State

Categories

Sub Categories

Click Here to Find Current Projects

List of Mining - Infrastructure Projects in WA


GRIFFIN BLUEWATERS POWER PROJECT - COAL-FIRED POWER STATION
Mining - Infrastructure (Roads, Airstrips, Culverts, Retaining walls) project at Lot 8 Wellington Loc 796 approx 3km north east of, Collie, WA 6225 for New. The commissioning of the coal-fired power station at Collie will commence October 2008. Click for more details...

JUNDEE-NIMARY GOLD OPERATIONS
Approximately 40 km east southeast of, Wiluna, WA 6646 Has Jundee-Nimary Gold Operations currently at Construction stage. Contract to involve site clearance, general earthworks & associated services such as lighting. Design work completed. A gravel airstrip & apron area are required for new mine site. Click for more details...

NIMARY - GOLD
Mine - Treatment Plant - Relocation Addition project In The Wiluna Council Area. Second hand Labouchere plant purchased from Dominion Mining. Contract to involve dismantling the carbon-in-pulp plant & transporting it from site 180 km north of Meekatharra to new mine 40 km northeast of Wiluna. Plant to then be reassembled & some modifications to be undertaken prior to recommissioning. The 500,000tpa carbon-in-pulp/carbon-in-leach plant to be expanded to 650,000tpa. Additional requirements include tankage, structural steel, mechanical & piping works. Refurbishment of existing facilities & installation of new equipment also included in this tender. Work scheduled for completion 31 October 1995. Click for more details...

EWINGTON 2 COAL OPERATIONS
8 km east of, Collie, WA 6225 Has Ewington 2 Coal Operations currently at Construction stage. Conveyor belts (Apex), drives (Flenders), pulleys & idlers (Pit Top) required for several electrical/mechanical packages associated with new coal handling facilities. Belt scrapers to be provided by Dyna Engineering (Osborne Park, WA). Click for more details...

RAVENSTHORPE NICKEL PROJECT
Access Roads/Earthworks project at 50km north of, Hopetoun, WA 6348 in the Mining - Infrastructure (Roads, Airstrips, Culverts, Retaining walls). The process plant location has been moved to the eastern side of Bandalup Hill. Some Jerdacuttup Road upgrades will no longer be required as heavy haulage will now be directed onto the South Coast Highway. Appropriate intersection design and construction will be required for the process plant access road to safely intersect the South coast highway. Proposed intersection approx 900 metres west of the Homestead Road turnoff to Oldfield. Click for more details...

MOUNT GIBSON PROJECT
Mining - Infrastructure (Conveyors, Stackers, Reclaimers, Materials handling) project In The City Of Greater Geraldon - Mullewa Council Area of Transfer Station type. A transfer station facility where iron ore will be transferred to rail for transport to the Port of Geraldton. Click for more details...

YANDICOOGINA IRON ORE OPERATIONS
A project in the WA Within East Pilbara. Expansion to 36 million tpa .Some conveyor work involved. Flow modifications. A current project to increase output to 24 million tonnes per annum is nearing completion. Click for more details...

MIITEL NICKEL OPERATIONS - SOUTH MIITEL
Mining - Infrastructure (Drifts, ventilator shafts, portals, shotcreting, declines) project In The Coolgardie Council Area of Private ownership. An initial Probale Ore Reserve resource estimate of 376,000 tonnes @ 2.6% for 9,790 tonnes of nickel. Development work will comprise an extension to the existing Miitel decline and the excavation of a ventilation shaft to the surface. The mining method will be mechanised flat back cut and fill. Click for more details...

PLUTONIC GOLD OPERATIONS - RESOURCE
Operating Mine project at 180 km North east of, Meekatharra, WA 6642 In The Council Area Of Meekatharra of Private. The Plutonic gold operation comprises both open pit and underground operations. There is also a CIL plant which operates sulphide and oxide circuits on site for the processing of ore. The mine can produce between 1.3 Mtpa to 1.8 Mtpa. In 2005, 251,000 ounces of gold were produced. Ore reserves are 14 Mt @ 5.2 gpt Au. Development work proposed includes increased mining at the Freshwater mine, in pit Tailing storage facilities at the Callp and Pirana pits. Work at the Freshwater mine is entitled the Trout Mining Project. Click for more details...

TELFER GOLD OPERATIONS
Mining - Infrastructure (Roads, Airstrips, Culverts, Retaining walls) project for Renovations, Refurbishments etc. development. Contract involves re-surfacing & extending the existing runway. Some fill & compaction works required. Tender to include lighting, navigational system & fencing associated with this upgrade. Click for more details...

RAVENSTHORPE NICKEL PROJECT - TREATMENT PLANT PACKAGES
A project in the WA Within Ravensthorpe. Processing includes a combination of pressure acid leach (PAL), atmospheric leach (AL) and Enhanced Pressure Acid Leach (EPAL). The EPAL process entails separate mining, stockpiling and beneficiation of Ilmonite ( high iron, low magnesium and calcium, upper levels) ore. The ilmonite is treated by PAL, whilst the saprolite is treated by AL using the PAL discharge and additional acid. This allows recovery of an additional 15,000 tpa of nickel. The process downstream of the leaching circuit uses the Cawse flowsheet with partial neutralisation, followed by separation of the barrren tailings from the nickel bearing solution, further impurity removal and preciptiation of MHP. This intermediate product is then transported to the QNI Yabulu refinery. Click for more details...

COYOTE GOLD PROJECT - DAMS/ROADS/AIRSTRIP
Mining - Infrastructure (Tailings, Dams, Water supply dams) project for New development. Construction of the airstrip has commenced and civil works for the plant, roads and dams will commence shortly. Click for more details...

PILBARA IRON ORE & INFRASTRUCTURE PROJECT - MINING CONTRACT
Pilbara Iron Ore & Infrastructure Project - Mining Contract is currently at the Construction stage, valued at about $ 200000000 it is Work will be carried out in two stages. The first stage comprises mine planning, equipment selection, procurement and commissioning, mine infrastructure planning, operator input to design, pre-production of initial bulk earthworks, pre-strip, pre-production ore mining, construction of haul roads, service reticulation, dewatering, installation and commissioning of mine site conveyancing and development of all mine site management systems. The second stage comprises ore production and mine planning to optimise annual operations and annual operating targets of the mine. Click for more details...

JAGUAR BASE METALS PROJECT - SITE PREPARATION WORKS/BOX CUT MINING CONTRACT
A project in the WA Within Leonora. Development comprises the movement of 1 million cubic metres of material over five months. Work will involve site clearing, mining the box cut, construction of haul roads, initial processing plant earthworks, and tailings dams construction. Click for more details...

WESTONIA GOLD PROJECT - ACCESS ROAD/EVAPORATION POND/EARTHWORKS
Currently at the Construction stage In Westonia is a project estimated to be $ 5000000. This project Earthworks will involve the construction of an access road, the construction and refurbishment of evaporation ponds and pit floor clean up. Click for more details...

MOUNT GIBSON IRON ORE MINE & INFRASTRUCTURE PROJECT - STORAGE SHED & FACILITIES
Mining - Infrastructure (Conveyors, Stackers, Reclaimers, Materials handling) project In The City Of Greater Geraldton Council Area of Storage Shed/Associated Facilities type. Construction of dedicated berth, storage shed and shiploading facilities to handle 130,000 tonnes of iron ore. Facilities will include hoppers, conveyors, storage tanks, clarifier, return water tank and pumps, HV cables, power transformer, MCC and switch rooms. A filter plant will be constructed to dry the slurry. Concrete floor, structural steel and cladding. Click for more details...

IRON ORE RAPID GROWTH 3 PROJECT - AREA C - INFRASTRUCTURE
Infrastructure project at Near, Newman, WA 6753 In The Council Area Of East Pilbara of Private. Area C Infrastructure Click for more details...

IRON ORE RAPID GROWTH 3 PROJECT - AREA C - SUMP/SLURRY PUMPS
A project in the WA Within East Pilbara. Slurry and Sump Pumps. Click for more details...

GERALDTON PORT BERTH 5 IRON ORE EXPANSION PROJECT - MOTOR CONTROL CENTRES
Motor Control Centres - Supply Of project at Geraldton Port, Marine Terrace, Geraldton, WA 6530 In The Council Area Of City Of Greater Geraldton of Private. Supply of Motor control Centres. 3 No.Fully equiped control centres. Click for more details...

GERALDTON PORT BERTH 5 IRON ORE EXPANSION PROJECT - CONTROL ROOM
Control Room project at Geraldton Port, Marine Terrace, Geraldton, WA 6530 In The Council Area Of City Of Greater Geraldton of Private. Control Room Click for more details...

GERALDTON PORT BERTH 5 IRON ORE EXPANSION PROJECT - BELT SCRAPERS
New project of Mining - Infrastructure (Wharfs, Piers, Port facilities, Piling, Dredging) project at Geraldton Port, Marine Terrace, Geraldton, WA 6530. Belt Scrapers Click for more details...

GERALDTON PORT BERTH 5 IRON ORE EXPANSION PROJECT - THIRD PARTY QUALITY ASSURANCE
Mining - Infrastructure (Conveyors, Stackers, Reclaimers, Materials handling) project at Geraldton Port, Marine Terrace, Geraldton, WA 6530 for New. Third party review of quality assurance for fabrication and construction of the berth 5 ZPMC shiploader. Click for more details...

SINO IRON ORE PROJECT - SLURRY PIPELINE
Private ownership Mining - Infrastructure (Conveyors, Stackers, Reclaimers, Materials handling) project In The City Of Karratha Council Area for New development. Scope of works modified. The Company has decided on the development of a 25km slurry pipeline instead of an overland conveyor.. Click for more details...

ALBANY IRON ORE PROJECT - PORT EXPANSION
Mining - Infrastructure (Wharfs, Piers, Port facilities, Piling, Dredging) project In The Albany Council Area of Port - Expansion type. Albany Port Authority proposes to dredge within Princess Royal Harbour & King George Sound to facilitate access of cape size vessels. Proposal includes dredged materials being used for land reclamation to create an additional berth adjacent to port to be leased to Grange Resources LTD to accommodate their Port infrastructure. Magnetite mined by Grange will be pumped as slurry approx 100 km from their Southdown Magnetite & Kemaman Pellet Plant to concentrate storage facility at Albany Port before being loaded on to cape size vessels to be shipped to Malaysia. Click for more details...

FORRESTANIA NICKEL PROJECT - SPOTTED QUOLL
Mining - Infrastructure (Roads, Airstrips, Culverts, Retaining walls) New project at Approximately 80km East of, Hyden, WA 6359. This type is Resource - Nickel with Private ownership. The prospect contains approximately 545 600 tonnes of ore averaging 6.3% Nickel; current estimates set the open pit mine-life at four years. The waste dump will be designed for 16 million tonnes of waste rock. Ore will be trucked via upgraded established roads to Flying Fox. Likely infrastructure to include: pit and pit access, ROM, waste dump, settling pond(s), administration building(s), lay-down, haul road, pipeline and power. Mine dewatering pipelines consisting of 450 mm HDPE buried to a depth in excess of 300 mm, parallel to the haul road, will convey mine water to established mine dewatering infrastructure at the Flying Fox mine. Click for more details...

BLUEWATERS POWERSTATION COAL HANDLING PLANT CONVEYOR
Mining - Infrastructure (Conveyors, Stackers, Reclaimers, Materials handling) project In The Collie Council Area of Plant Conveyor type. Unit 2 Coal Handling Plan Conveyor structure to be developed. Click for more details...

RAPID GROWTH 6 IRON ORE PROJECT (RGP6)
Mining - Infrastructure (Conveyors, Stackers, Reclaimers, Materials handling) project In The East Pilbara Council Area of Private ownership. The Rapid Growth Project 6 (RGP6) project aims to increase iron ore capacity installed in Western Australia to 240 million tonnes per annum (Mtpa) from the Rapid Growth Project 5 (RGP5) target of 205Mtpa. March 2011 financial approval for Jimblebar mine expansion (rail links, mining equipment, rolling stock for 35Mtpa capacity) & Port Hedland expansion (2 new berths & shiploaders, car dumper, connecting conveyor routes with associated rail works & rolling stock) as well as blending facilities in preparation for future growth beyond the inner harbour. Click for more details...

RAPID GROWTH 6 IRON ORE PROJECT - POINT NELSON DREDGING
Dredging/Reclamation/Piling project at Nelson Point & Lumsden Point, Port Hedland, WA 6721 In The Council Area Of Port Hedland of Private. Dredging of 6 million cubic metres of material between Nelson & Burgess Points adjacent BHP Billiton's existing berths in Port Hedland Inner Harbour. To provide 2 new berth pockets & upgrade the existing departure channel & swing basin to accommodate vessels up to 250,000DWT. Spoil removed by a Backacter dredge to be placed offshore near the existing Spoil Ground I. Material removed by a Cutter Suction dredge to be sent by floating, submerged & onshore pipeline for placement in an area of over 200ha between Lumsden Point & the light industrial area of Wedgefield. Construction of a perimeter bund using 250,000cu m of fill for an initial 5m height then dredge material to be used to take it up to 9m. Construction also of a 60m approx wide corridor to carry 2 x 900mm diameter pipelines. Driving of marine piles for future wharf construction. Click for more details...

GREATER GORGON GAS PROJECT - LNG JETTY & MARINE STRUCTURES - ELECTRICAL
Mining - Infrastructure (Wharfs, Piers, Port facilities, Piling, Dredging) project at On, Barrow Island, WA 6712 for New. For the provision of lighting & earthing material (including cables & junction boxes). Click for more details...

ROY HILL IRON ORE PROJECT - INFRASTRUCTURE - NORTHERN RAIL
Mining - Infrastructure (Roads, Airstrips, Culverts, Retaining walls) project In The Port Hedland Council Area of Private ownership. It is proposed to develop a railway of approximately 320km to transport iron ore from the Roy Hill 1 mine to facilities at Port Hedland and the proposed Boodarie multiuser stockyard area which is to be vested in the PHPA (Port Hedland Port Authority). The railway proposal includes: a marshalling yard (with associated workshops and maintenance facilities storage and laydown areas, rail welding yard), passing loops and sidings, construction water bores and 'turkeys nest' dams, borrow and ballast areas for construction material, communications cable, towers and signalling system, construciton works accommodation camps and amenities for workers, access roads and construction power supplies. Five train sets will be required to transport 55 Mtpa, with each train consisting of two diesel electric locomotives and 232 iron ore wagons. When spares are included, this will entail a fleet of 17 locomotives and 1790 wagons. Fuel supply trains will require one additional AC locomotive and 12 tanker cars. An unsealed, at-grade access road will run adjacent to and generally parallel to the proposed railway for its entire length, for the purposes of railway access and maintenance. The road pavement width will be approximately 9m wide. Seven sidings are expected to be required along the entire length of the railway to allow trains travelling in opposite directions to pass. Additional sidings called "back-tracks" will be provided on the back to eh passing sidings along the alignment as required to allow removal of 'bad-order' wagons (mechanical fault). Road crossings will be at grade or grade separated in accordance with the requirements of Main Roads of Western Australia. Level crossings on access roads will be protected with signs that comply with this standard. To preserve current land uses in a way that is compatible with the proposed railway, fencing and/or controls will need to be installed at occupational rail crossings, vehicle the paths, livestock grids and in other areas where access requires controlling or restricting. Watercourses crossings will consist of culverts or bridges. Culverts will be used in preference to bridges. For bridges, to provide a simple and efficient method of construction, the design of the rail bridges will be standardised for fast construction requiring a minimum quantity of in situ concrete. The span length proposed is 25m. The construction methodology will be to at 25m intervals drive circular steel pier columns as a "trestle" consisting of three members with the two outer members raking and the central pier column vertical. A heavy hardstand granular pavement is required for installation of piled substructure over the full length of each bridge primarily to provide safe, stable access for heavy plant and equipment. The width of the hardstand on both the upstream and downstream sides of the piers will be approximately 20m, ie a total fo 40m wide. Hardstand will remain in service until superstructure units are placed by heavy cranage. Prefabricated steel headstocks will be lifted into place by a crane and site welded to the pier columns. Decks will consist of prefabricated composite girders or steel through girder construction. The marshalling yard will be adjacent to the main line and will incorporate 10 rail tracks. The site is expected to accommodate a rolling-stock workshop and washdown bay, locomotive provisioning hall, rail infrastructure yard, diesel fuel storage, electrical substation, communications tower, administration building, car parks, potable and wastewater treatment units and fire-water storage and access roads. The rolling stock workshop will be a single storey building with a heavy duty concrete slab, overhead travelling cranes, high pressure water wash-down facilities and various pieces of maintenance equipment including a wheel lathe to se Click for more details...

GREATER GORGON GAS PROJECT - LNG JETTY & MARINE STRUCTURES - PRE ASSEMBLED RACKS - PAINTING
On, Barrow Island, WA 6712 Has Greater Gorgon Gas Project - Lng Jetty & Marine Structures - Pre Assembled Racks - Painting currently at Construction stage. For the provision of labour & materials to touch up painting of metal pipework & fittings. Click for more details...

BHP BILLITON PORT HEDLAND INNER HARBOUR EXPANSION
Berths/Shiploader/Car Dumper/Conveyor/Rail Works project at Finucane Island via, Port Hedland, WA 6721 In The Council Area Of Port Hedland of Private. Port expansion as part of project to increase iron ore capacity to 220million tonnes per annum (Mtpa). To include 2 new berths & shiploaders, a car dumper (No. 5), connecting conveyors & associated rail works. Click for more details...

ANDERSON POINT PORT FACILITIES - BERTH 3
Mining - Infrastructure (Wharfs, Piers, Port facilities, Piling, Dredging) New project at Anderson Point, Port Hedland, WA 6721. This type is Port Facilities with Private ownership. The expansion will provide an additional 400m of wharf superstructure, 7 berthing dolphins, navigational aids and associated mechanical components. Click for more details...

ARGYLE DIAMOND OPERATIONS UNDERGROUND EXPANSION - CRUSHERS, CONVEYORS & DEWATERING
Mining - Infrastructure (Conveyors, Stackers, Reclaimers, Materials handling) New project at 110km south-southwest of, Kununurra, WA 6743. This type is Crushers/Conveyors/Dewatering Pump Stations with Private ownership. Supply of 2 underground crushers. 1.2km of conveyors. Dewatering pump stations. Associated piping, electrical, instrumentation & control equipment. Click for more details...

NICKEL WEST OPERATIONS - KAMBALDA NICKEL CONCENTRATOR MATERIALS HANDLING CONTRACT
via, Kambalda, WA 6442 Has Nickel West Operations - Kambalda Nickel Concentrator Materials Handling Contract currently at Construction stage. A 5 year contract at the concentrator plant which handles ore from the Leinster, Mouth Keith & Cliffs mines. To include ore handling, crushing & sampling. Click for more details...

GREATER GORGON GAS PROJECT - CIVILS & UNDERGROUND SERVICES - CONSTRUCTION OF IN-SITU CONCRETE - MR & PR STRUCTURES
New project of Mining - Infrastructure (Computer & telecommunication system for mine, scada) project at Both on & off, Barrow Island, WA 6712. For the construction of reinforced concrete base & foundations, columns, table tops, pedestals & plinths that includes cast-in items, holding down blots, plates, angles, steel columns openings & box-outs for shear keys in tops of pedestals. Click for more details...

GREATER GORGON GAS PROJECT - CIVILS & UNDERGROUND SERVICES - MANHOLE STEEL COVERS (GATIC)
Mining - Infrastructure (Computer & telecommunication system for mine, scada) project at Both on & off, Barrow Island, WA 6712 of Manhole Steel Covers type of New development. For the provision of various types, classes & sizes of steel manhole metal covers & frames. Click for more details...

GREATER GORGON GAS PROJECT - LNG JETTY & MARINE STRUCTURES - PAR PIPE TESTING & INTERNAL CLEANING
Par Internal Pipe Cleaning project at On, Barrow Island, WA 6712 In The Council Area Of Ashburton of Private. For pipe line cleaning, hydrostatic testing, drying, & purging lines with residual positive pressure of nitrogen. Click for more details...

LAMBOO/NICOLSONS GOLD JOINT VENTURE PROJECT - ROADS & INFRASTRUCTURE
Mining - Infrastructure (Roads, Airstrips, Culverts, Retaining walls) project In The Halls Creek Council Area of Roads/Infrastructure type. For the provision of roads & infrastructure to include road base material. Click for more details...

PORT HEDLAND INNER HARBOUR - BHP BILLITON STOCKYARD EXPANSION CIVIL WORKS
Port Hedland Inner Harbour - Bhp Billiton Stockyard Expansion Civil Works is currently at the Construction stage, valued at about $ 50000000 it is Upgrade of the existing ore blending stockyard at Nelson Point. To include bulk earthworks, stone column ground improvement works, rail, concrete works, piping & instrumentation for dust suppression & road works. Click for more details...

ROY HILL IRON ORE PROJECT - PORT MARINE - QUICK RELEASE HOOKS
A project in the WA Within East Pilbara. For the provision of quick release hooks. Click for more details...

DEFLECTOR COPPER GOLD PROJECT - ACCOMMODATION CAMP - EXPANSION
New project of Mining - Infrastructure (Roads, Airstrips, Culverts, Retaining walls) project at Via Geraldton Mt Magnet Rd 60km SE of, Mullewa, WA 6630. Planned expansion of an onsite accommodation camp. Access road. Click for more details...

GREATER GORGON GAS PROJECT - LNG JETTY & MARINE STRUCTURES - SHIPPING CONTAINERS
Mining - Infrastructure (Wharfs, Piers, Port facilities, Piling, Dredging) project at On, Barrow Island, WA 6712 of Shipping Containers type of New development. For the provision shipping containers. Click for more details...

BODDINGTON GOLD OPERATIONS EXPANSION
Operating Mine - Expansion New project In The Boddington Council Area. Life-of-mine (LoM) extension through deepening & widening the Wandoo North & South open pits. To include expansion of the existing & construction of a new 1500 million tonne (Mt) waste rock dump. Construction over 1650ha of a second 1600Mt residue disposal area (RDA) involving decommissioning of an existing water storage dam (D4). Construction of new water storage dams (D5 & D6). Expansion of existing stockpiles including provision of stockpiling any bauxite encountered for third party processing. Associated diversion of Bibbulmun track, roadworks, pipelines/pumping facilities & power lines. Click for more details...

ROY HILL IRON ORE PROJECT - NON-PROCESS INFRASTRUCTURE - MINE SITE HV AREA
Currently at the Construction stage In East Pilbara is a project estimated to be $ 100000000. This project Construction of various non-process infrastructure buildings for the Roy Hill Iron Ore Mine, comprising three main works zones being Mine Services Area, a Gatehouse and Go-Line Facility and to include HV area. Click for more details...

ROY HILL IRON ORE PROJECT - GENERAL - IMPACT ROLLER (INCLUDING PRIME MOVER/TRACTOR)
Roy Hill Iron Ore Project - General - Impact Roller (Including Prime Mover/Tractor) is currently at the Construction stage, valued at about $ 250000 it is For the provision of an Impact Roller (including Prime Mover/Tractor). Click for more details...

WHEATSTONE DEVELOPMENT PROJECT - PRODUCT LOADING FACILITIES & TUG BERTH - ON SITE PIPE WELDING
Mining - Infrastructure (Wharfs, Piers, Port facilities, Piling, Dredging) project at Vicinity of, Onslow, WA 6710 of Pipe Welding - On Site type of New development. Conduct all pipe welding on Site at Ashburton North (12 kilometres west of Onslow). Tasks to be performed include but are not limited to weld out of module to module pipework incl. works over water. Weld out of platform pipework including fit up to associated mechanical equipment; TIG welding of stainless 316 & carbon steel piping & all other pipe welding tasks as required. Click for more details...

PILGANGOORA LITHIUM PROJECT - ROAD & RAIL CROSSING UPGRADES
New project of Mining - Infrastructure (Roads, Airstrips, Culverts, Retaining walls) project at 120km South of, Port Hedland, WA 6721. For the provision of road & rail crossing upgrades. Click for more details...

ELLENDALE DIAMOND MINE - TAILINGS STORAGE FACILITY - EROSION REMEDIATION
Erosion Remediation project at Via, Derby, WA 6728 In The Council Area Of Derby-W Kimberley of State. Works to include remediation works on the walls of the main Ellendale Tailings Storage Facility to ensure the facility remains safe & stable. Works will primarily involve placing rock material in areas where significant scour & erosion occurs. Click for more details...

Copyright © CoreLogic. All rights reserved. Powered by Cordell Connect