TASMAN PROJECT - MOUNT SUGARLOAF - SURFACE BUILDINGS
Tasman Project - Mount Sugarloaf - Surface Buildings is currently at the Construction stage, valued at about $ 1000000 it is Administration, worker amenities and stores, workshop, bunded fuel area. Click for more details...

TASMAN PROJECT - MOUNT SUGARLOAF - ACCESS ROAD
Mining - Infrastructure (Roads, Airstrips, Culverts, Retaining walls) project at 25 km west of, Newcastle, NSW 2300 for New. Construction of an access road . Click for more details...

TASMAN COAL PROJECT - MOUNT SUGARLOAF - ROAD UPGRADE (NO3)
Private ownership Mining - Infrastructure (Roads, Airstrips, Culverts, Retaining walls) project In The Newcastle Council Area for New development. Contract includes the round about on John Renshaw Drive. Click for more details...

LIDDELL COAL COLLIERY - RESOURCE
Mine - Coal New project In The Singleton Council Area. Existing operation produces 4.5 Mtpa of Rom coal and the CHPP processes 700 tonnes per hour. A proposal has been approved to increase ROM coal production to 8 Mtpa. Associated development will comprise the construction of a new Coal Handling Plant, establishment of a new supplementary stockpile with capacity of 450,000 tonnes, alter the planned 1500 ML Dam 13B footprint, construct a bridge over the main Northern Railway to improve transport between existing coal pits, alter an access road to the CHPP, relocation of offices, workshop and storage area and an associated access road, and the construction of a desalination unit within the CHPP area for the treatment of mine water. Capital expenditure on the Washplant upgrade alone was approx $100 million. Click for more details...

WEST CLIFF COLLIERY - OVERLAND CONVEYOR
Mining - Infrastructure (Conveyors, Stackers, Reclaimers, Materials handling) project at Wedderburn Rd, Appin, NSW 2560 for New. The Overland Conveyor was to be over the 3 kilometres of rough terrain between the Appin and West Cliff Mines. Click for more details...

TRITTON COPPER PROJECT - MURRAWOMBIE - MINING/EARTHWORKS CONTRACTS
Private ownership Mining - Infrastructure (Tailings, Dams, Water supply dams) project In The Bogan Council Area for New development. The construction of the box cut and the ROM development contract has been awarded to a local contractor ahead of full mobilisation to site later in February 2004 by the principal mining contractor. Click for more details...

ULAN COAL OPERATIONS - CONVEYORS
A project in the NSW Within Upper Hunter. The overland conveyor will be 2 km long and have 1400 t/h capacity. An underground truck conveyor will be upgraded and extended to a total length of 3.2 km. Also a new 4250 t/h stackout conveyor that is 1.6 km long will be installed and it will extend across an open cut haul road via culvert underpass to a 400,000 tonne overall hub stockpile. Click for more details...

MOUNT THORLEY WARKWORTH NO 1 COAL OPERATIONS
Mount Thorley Warkworth No 1 Coal Operations is currently at the Planning stage, valued at about $ 500000 it is Possible infrastructure requirements for extensions at Warkworth and possible integration with the adjacent Mount Thorley operations include the construction of a new conveyor for Warkworth Mine to Mount Thorley Operations and the Mount Thorley Coal Loader. Click for more details...

TASMAN PROJECT - MOUNT SUGARLOAF - SURFACE INFRASTRUCTURE - CONVEYORS
Mining - Infrastructure (Conveyors, Stackers, Reclaimers, Materials handling) project for New development. Includes conveyor and gantries and truckloader bins and bunded fuel tank area. Click for more details...

BAYSWATER POWER STATION
Bayswater Power Station is currently at the Construction stage, valued at about $ 500000 it is Includes testing and calibration of belt weighers at Bayswater and Liddel Power Stations as and when directed by the Principal for a two year period with an option for a further two years. Click for more details...

MOUNT OWEN COAL OPERATIONS - ROM RECEIVAL FACILITY
Private ownership Mining - Infrastructure (Roads, Airstrips, Culverts, Retaining walls) project In The Singleton Council Area for New development. Construction and operation of a ROM receival facility and haul roads to enable Mount Owen Mine to process ROM coal from Ravensworth East and Glendell mines. Click for more details...

AUSTAR COAL OPERATIONS EXPANSION
Mining - Infrastructure (Drifts, ventilator shafts, portals, shotcreting, declines) project In The Cessnock Council Area of Operating Mine - Extn - Stage 3 type. For longwall extraction from panels A1 & A2 using a new method of longwall mining known as longwall top caving. For the construction and operation of some additional surface infrastructure including a larger capacity ventilation fan, downcast shaft, substation, nitrogen injection plant, tube bundle shed, and diesel storage and dispatch system, and for the upgrading of some existing surface infrastructure including the water treatment plant, and the water reticulation and pumping system. Click for more details...

POONCARIE MINERAL SANDS PROJECT - GINKGO - RESOURCE
South of, Menindee, NSW 2879 Has Pooncarie Mineral Sands Project - Ginkgo - Resource currently at Construction stage. Resource at gingko as at mid 2004 Measured 162Mt ore 5,767 kt heavy minerals, Indicated 43Mt, 856kt heavy minerals. Road construction and a construction camp will be part of the development. Click for more details...

NORTHPARKES COPPER & GOLD OPERATIONS - E48 - RESOURCE
Private ownership Mining - Infrastructure (Tailings, Dams, Water supply dams) project In The Parkes Council Area for New development. Development comprises a new underground mine which is 2 km north of the existing E26 underground mine. Mining operations will be conducted by rock caving and ore will be hoisted via an existing shaft. A new above ground conveyor to the existing processing plant will be constructed. Two new tailings storage facilities will be constructed for the residue. A major engineering and construction component of the project will be to set up the underground crusher chamber. Resource estimate is 22,600,000 tonnes @ 1.15% copper and 0.46 g/t gold containing 260,000 tonnes of copper and 334,000 ounces of gold. Mine is expected to produce 5.5 Mtpa and extended to 2017. Click for more details...

BAAL BONE COLLIERY
Mining - Infrastructure (Conveyors, Stackers, Reclaimers, Materials handling) project for New development. Series of underground main-gate conveyors for longwall mining. Total length, approx 10 kms. Includes 3 systems. Click for more details...

ENDEAVOUR BASE METALS OPERATIONS - ELURA
Mining - Infrastructure (Concrete Batching Plants) project at 40 km north west of, Cobar, NSW 2835 for New. Cement paste fill plant is planned to extend the life of the mine, with some reduction in cost per tonne. The paste fill plant will use plant tailings, Cockle Creek Black smelter sand and cement to fill the mined voids, allowing additional ore to be extracted. Click for more details...

WEST WALLSEND COLLIERY - LACHLAN LEASES
West Wallsend Colliery - Lachlan Leases is currently at the Construction stage, valued at about $ 600000 it is Includes civil work, brick building, mechanical work erecting fan on site and associated steel work. Click for more details...

POONCARIE MINERAL SANDS - GINKGO
Mining - Infrastructure (Roads, Airstrips, Culverts, Retaining walls) project for New development. The haul road will be constructed in two stages. The first stage will involve formation of the road to driveable condition using local materials. Upon commencement of transportation of extracted material from the mine site, crushed gravel will be back loaded from Broken Hill to construct pavement. The second stage will involve sealing works and will commence approx two years after the start of mine operations. The second stage is estimated to cost $8 million. A bridge will also be constructed over the Great Darling Anabranch. Click for more details...

COORANBONG COLLIERY - MANDALONG MINE PROJECT
Mining - Infrastructure (Roads, Airstrips, Culverts, Retaining walls) project In The Lake Macquarie Council Area of Private ownership. Bridge across the Great Northern rail line and 3.5 km connection road to from a T-intersection with the existing Newstan haul road. Click for more details...

RAVENSWORTH/NARAMA COAL OPERATIONS - RAVENSWORTH EAST - RESOURCE
Approx 25 kms west of, Singleton, NSW 2330 Has Ravensworth/Narama Coal Operations - Ravensworth East - Resource currently at Construction stage. Current production of 2.0 million tonnes per annum will be increased to 2.5 million tonnes per annum. This will involve the dragline changing to a 7 day operation. Click for more details...

RAVENSWORTH/NARAMA COAL OPERATIONS - RAVENSWORTH WEST - RESOURCE
Currently at the Construction stage In Singleton is a project estimated to be $ 30000000. This project The mine will produce coal at the rate of 1.0 to 1.5 million tonnes per year for six years. Development cost of $30 million are expected. The operation will share existing infrastructure and equipment with Ravenswood East. The Ravensworth/Narama complex, located in the Hunter Valley in New South Wales, includes the Ravensworth East operation, Ravensworth West mining tenements and Coal and Allied's share of the Narama operation. Click for more details...

ARDLETHAN TIN OPERATIONS - PREPARATION/TREATMENT EQUIPMENT SUPPLY
A project in the NSW Within Coolamon. Includes mobile preparation & treatment equipment to be located close to the excavator. Ore is placed in a stockpile & a loader working continuously will feed the ore into the feeder-hopper of the scrubber-trommel. More water will be added so that the undersize can be pumped through in-line jigs which will be located within boom of the trommel unit. Some tin concentrate will be recovered in the in-line pressure jigs. The finer tin particles will be picked up in a spiral plant. Click for more details...

COWAL GOLD PROJECT
Site Office project at North west of, West Wyalong, NSW 2671 In The Council Area Of Bland of Private. Includes the construction/supply of buildings and services required to establish a site office at the Cowal Gold Project. Capabilities required include-supply/fabrication of steel industrial shed, construction management, transportable office accommodation, fencing, electrical, concrete works, sewerage plant and plumbing. Click for more details...

WEST CLIFF COLLIERY
Upgrade Conveyor Belts & Drive Units project at Wedderburn Rd, Appin, NSW 2560 In The Council Area Of Wollondilly of Private. The drive units involved are numbers 1.11, 1.5 & 1.9. Click for more details...

CAMDEN GAS PROJECT - STAGE 2 EXTENSION DAM
Private ownership Mining - Infrastructure (Tailings, Dams, Water supply dams) project In The Camden Council Area for New development. Construction of an earth dam at the MT1 gas well site. The footprint of the dam will be 60mx60m long and 60mx60m wide. The connection of 15 existing coal seam methane wells to the existing Stage 2 project. Click for more details...

ENDEAVOR BASE METAL OPERATIONS - COPPER RECOVERY CIRCUIT
Mining - Infrastructure (Conveyors, Stackers, Reclaimers, Materials handling) project at 40 Km North west of, Cobar, NSW 2835 for New. Copper recovery circuit is in design. Construction is expected to commence shortly. Testwork and detailed design has been completed. The circuit will treat the lead concentrate to extract a copper concentrate estimate to be 1000 tonnes of copper per annum. Click for more details...

LIDDELL POWER STATION - ANTIENE RAIL COAL UPLOADER
A project in the NSW Within Muswellbrook. Proposed development will include the construction of a new rail loop off the main northern rail line at Antiene, an uploading hopper and associated facilities. These facilities will include minor maintenance, fuel storage, and refuelling facilities. Also an overland conveyor to transport coal to the Bayswater power station will be constructed. The proposed development is designed to deliver 15 million tonnes of coal per year and is required to be operational by January 2007. Click for more details...

KOORAGANG COAL TERMINAL STAGE 3 EXPANSION WORKS
Mining - Infrastructure (Conveyors, Stackers, Reclaimers, Materials handling) New project at ., Kooragang, NSW 2304. This type is Coal Terminal Expansion with Private ownership. Expansion of terminal capacity from 89 mtpa to 102 mtpa. Development will involve a fourth stacking stream, a new stockpile pad, associated stacking conveyors and a new coal stacker. Click for more details...

NORTHPARKES MINES - TAILINGS DAM EARTHWORKS
New project of Mining - Infrastructure (Tailings, Dams, Water supply dams) project at Bogin Road Via, Parkes, NSW 2870. Project will involve the excavation, movement and placing of an estimated 600,000 cubic metres of clay and rock. Earthworks involving the raising the height of an existing tailings storage facility. Click for more details...

LIDDELL POWER STATION - CONVEYOR BELTS
Currently at the Construction stage In Muswellbrook is a project estimated to be $ 400000. This project Development comprises the replacement of conveyor belts at Liddell Power Station, as and when directed by the Principal for a two (2) year period from the date of the awarding of Macquarie Generation's Contract. The work includes the removal, overhaul and installation of each conveyor's head and tail end belt cleaning systems. Tenderers are to demonstrate in their tender a working knowledge of the requirements of the Specification gained through experience with and knowledge of the plant described or similar plant. Click for more details...

BENGALLA COAL OPERATIONS - ROM HOPPER RELOCATION CONSULTANCY
Mining - Infrastructure (Conveyors, Stackers, Reclaimers, Materials handling) project at 4 km west of, Muswellbrook, NSW 2333 of Consultancy - Rom Hopper Relocation type of New development. Tenders to include installation of the new ROM hopper and decommissioning the old one. Click for more details...

BENGALLA COAL OPERATIONS - OVERLAND CONVEYOR DECOMMISSIONING
Mining - Infrastructure (Conveyors, Stackers, Reclaimers, Materials handling) project at 4 km west of, Muswellbrook, NSW 2333 for New. For the decommissioning of an overland conveyor. Click for more details...

CAMDEN GAS PROJECT - RAZORBACK WELLS - RESOURCE
Resource - Coal Bed Methane project at Finns Rd & Woodbridge Rd, Camden Park, NSW 2568 In The Council Area Of Wollondilly of Private. To construct nine coal seam gas wells including gas gathering systems and access roads. The wells will be connected to the Rosalind Park Gas Plant for production. Click for more details...

LIDDELL COAL OPERATIONS - COAL HANDLING PREPARATION PLANT
Coal Handling Preparation Plant project at 20 Km North West of, Singleton, NSW 2330 In The Council Area Of Singleton of Private. Construction of a new Coal Handling Preparation Plant. This will involve the construction of a new preparation section, upgrades to the ROM receival and product coal facilities. The new preparation area will be located next to the old CHPP and its capacity will be 1200 tonnes per hour. This will include new screening, cyclone and spiral components for the plant. Upgrades to the ROM receival equipment include shortening of the apron feeder, a new rotating star wheel, new sizers and an increase in the drive power and length of the ROM conveyor. Modifications to the product handling equipment will include a short product conveyor to collect coal from the new CHPP to be deposited at a new transfer station onto the existing product stockpile rising conveyor. The existing road truck type coarse rejects bin will be replaced by a larger bin capable of loading mining sized trucks. The exisiting CHPP will be dismantled and recycled or disposed of over a one year period. Click for more details...

ROCGLEN COAL PROJECT - ROAD DIVERSION
Mining - Infrastructure (Roads, Airstrips, Culverts, Retaining walls) project for New development. For the provision of road diversion. Click for more details...

BICKHAM COAL COMPANY - BULK SAMPLE EXCAVATION PROJECT - RAIL LOADING FACILITY UPGRADE
Currently at the Early Planning stage In Upper Hunter is a project estimated to be $ 10000000. This project For the provision of upgrade services for the rail loading facility. Scope of work not yet determined. Click for more details...

RIDGEWAY DEEPS UNDERGROUND GOLD MINE EXTENSION PROJECT - PIPING - SUPPLY & INSTALL FOR SURFACE FACILITIES INFRASTRUCTURE
Mining - Infrastructure (Slurry pipelines) project In The Orange Council Area of Private ownership. For the supply & installation of piping. Click for more details...

ULAN COAL MINE CONTINUED OPERATIONS PROJECT - ULAN WEST UNDERGROUND
Private ownership Mining - Infrastructure (Conveyors, Stackers, Reclaimers, Materials handling) project In The Mid Western Regional Council Area for New development. Extension of underground mining operations in a location west of the existing Ulan No 3 underground mine & north of the recently closed open cut pit. To operate for 21 years using the retreat longwall method with a panel width of up to 400m. Access to the Ulan West operations to be via a series of portals to be constructed within the vicinity of the existing open cut pit. New surface facilities to be constructed around the entrance to include ventilation, power & water management facilities & a small temporary coal stockpile. An access ramp will also accommodate an overland conveyor out of the mine. Ancillary facilities to include a steel framed, concrete walled bathhouse along with other demountable buildings for workshops & administration purposes. Some temporary structures may also be installed during construction. Click for more details...

NEWCASTLE COAL INFRASTRUCTURE GROUP COAL TERMINAL 3 - OUTBOUND SYSTEM CIVIL STRUCTURAL MECHANICAL WORKS
New project of Mining - Infrastructure (Conveyors, Stackers, Reclaimers, Materials handling) project at Part of lots 6, 7, 20 Cormorant Rd DP 4015754 & 252325, Newcastle, NSW 2300. Design, Supply & Installation of Piled Foundations, Supply & Installation of Concrete Foundations, Shop Detailing, Supply, Fabrication, Painting, Off Site Pre-Assembly & Site Erection of Structural Steel and part supply & complete Mechanical Installation for the Outbound System comprising a 2000t Buffer Bin, two Belt Feeders, Sample Plant, two Transfer Houses, three Conveyors and two substation slabs for a 30Mtpa Coal Export Terminal. Click for more details...

PORT WARATAH COAL SERVICES - KOORAGANG TERMINAL STACKING EXPANSION
New project of Mining - Infrastructure (Conveyors, Stackers, Reclaimers, Materials handling) project at Curlew St, Kooragang, NSW 2304. Fabrication & installation of new stackers. Part of the 3EXP project to expand capacity of Stage 3 of Kooragang Terminal from 77 Mtpa to a nominal 120 Mtpa. Click for more details...

WEST CLIFF COLLIERY WASHERY UPGRADE
New project of Mining - Infrastructure (Conveyors, Stackers, Reclaimers, Materials handling) project at 4km southeast of, Appin, NSW 2560. Upgrade of the West Cliff Washery over the life of the Bulli Seam Operations Project to handle up to 105Mtpa throughput. To include installation of new components such as rotary breaker & screen house, coarse & fine coal storage bins, triple roll crusher, small coal circuit modules (eg desliming screens, primary & secondary cyclones, centrifuges), flotation cells & a teetered bed separator, coal & tailings thickeners, belt filters & tailings presses. Replacement of the existing Baum jig with a dense medium drum. Upgrades of existing conveyor systems, piping, pumps, sumps, safety & auxiliary systems. Upgrades of power supply systems to provide additional capacity & back up supply. Click for more details...

WILPINJONG COAL OPERATIONS EXPANSION
A project in the NSW Within Mid Western Regional. A project at the existing open-cut mine to expand Run-of-Mine (RoM) coal production from 13million tonnes per annum (Mtpa) to 15Mtpa for 12Mtpa per annum of washed & unwashed product coal to be railed to domestic power customers & a port for export. To involve a 7m extension to the coal handling & preparation plant (CHPP) building to accommodate a capacity increase to 1200tonnes per hour (tph). Associated upgrading of the coal handling & stockpiling system to include an additional ROM hopper with associated sizing station & raw coal conveyor & stacker plus an additional product coal stockpile with associated stacking conveyor & reclaim conveyor. Other work to include minor earthworks, conveyors, transfer stations & relocation of site roads. Click for more details...

CENTENNIAL COAL UNDERGROUND MOBILE FLEET 2011-15
Mining - Infrastructure (Conveyors, Stackers, Reclaimers, Materials handling) project at various mines, ., NSW 2999 of Coal Mining & Handling Equipment type of New development. A project to purchase for various Western Coalfield & Hunter Region operations a mobile development suite for gateroad development, bord & pillar production operations as well as longwall equipment. To include continuous miners, coal clearance systems, breaker line supports, up to 5 feeder breakers, load haul dumps, roof bolters for road development & bord & pillar operations, rubber tyred vehicles, up to 50 shuttle cars, man transporters & specialised mining vehicles. Click for more details...

CENTENNIAL WESTERN COAL SERVICES - SPRINGVALE SERVICES SITE UPGRADE
A project in the NSW Within Lithgow. A project to support western operations (Springvale, Angus Collieries) by upgrading the coal handling & distribution capacity at the central Springvale Coal Services site to 9.5 million tonnes per annum (Mtpa) of run-of-mine (ROM) coal. To include expansion of the coal washery involving installation of new plant adjacent the existing plant for an overall capacity of 7 Mtpa along with additional conveyors & transfer points. Increase of reject disposal capacity. Construction of a private haul road linking the site to the existing Angus Place-Mount Piper power station haul road. Continued integrated rehabilitation of the former Lambert Gully Mine also located on the coal services site. Click for more details...

PINE DALE COAL OPERATIONS STAGE 2 EXTENSION
Mining - Infrastructure (Roads, Airstrips, Culverts, Retaining walls) project In The Lithgow Council Area of Operating Mine - Extension type. A project to extend operations 10-15 years by incorporating 201ha in the Blackmans Flat area adjoining the now exhausted original Pine Dale mine & the recently approved 27ha Stage 1 Yarraboldy extension. Continued open cut operations accessing 14.2 million tonnes (Mt) at a rate of 2Mt product coal annually. Construction of a new mine industrial area to include a 600tph crushing & screening plant, 100,000t run-of-mine (ROM) stockpile, 200,000t product stockpiles & maintenance facilities. Construction or relocation of offices, amenities, workshop, water management infrastructure, electric power supply, explosives magazine & fuel storage area. Dewatering of existing pit prior to use for overburden & interburden emplacement. Reinstatement of the now derelict Wallerawang spur rail line & rail siding & construction of a rail load out facility. Internal access roads & private haul road crossing. An additional 60 employees expected at maximum production. Click for more details...

THE MAC ACCOMMODATION CENTRE BOGGABRI STAGE 1
Mining - Infrastructure (Tailings, Dams, Water supply dams) New project at 262 Carloola Rd, Boggabri, NSW 2382. This type is Accommodation Modules/Administration/Kitchen/Dining/Laundry/Civils/Reservoir with Private ownership. Construction of stage 1 of an accommodation village to provide 328 rooms & laundry facilities in prefabricated modules. Construction also of an office/administration building & a kitchen/dining building with concrete floors & metal walls & roofs. Civil works package expected to include bulk earthworks, roadworks, stormwater & construction of an 8ML reservoir. Click for more details...

MOUNT ARTHUR COAL OPERATIONS - WATER NETWORK UPGRADE
Mining - Infrastructure (Tailings, Dams, Water supply dams) New project at Denman Rd cnr Thomas Mitchell Dr 5km south of, Muswellbrook, NSW 2333. This type is Earthworks/Piping with Private ownership. Supply & installation of 25km of poly pipe. Relocation of pumps & pontoons & associated earthworks. Click for more details...

LIDDELL COAL OPERATIONS EXPANSION
Mining - Infrastructure (Roads, Airstrips, Culverts, Retaining walls) project at Old New England Hwy, Ravensworth, NSW 2330 for New. A project for a 5 year life-of-mine (LoM) extension by expanding the existing South pit followed by expansion of the Entrance pit after which a new MIA pit to be developed involving relocation of the current mine infrastructure area. Construction of a new conveyor & transfer point to link to the existing overland conveyor to allow transfer of up to 1.5 million tonnes per annum (Mtpa) of coal to the Ravensworth coal handling & preparation plant (CHPP) now that the demolished Cumnock CHPP is no longer available to take excess run-of-mine (ROM) coal. A new 50,000t stockpile at the new conveyor & expansion of the existing ROM stockpile capacity to 200,000t as well as a new tailings emplacement area in the South Pit void. Associated infrastructure expected to include access & haul roads, surface water management systems, new dewatering bores for the Hazeldene, Entrance & South pit workings, an explosive reload facility, powerlines, pipelines & a water truck fill point. Click for more details...

MINERAL HILL COPPER GOLD OPERATIONS - SOUTHERN RESIDUE TAILINGS STORAGE FACILITY
New project of Mining - Infrastructure (Tailings, Dams, Water supply dams) project at Via Melrose Dandaloo Rd, 65km north of, Condobolin, NSW 2877. For the provision of a Southern Residue Storage Facility to be constructed immediately adjacent to the southern face of the existing tailings storage facility & the western face of the existing waste rock emplacement. Click for more details...