundas of Private. Expansion of existing infrastructure at Maggie Hays comprises upgrading the processing plant from 0.5 mtpa of ore to 1.5 mtpa. Downstream facilities of flotation, concrete handling, tails disposal, reagent mixing and process water systems would also be expanded. Other facilities such as the laydown area, both explosive magazines and mixing facility, the ROM pad, waste rock dump, fuel storage (2 x 55,000 litre tanks) will be expanded. Expansion of existing workshop buildings and administration areas will be done as a needs basis. The power plant will Increase from 7 MW to 10 MW and the construction of a new 4 MW plant at the Maggie Hays mine site. Two new process water ponds and a merging lane at the corner of Hyden Norseman Road and the Maggie Hays access road. Click for more details...

IRON ORE RAPID GROWTH PROJECT 3 - PORT INFRASTRUCTURE
At, Finucane Island, WA 6721 Has Iron Ore Rapid Growth Project 3 - Port Infrastructure currently at Construction stage. Development comprises construction a new single stockyard row in area S, the Eastern Yard including a new stacker and new reclaimer. Constructing a new dedicated Return Screened Fines stockpile adjacent to Car Dumper 4 including new stacker and new reclaimer. Joining the existing Berths C & D together to allow existing shiploaders SLO3 and SLO4 to access either berth. Modifications to the long travel of shiploaders SLO3 and SLO4 so they can travel and shipload on Berth C and D. Upgrading and rebuilding the existing Berth C to accommodate shiploader SLO4 and 250,000 DWT vessels, modify the exisitng control system to suit the new operating regime, improve dust control measures, upgrade electrical infrastructure to suit the proposed development, upgrade the exisiting general infrastructure including upgrading a warhouse building , upgrading roads and constructing a new water recovery plant. The existing existing environmental berm will be extend to provide a visual buffer to the town of Port Hedland on the other side of the harbour from the new eastern stockyard. Construction of temporary lay down areas and buildings for the contractors and temporary construction offices for BHP and EPCM staff. Borrow pits will be developed for the taking of material for construction purposes. A new 66 Kv power line will also be constructed and installed. Click for more details...

MOUNT GIBSON IRON ORE MINE & INFRASTRUCTURE PROJECT - STORAGE SHED & FACILITIES
Mining - Support Facilities (Industrial buildings) project In The City Of Greater Geraldton Council Area of Storage Shed/Associated Facilities type. Construction of dedicated berth, storage shed and shiploading facilities to handle 130,000 tonnes of iron ore. Facilities will include hoppers, conveyors, storage tanks, clarifier, return water tank and pumps, HV cables, power transformer, MCC and switch rooms. A filter plant will be constructed to dry the slurry. Concrete floor, structural steel and cladding. Click for more details...

IRON ORE RAPID GROWTH 3 PROJECT - AREA C - ANFO STORAGE FACILITY
Great Northern Highway, Newman, WA 6753 Has Iron Ore Rapid Growth 3 Project - Area C - Anfo Storage Facility currently at Construction stage. Ammonium Nitrate and Fuel Oil facility. The building will be built into the side of a hill and will be 3 levels and 27.1 metres high. The middle level will be 49.2 metres long and 26.2 metres wide. Click for more details...

CENTRAL NORSEMAN GOLD OPERATIONS - RESOURCE
Resource -Gold project at 30 Km North of, Norseman, WA 6443 In The Council Area Of Dundas of Private. Norseman gold operation comprises two underground mines, Harlequin, Bullen, various open pits and the Phoenix mill treatment plant. The Davyhurst gold operation has been sold to Monarch Resources. Mining is to continue at all operations and various infrastructure projects will be undertaken. At Harlequin the mine ventilation system and the surface workshop will be upgraded in preparation for long term mining at the Harlequin decline. The Phoenix mill treatment plant will undergo maintenance of the crusher, ball and SAG mill and the installation of new ore feeders. A new tailings storage facility designed to provide 10 years storage will be developed. A major upgrade to the power distribution network will be undertaken. Lastly the single person quarters at Norseman will be upgraded and refurbished. Click for more details...

INDEE GOLD PROJECT - ACCOMODATION/ADMINISTRATION/STORAGE FACILITY
80 Km South west of, Port Hedland, WA 6721 Has Indee Gold Project - Accomodation/Administration/Storage Facility currently at Tenders & Building stage. Construction comprises an accommodation building for 40 persons, ablution block, kitchen/mess facilities, administration building and an equipment storage facility. Click for more details...

KING ISLAND SCHEELITE MINE REDEVELOPMENT PROJECT STAGE 1 - BUILDING CONTRACTORS COMPOUND
Private ownership Mining - Support Facilities (Industrial buildings) project In The King Island Council Area for New development. For the provision of accommodation buildings, bath houses & crib rooms etc for Building Contractors Compound. Click for more details...

KING ISLAND SCHEELITE MINE REDEVELOPMENT PROJECT STAGE 1 - MINING CONTRACTORS COMPOUND
New project of Mining - Support Facilities (Industrial buildings) project at Near, Grassy, TAS 7256. For the provision of mining contractors compound. Click for more details...

MURRAY BASIN STAGE 2 - KWR MINERAL SANDS PROJECT - WORKSHOP
Mining - Support Facilities (Industrial buildings) project at 28 km east of, Ouyen, VIC 3490 of Workshop type of New development. For the construction of a workshop. Click for more details...

NULLAGINE GOLD PROJECT - ACCOMMODATION VILLAGE/ANCILLARY FACILITIES
Accommodation Village/Ancillary Facilities project at 10 km South of, Nullagine, WA 6758 In The Council Area Of East Pilbara of Private. A 120 person accommodation village and ancillary buildings to be constructed. Living units will be both two and four room transportable accommodation units with their own ensuite shower and toilet. Ancillary buildings and facilities to be constructed comprise a dry mess and kitchen including refrigeration and dry storage area, outdoor barbeque area, wet mess inclusive of a small retail facility, laundry facility, recreational room including TV, tea & coffee making facilities, gymnasium, sports court and equipment, resident phone facilities, 5 or 6 person transportable units for short term residents, additional ablutions for recreational areas and short term residential accommodation, LPG facility to provide gas for cooking and hot water systems, truck delivery and turn around area, parking area, transportable site administration office with capacity for approximately 12 offices and first aid facilities, small onsite laboratory to process treatment plant samples, workshop building housing electrical, mechanical and fabrication works, maintenance office and crib room, ablutions to service the site facilities. An onsite diesel power station will be installed by a contractor which will supply the power for the camp. Water will be pumped from bores and stored in water tanks and treated by osmosis processing facility. Sewage from the camp will be pumped into septic tanks into a sewage treatment plant and sewage from the processing plant will be pumped into sceptic tanks and then pumped to leach drains. Click for more details...

HOPE DOWNS IRON ORE PROJECT - PROCESSING PLANT
75 Km Northwest of, Newman, WA 6753 Has Hope Downs Iron Ore Project - Processing Plant currently at Construction stage. A crush and screen process plant. The plant will initially process 22 Mta of dry iron ore with expansion later on to process 30 Mta of dry iron ore. The process plant will comprise a primary crusher in a processing circuit that incorporates screens that will seperate the oversized ore. The primary ore will then be crushed a second time and fed to seperate lump and fine products. These will be stockpiled for train loading by conveyor belts and travelling luffing stackers. Stockpiled products will be reclaimed by a rail mounted bucket wheel reclaimer. It will then be conveyed to a train loading facility for transport by rail to Dampier port. Click for more details...

BOGGABRI COAL OPERATIONS EXPANSION
Mining - Support Facilities (Industrial buildings) project at 17km northeast of, Boggabri, NSW 2382 of Operating Mine - Expansion - Stage 2 type of New development. Expansion of existing Boggarbri open cut coal operations. Upgrade of the coal handling & preparation plant (CHPP) to increase throughput from 1.5 million tonnes per annum (Mtpa) to 2.5Mtpa in 2011 & 4.3Mtpa in 2013. Installation of a new 132kV switchyard/sub-station/overhead power lines. Installation of modular buildings for offices & bathhouse extension. Construction of a light vehicle workshop, a heavy vehicle workshop with warehouse & a car park. 150 construciton jobs expected as well as 500 operational jobs. Click for more details...

IRON ORE RAPID GROWTH 4 PROJECT - MOUNT WHALEBACK RAIL LOOP MODIFICATIONS
Rail Loop Modifications New project In The East Pilbara Council Area. Rail Loop Modifications. The new Newman Hub layout covers modifications at the yard entry, modifications for the new train load-out, modifications for the new car dumper and installation of facility for loco servicing. Click for more details...

ROCGLEN COAL PROJECT - WORKSHOP
Mining - Support Facilities (Industrial buildings) project for New development. For the provision of a workshop. Click for more details...

ABYDOS IRON ORE PROJECT
Operating Mine - Iron Ore project at 85km West of, Marble Bar, WA 6760 in the Mining - Support Facilities (Industrial buildings). Upgraded resource estimate of 22.2Mt @ 56.7% Fe. Project will consist of two open pits which will be mined using conventional drill and blast, load and haul techniques. Pit dewatering will not be required. Ore processing and transport. Additional infrastructure will include the administration area, haul road, Abydos Link road, access tracks, explosives magazines, water bores and associated reticulation and borrow pits. Re-fuelling and fuel storage areas, workshops, washdown areas and laydown areas will be located within the administration area and the ROM area. All personnel and staff will be housed at the Abydos accommodation village. Click for more details...

DRAYTON COAL OPERATIONS EXTENSION PROJECT
Mining - Support Facilities (Industrial buildings) project for New development. Mining of an additional resource of 30 million tonnes from the Greta Coal Measures (targeting the Rowan formation) at a rate of up to 8 Mtpa to extend the mine life to 2017. The extension of mining will predominantly progress to the South of current operations; however, additional areas within the North and East of the project area are also proposed to be mined. The project will require some additional items of equipment to accommodate an increased rate of production such as: 1 x excavator, 3 x track dozers, 5 x 280 tonne rear dump trucks, 1 x additional drill, grader and watercart, plus other minor ancillary equipment. The existing Coal Handling Plant (CHP) & associated stockpile reclamation system will be upgraded in order to align the facilities with the proposed increase in annual production. A new 80 000 tonnes product coal stockpile & a 40 000 tonne domestic product coal stockpile are proposed to further assist production efficiencies. Minor changes to Drayton's water management system are also proposed to maximise water management & use at the mine. Drayton will continue to utilise dragline, excavators, loaders and a fleet of trucks to both uncover the coal & transport it to on-site processing and load-out facilities. Blasting will continue to be required to assist with overburden & coal extraction. Drayton will continue to utilise existing infrastructure such as administration offices, workshops, parking facilities, conveyors, coal handling facilities and coal stockpiles. Click for more details...

BERRIMAH ROAD WAREHOUSE
Mining - Support Facilities (Industrial buildings) project In The Darwin City Council Area of Private ownership. Construction of a warehouse to include railway track running into warehouse. Parking for 6 cars. Associated landscaping. Click for more details...

MURRAY BASIN STAGE 2 MINERAL SANDS PROJECT - CIVIL WORKS & BULK EARTHWORKS
Murray Basin Stage 2 Mineral Sands Project - Civil Works & Bulk Earthworks is currently at the Construction stage, valued at about $ 5000000 it is For the provision of site-wide civil works & bulk earthworks. Click for more details...

WORSLEY ALUMINA EFFICIENCY & GROWTH PROJECT - HEAVY EQUIPMENT WORKSHOP & REFUELING
Mining - Support Facilities (Industrial buildings) project at 15 Km South east of, Collie, WA 6225 for New. For the supply of a heavy equipment workshop and refueling. Click for more details...

RG TANNA COAL TERMINAL BUILDING SERVICES WORKSHOP CONVERSION
., Gladstone, QLD 4680 Has Rg Tanna Coal Terminal Building Services Workshop Conversion currently at Construction stage. Construction of concrete footings & slab, underground services installation and asphalting the compound. Click for more details...

PANNAWONICA ACCOMMODATION & FACILITIES UPGRADE
Mining - Support Facilities (Industrial buildings) Renovations, Refurbishments etc. project at at, Pannawonica, WA 6716. This type is House Refurbishment/Office Refurbishment/Service Station/Workshop with Private ownership. Refurbishment of 233 houses. Upgrade & refurbishment of 19 existing commercial & infrastructure buildings. Construction also of a new service station & light vehicle workshop within the town. Click for more details...

PECULIAR KNOB IRON ORE PROJECT - TRANSHIPMENT STORAGE PORT FACILITY
At Berth 7, Port Pirie, SA 5540 Has Peculiar Knob Iron Ore Project - Transhipment Storage Port Facility currently at Construction stage. Contract for the design, procurement, construction & commissioning of an ore receival, storage & out-load facility at Port Pirie. To include train unloading, enclosed stockpiling in a storage shed (10,500 sqm), reclaiming/shiploading overland conveyors. Associated infrastructure/siteworks. Click for more details...

MOUNT ARTHUR COAL OPERATIONS EXPANSION RX1
Operating Mine - Expn - Rx1 New project In The Muswellbrook Council Area. Increase of run-of-mine (ROM) capacity by 4million tonnes per annum (Mtpa) to reach 24Mtpa approx. 300 new full time jobs expected. Click for more details...

ANDERSON POINT PORT FACILITIES - BERTH 3
Mining - Support Facilities (Industrial buildings) New project at Anderson Point, Port Hedland, WA 6721. This type is Port Facilities with Private ownership. The expansion will provide an additional 400m of wharf superstructure, 7 berthing dolphins, navigational aids and associated mechanical components. Click for more details...

MOUNT ARTHUR COAL OPERATIONS - TOOLS STORE/REPAIR BAYS/FIRST AID FACILITY
New project of Mining - Support Facilities (Industrial buildings) project at Denman Rd cnr Thomas Mitchell Dr 5km south of, Muswellbrook, NSW 2333. Contract for heavy vehicle tool store, light vehicle repair bays & first aid building. Click for more details...

PORT OF WHYALLA NORTH HARBOUR EXPANSION
Mining - Support Facilities (Industrial buildings) project In The Whyalla Council Area of Rail Facilities/Ship Loading type. Expansion of OneSteel's bulk export operations from 7 million tonnes per annum (Mtpa) approx to 12 Mtpa. To include construction of additional receival & storage facilities (rail infrastructure, tip pocket & storage sheds), ship loading facilities (conveyors, loader, berthing infrastructure) & expansion of transhipping operations. Click for more details...

DOYLES CREEK COAL PROJECT - MINE SAFETY & TRAINING SCHOOL
Mining - Support Facilities (Industrial buildings) project In The Singleton Council Area of Training School type. Establishment of a stand alone mine safety & training school for around 30 staff & 100 students a year. Construction of dedicated surface infrastructure to include a training room, on site accommodation modules for 8 visiting students & a large building to simulate underground mining conditions. Subsequent development to include a separate portal to the West Borehole Seam plus a network of first workings with 20m centre pillars at a rate of 400m a year (8,000 tpa) for more than 21 years. Click for more details...

BARALABA COAL OPERATIONS EXPANSION MIA
Mining - Support Facilities (Industrial buildings) project at near, Baralaba, QLD 4702 for New. Construction of all infrastructure associated with 20 year expansion for central, south & north pits. To include workshops, wash down area, administration, fuel tanks, water & sewerage treatment & other civil infrastructure. Concrete, structural steel, civil/earthworks, hydraulics & drainage, piling & electrical works. Click for more details...

GROSVENOR COAL PROJECT - MINE INFRASTRUCTURE AREA (MIA)
Support Buildings New project In The Isaac Regional Council Area. Construction of 7 separate buildings to provide support infrastructure. To include workshops, training room, administration buildings, amenities buildings & truck wash area. Concrete slab, steel portal frame, lightweight cladding, metal roof. Click for more details...

STORMONT JOINT VENTURE GOLD PROJECT
Mining - Support Facilities (Industrial buildings) New project at off Cradle Mountain Rd west of, Moina, TAS 7306. This type is Resource - Gold with Private ownership. Mining of 80,000t approx of the Stormont skarn-style gold-silver-bismuth deposit to 50m deep using conventional methods (drill & blast, excavators, articulated trucks). Ore to be trucked from a run-of-mine (RoM) stockpile over 130km for processing at BCD's Beaconsfield carbon-in-leach (CIL)/Bacox plant. An on-site mobile crusher may be required in addition to a hydraulic rock-breaker. Associated temporary waste rock dump, office, crib room/amenities, workshop (open ended shed with laydown area) & diesel fuel/oil storage system. Rehabilitation at completion of campaign. Expected employment for 14 people plus truck haulers. Click for more details...

DUGALD RIVER BASE METAL PROJECT - MINE INDUSTRIAL AREA & PLANT BUILDINGS
Private ownership Mining - Support Facilities (Industrial buildings) project In The Mt Isa City Council Area for New development. Construction of Plant & Industrial buildings. Click for more details...

ROY HILL IRON ORE PROJECT - NON-PROCESSING INFRASTRUCTURE
Mining - Support Facilities (Industrial buildings) project for New development. For the development of heavy and light vehicle workshops, a washdown facility, a boilermaker workshop, tyre change facility, lube farm administration buildings and a gatehouse. Click for more details...

ICHTHYS GAS PROJECT - ONSHORE - SITE FACILITIES BLD1 - CEILINGS PARTITIONS & LININGS SUBCONTRACT
Ceilings/Partitions/Linings - Supply & Install New project In The Darwin City Council Area. Supply, delivery & installation of all new ceilings, partitions & linings to buildings in the gatehouse, operations & warehouse/workshop zones. Click for more details...

BHP BILLITON MOOKA CAR REPAIR WORKSHOP
Bhp Billiton Mooka Car Repair Workshop is currently at the Construction stage, valued at about $ 30000000 it is Contract for the construction of a maintenance workshop & warehouse. To include process equipment installation as well as rail & infrastructure components including roads, track, signalling & communications electrical engineering. Water supply. Click for more details...

AMRUN (SOUTH OF EMBLEY) BAUXITE PROJECT - ACCOMMODATION VILLAGE (DESIGN & CONSTRUCTION)
New project of Mining - Support Facilities (Industrial buildings) project at 40km SW of, Weipa, QLD 4874. For the design & construction of an Accommodation Village (comprising approximately 1,200 accommodation rooms) & temporary on-site construction facilities at different locations external to the construction camp. Accommodation rooms will be supplied by Rio Tinto. The accommodation village & the temporary on-site construction facilities includes but is not limited to: Four (4) bed unsuited accommodation modules. People with Disabilities (PWD) two (2) bed unsuited accommodation modules. Maintenance & storage facilities. Office & administration facilities. Communications/data/television signal facility. Close Circuit Television (CCTV) monitoring facilities. Ablutions modules. Kitchen, dining & crib facilities. Entertainment facilities. Gymnasiums. Sporting facilities. Training/education centre. Laundry modules. Commercial laundry facility. First aid facility Power generation units & distribution panels with reticulation network. Area & general lighting requirements. Potable water treatment, storage & distribution networks. Waste water treatment systems & collection networks. Click for more details...

PILGANGOORA LITHIUM TANTALUM PROJECT - EPC CONTRACT
Mining - Support Facilities (Industrial buildings) project for New development. For the provision of engineering, procurements & construction for the Pilgangoora Lithium-Tantalum Project. Click for more details...