State

Categories

Sub Categories

Click Here to Find Current Projects

List of Mining - Primary And Secondary Processing Projects


HISMELT EXPANSION PROJECT
Private ownership Mining - Primary And Secondary Processing (Piping) project In The Kwinana Council Area for New development. One of three packages. Pipework. Click for more details...

LIDDELL COAL COLLIERY - RESOURCE
Mine - Coal New project In The Singleton Council Area. Existing operation produces 4.5 Mtpa of Rom coal and the CHPP processes 700 tonnes per hour. A proposal has been approved to increase ROM coal production to 8 Mtpa. Associated development will comprise the construction of a new Coal Handling Plant, establishment of a new supplementary stockpile with capacity of 450,000 tonnes, alter the planned 1500 ML Dam 13B footprint, construct a bridge over the main Northern Railway to improve transport between existing coal pits, alter an access road to the CHPP, relocation of offices, workshop and storage area and an associated access road, and the construction of a desalination unit within the CHPP area for the treatment of mine water. Capital expenditure on the Washplant upgrade alone was approx $100 million. Click for more details...

KUNWARARA MAGNESITE OPERATIONS - KG2 EXTN
A project in the QLD Within Rockhampton Regional. Installation of a new crushing and screening circuit. Click for more details...

HISMELT EXPANSION PROJECT
Mining - Primary And Secondary Processing (Minerals Processing) project In The Kwinana Council Area of Earthworks - Preliminary Works type. Concrete works and pipebridges. A vertical package comprising both civil and mechanical works. Includes earthworks, stone column foundations, 10,000 cu m of reinforced concrete foundations and 1,000 tonnes of structural steel pipe racks, associated pipes, ducting and accessories. Click for more details...

BLACKWATER COMET CHPP PROJECT
Mining - Primary And Secondary Processing (Coal Processing) project In The Central Highlands Regional Council Area of Prep Plant/Raw Coal Area/Loadout/High Voltage - Design/Const Package (Combined) type. Now includes the Comet CPP Project (Preparation Plant), and all coal handling facilities, as well a high voltage electrical package. Click for more details...

GLOUCESTER RUBY MINE
Mine - Rubies project at Mid way between Scone and, Gloucester, NSW 2422 In The Council Area Of Gloucester of Private. Mine production for December Quarter 2006 was 15,281 tonnes of gemstones. Click for more details...

DRUMMOND BASIN PROJECT - WIRRALIE
Mining - Primary And Secondary Processing (Minerals Processing) project In The Whitsunday Regional Council Area of Private ownership. Preliminary feasibility study results show heap leach processing, rather than using existing plant could improve economics. Click for more details...

JAGUAR BASE METALS PROJECT - PROCESSING PLANT/MECHANICAL WORKS CONTRACT
A project in the WA Within Leonora. A centrally located processing facility to be located on the granted Teutonic Bore mining lease, 4 km to the north of the Jaguar deposit. A 350,000 tpa plant to treat ore by crushing, grinding and flotation. Copper and zinc concentrate production is expected to commence in July 2007, increasing to 10,000 tonnes of copper, 34,000 tonnes if zinc and 1 million ounces of silver in concentrate per annum over a six year period. Click for more details...

PAULSENS GOLD PROJECT
Mining - Primary And Secondary Processing (Minerals Processing) project at 180 km west of, Paraburdoo, WA 6754 for New. A high grade shallow underground mine including 250,000 Tpa CIL plant. Gold production was 488,260 tonnes @ 7.94 g/t for 117,266 ounces of gold since June 2005. Production is expected to be 75-80,000 ounces of gold per annum. Measured and Indicated resource is 1,105,000 tonnes @ 10.7 g/t for 379,700 ounces of au and inferred resource is 122,000 tonnes @ 9.3 g/t for 36,300 ounces of au. Click for more details...

WORSLEY ALUMINA REFINERY CAPITAL DEVELOPMENT PROJECT
Mining - Primary And Secondary Processing (Minerals Processing) project at Near, Collie, WA 6225 of Expansion Of Capacity type of New development. An expansion to 3.5 million tonnes per annum ( increase of 250,000 tonnes). To be undertaken over the next two years with minimum interruptions by utilising planned maintenance shutdowns. Includes additions to precipitation circuit, modifications to digestion area emission control system, additional baixite residue washing and disposal facilites, upgrade of power supply. Click for more details...

FOSTERVILLE GOLD OPERATIONS
Mining - Primary And Secondary Processing (Minerals Processing) New project at Near Fosterville 20 km northeast of, Bendigo, VIC 3550. This type is Ccd Thickener with Private ownership. Design & suply of CCD thickener. Click for more details...

KOGAN CREEK COAL/POWER STATION PROJECT
Mining - Primary And Secondary Processing (Coal Processing) project In The Western Downs Regional Council Area of Private ownership. Proposed open cut coal mine and associated power station Click for more details...

ARDLETHAN TIN OPERATIONS - PREPARATION/TREATMENT EQUIPMENT SUPPLY
A project in the NSW Within Coolamon. Includes mobile preparation & treatment equipment to be located close to the excavator. Ore is placed in a stockpile & a loader working continuously will feed the ore into the feeder-hopper of the scrubber-trommel. More water will be added so that the undersize can be pumped through in-line jigs which will be located within boom of the trommel unit. Some tin concentrate will be recovered in the in-line pressure jigs. The finer tin particles will be picked up in a spiral plant. Click for more details...

POWERCOAL COLLIERIES
Lifting Products - Supply project at Various sites lake Macquarie, Central Coast & Lithgow Regions, Lithgow, NSW 2790 In The Council Area Of Lithgow of Private. Supply and delivery of lifting and materials handling products (including winches, hoists, blocks, wire and fibre ropes, chains, shackles, tumbuckles etc) for an initial two year period with "optional" extension period. Click for more details...

DRUMMOND BASIN PROJECT - WIRRALIE
300 km west of Mackay via, Mount Coolon, QLD 4804 Has Drummond Basin Project - Wirralie currently at Early Planning stage. Assets include a 315,000 ounce gold resource at the Wirralie gold mine, three tenement packages totalling some 3,200 sqkm with excellent exploration potential and the Wirralie 1.5 Mtpa CIP treatment plant, infrastructure, administration buildings, Camp Yandan heap leach pad. The Wirralie treatment plant is currently on care and maintenance. The company plans to begin mining the relatively straightforward oxide ore and then using the time and cash flow to expand the suplhide resrouce base. The sulphide resource is beneath the oxide resource. Click for more details...

DOUGLAS MINERAL SANDS PROJECT
Turnkey Contract - Design & Project Management Of Processing Facilities New project In The West Wimmera Council Area. Includes design, procurement, construction & commissioning of the mineral sands processing facilities and associated infrastructure. Click for more details...

MURRIN MURRIN NICKEL PROJECT - HYDROGEN SULPHIDE PLANT SHUTDOWN
A project in the WA Within Leonora. 10 DAY shutdown planned. Click for more details...

LAKE VERMONT COAL PROJECT - PREPARATION PLANT - OPERATION
Preparation Plant - Operation project at Approx 15 km north east of, Dysart, QLD 4745 In The Council Area Of Isaac Regional of Private. for a 4 Mtpa plant. Click for more details...

KING ISLAND SCHEELITE PROJECT - OLD DOLPHIN MINE - MECHANICAL FOR PROCESSING FACILITY INCORPORATED INTO PROJECT ID 8691
Private ownership Mining - Primary And Secondary Processing (Minerals Processing) project In The King Island Council Area for New development. For the mechanical installation for the processing facility. Click for more details...

ABBOT POINT COAL TERMINAL EXPANSION STAGE 3
Mining - Primary And Secondary Processing (Coal Processing) project at Abbot Point 25 km north west of, Bowen, QLD 4805 of Coal Terminal Expansion - Stage 3 type of New development. Expansion of terminal capacity from 15 mtpa to 50 mtpa. Key components of the stage 3 expansion will involve the construction of a second berth, a second rail loop and train dump facilities and associated second in loading conveyor. Installation of a new stockyard bund and two new stockpile rows. Up to three new stacker reclaimers and a new yard conveyor and transfer towers will be installed. A second outloading conveyor to the offshore berth, using the existing jetty structure will be installed. Installation of a second offshore berth and a second shiploader on the new berth. Lastly there will dredging work associated with the second berth and the dredge material will be disposed of on either land or sea. Click for more details...

ALCAN GOVE BAUXITE OPERATIONS - REFINERY EXPANSION - ELECTRICAL/INSTRUMENTATION
Mining - Primary And Secondary Processing (Minerals Processing) New project at Gove Peninsula North West Arneham Land via, Gove, NT 0880. This type is Electrical/Instrumentation with Private ownership. Refinery expansion will increase production from a current 2 Mt/y to 3.8Mt/y in 2007. Proposed expansion includes stockpiling and handling. Bauxite will not be exported from Gove anymore but will be directed to the refinery. Stockpile sizes will remain the same, but stacker and feed conveyor systems will be upgraded or replaced and the refinery reclaimer will also be replaced. Three new grinding mills will be installed to replace the old rod and ball mills. One new mill slurry tank and pump transfer system together with one train of indirect mill slurry equipment will be installed. The heated feed will now be processed in a new high temperature double digestion process. A third low temperature digestion plant will be installed, as well as deep-cone thickners and high pressure pumps. The mud and liquor residue will be seperated in pressure decanters and processed through a train of new high rate washers and a single train of five deep cone thickners. The existing washers and thickners will be used for storage of residue liquids. Some will be demolished. Six new vertical pressure filters will be installed in a new security filtation area to process most of the turbid liquor flow from the thickners. Agglomeration precipitators and growth precipitators will be added to increase capacity as well as two interstage cooling facilities will be installed on each growth precipitator train. Flash vessels and a barometric condenser will be installed using cooling water from new cooling towers. A new hydrocyclone classification system with three classification stages allowing three different sized hydrate streams to be produced will be installed. A new filtration area and equipment will be installed to conduct filtration of various hydrate streams. Equipment will include six drum filters, vacum pumps and air blowers. Three new stationary calciners will be installed in conjunction with new hydrate conveyors and upgraded aluminia transfer systems. A new evaporation plant will be installed as well as cooling towers for vapour removal in the last three flash stages. Lime plant capacity will be increased from 140 t/h to 200 t/h by installing a new burner system and modifying the kiln's internal geometry. A new burnt lime storage silo will be installed. The existing power station will be converted from fuel oil to gas that will involve a new boiler and associated turbine units. The neutralisation plant will include a mixing tank and two thickners in a bunded area. New liquor purification plant will be constructed involving two seperate plants for the mixing and drying stage. Click for more details...

EMILY ANN INFRASTRUCTURE EXPANSION
Infrastructure Expansion project at 140 kM West of, Norseman, WA 6443 In The Council Area Of Dundas of Private. Expansion of existing infrastructure at Maggie Hays comprises upgrading the processing plant from 0.5 mtpa of ore to 1.5 mtpa. Downstream facilities of flotation, concrete handling, tails disposal, reagent mixing and process water systems would also be expanded. Other facilities such as the laydown area, both explosive magazines and mixing facility, the ROM pad, waste rock dump, fuel storage (2 x 55,000 litre tanks) will be expanded. Expansion of existing workshop buildings and administration areas will be done as a needs basis. The power plant will Increase from 7 MW to 10 MW and the construction of a new 4 MW plant at the Maggie Hays mine site. Two new process water ponds and a merging lane at the corner of Hyden Norseman Road and the Maggie Hays access road. Click for more details...

RAVENSTHORPE NICKEL PROJECT - TESTING/CALIBRATION OF INSTRUMENTS
Private ownership Mining - Primary And Secondary Processing (Minerals Processing) project In The Ravensthorpe Council Area for New development. Site services for testing and calibration of instruments. Click for more details...

PERSEVERANCE JOINT VENTURE PROJECT - GOLD RESOURCE
Resource - Gold project at Via, Coolgardie, WA 6429 In The Council Area Of Coolgardie of Private. Recently completed grade control drilling has resulted in a 28% increase in the Indicated Resource from 448 000t @ 6.4%g/t for 92 100 contained ounces to 490 700t @ 7.5%g/t for 118 500 ounces as a result of the conversion of additional ounces. Click for more details...

IRON ORE RAPID GROWTH 3 PROJECT - PORT/AREA C - UPS SYSTEM
Mining - Primary And Secondary Processing (Computerised systems for processing equipment) project In The Port Hedland Council Area of Private ownership. Uninterruptible Power Supply System. Click for more details...

JAGUAR BASE METALS PROJECT - PROCESSING PLANT
Mining - Primary And Secondary Processing (Minerals Processing) New project at Via, Leonora, WA 6438. This type is Processing Plant with Private ownership. The old Cadjebut and Black Cat processing plant is now onsite and are being refurbished with work to be completed by June 2006. Design work for the configuation has been completed. Long lead item for the plant have all been ordered. The plant was originally designed for processing 365,000 tonnes of ore per year, but it managed 550,000 tonnes per year when in operation. Click for more details...

WORSLEY ALUMINA EFFICIENCY/GROWTH PROJECT - 415 V MOTOR CONTROL CENTRES & LOAD CENTRES
Mining - Primary And Secondary Processing (Minerals Processing) project at 15 Km South east of, Collie, WA 6225 of 415 V Motor Control Centres/Load Centres - Supply type of New development. 415 V Motor Control Centres (MCC) and Load Centres. Click for more details...

COSMOS NICKEL PROCESSING FACILITY - UPGRADE
Nickel Processing Facility - Upgrade project at 35 Km North West of, Leinster, WA 6437 In The Council Area Of Leonora of Private. The plant currently processes 150,000 tonnes of ore per annum and some years has produce 30% more than this. Plant equipment comprises crusher, sag mill, flotation cells, cyclones, a thickner and filter. It is proposed to upgrade the plant to process 300,000 tonnes of ore per year by upgrading the comminution circuit. Click for more details...

ST IVES GOLD OPERATIONS - HEAP LEACH FACILITY STAGE 3 EXPANSION
Currently at the Construction stage In Coolgardie is a project estimated to be $ 8589000. This project Work comprises clearing the site, earthworks, pipeworks, Geomembrane and geofabrics liners for the heap leach facility. Click for more details...

TOM PRICE IRON ORE OPERATION - CIVIL WORKS CONTRACT
Mining - Primary And Secondary Processing (Civil works at processing facilities) project for New development. Work comprises civil and concrete works for the Vault, Rail Stacker and miscellaneous concrete works at the Tom Price mine. Click for more details...

QUEENSLAND ALUMINA RED MUD DAM REDEVELOPMENT
Dam/Pipeline/Roadworks/Processing Plant project at ., Boyne Island, QLD 4680 in the Mining - Primary And Secondary Processing (Civil works at processing facilities). Containment walls, processing plant, roads & pipes. Click for more details...

WALLOWAY BASIN GAS PROJECT - STAGE 2 - COMMERCIAL PLANT
Mining - Primary And Secondary Processing (Minerals Processing) project In The Orroroo/Carrieton Council Area of Private ownership. Stage 2 involves a plant to produce around 15PJ syngas a year for a 250MW power station. Click for more details...

LUCKY BREAK HEAP LEACH PROJECT (NORNICO STAGE 2) - COMMERCIAL PLANT
Mining - Primary And Secondary Processing (Minerals Processing) project at Gregory Development Rd south of, Greenvale, QLD 4816 for New. For a 250,000 tpa plant to run 4-5 years. The building will be 40m x 60m & likely to be prefabricated. Click for more details...

BODDINGTON GOLD MINE EXPANSION PROJECT - MILL LINER HANDLER & HYDRAULIC BOLT REMOVERS
Mining - Primary And Secondary Processing (Minerals Processing) project In The Boddington Council Area of Mill Liner Handler/Hydraulic Bolt Removers type. Mill liner handler and hydraulic bolt removers. Click for more details...

BROKEN HILL SEPARATION PLANT UPGRADE
Currently at the Planning stage In Broken Hill is a project estimated to be $ 36000000. This project The upgrade of the separation plant is proposed to take into account the development of the nearby Snapper project. Upgrades will be undertaken for the plant itself and associated infrastructure. The plant upgrades planned are the additions of a rutile circuit and a zircon circuit. An option to locate a Wet High Intensity Magnetic Separator circuit from the mine site is also proposed. These addition will production to increase from 576,000 tpa to 650,000 tpa. The rutile, ilmenite and zircon circuit feed and rejects stockpiles will all be expanded. The non-magnetic concentrate heavy mineral concentrate receival area will also be expanded. The capacity of the two coal container storages will be expanded from 1000 tonnes to 1500 tonnes. Click for more details...

KING ISLAND SCHEELITE PROJECT - MECHANICAL FOR PRIMARY CRUSHING & SCREENING PLANT
Mechanical - For Primary Crushing/Screening Plant New project In The King Island Council Area. For the provision of mechanical installation for the primary crushing & screening plant. Click for more details...

SUNNYSIDE OPEN CUT COAL PROJECT - CRUSHING & SCREENING PLANT
Mining - Primary And Secondary Processing (Civil works at processing facilities) project In The Gunnedah Council Area of Crushing/Screening Plant type. Crushing and screening plant for 5 year operation of mine at around 1 million/annum. coal will then be trucked to Whitehaven's Gunnedah coal preparation plant. Click for more details...

KING ISLAND SCHEELITE PROJECT - CIVIL WORKS FOR PROCESSING PLANT BUILDING
A project in the TAS Within King Island. For the provision of civil works for the processing plant building. Click for more details...

CLERMONT COAL PROJECT - COAL HANDLING PREPARATION PLANT
Private ownership Mining - Primary And Secondary Processing (Coal Processing) project In The Isaac Regional Council Area for New development. Off site fabrication & installation of 2 major (2500tph) & 3 minor (300tph) conveyors, a dump hopper, a wash plant (300tph). Associated process piping. Click for more details...

MANDALONG COAL OPERATIONS - POWER GENERATION PROJECT
Flares/Pilot Plant/Gas Engines project at 3km southwest of, Morisset, NSW 2264 In The Council Area Of Lake Macquarie of Private. Utilisation of the coal seam/methane bed gas from the mine's underground workings to produce up to 12MW of electricity to be fed into the NSW power grid via the mine's existing high voltage substation. Construction next to the existing methane drainage plant at the Mandalong Mine Access Site of gas flares & installation of multiple gas engines constructed off-site & to be located on formed gravel pads along with associated structures. Click for more details...

GREATER GORGON GAS PROJECT - LNG & CONDENSATE STORAGE TANKS - ANNULAR STANDS
Private ownership Mining - Primary And Secondary Processing (Tankage, Silos) project In The Ashburton Council Area for New development. For the detail, supply, fabrication, testing & prime of Annular Stands. Click for more details...

GREATER GORGON GAS PROJECT - LNG & CONDENSATE STORAGE TANKS - MATERIALS FOR INSTRUMENT MOUNTING & SUPPORTS (REV 1)
New project of Mining - Primary And Secondary Processing (Tankage, Silos) project at On, Barrow Island, WA 6712. For the provision of materials for instrument mounting supports. Click for more details...

MOUNT BOPPY GOLD MINE RECOMMENCEMENT
Mining - Primary And Secondary Processing (Minerals Processing) New project at 46km East of, Cobar, NSW 2835. This type is Mine - Recommencement with Private ownership. Mount Boppy Mine recommencement. Ore to be delivered to the recently refurbished Manuka Silver Mine (formerly Wonawinta Silver Mine) Processing Plant for processing. Click for more details...

CAVAL RIDGE COAL PROJECT - COAL PREPARATION PLANT & RAIL FACILITIES
Mining - Primary And Secondary Processing (Coal Processing) project at 16km south of, Moranbah, QLD 4744 of Coal Preparation Plant/Rail Loadout/Conveyor/Roads type of New development. The proposed Caval Ridge CHPP will have a nominal feed capacity of 2 000 t/h and is capable of processing 14-16 Mt/a to produce a nominal 8 Mt/a of hard coking coal, 5.5 Mt/a of which will be sourced from the Caval Ridge Mine & the balance to come by conveyor from the expanded Peak Downs mine. The facility shall operate seven days per week on a continuous basis. The CHPP will consist of: ROM dump hopper for primary sizing; secondary and tertiary sizers with intermediate screening; raw coal stockpiles with mechanised stacking and reclaim facilities; 2 module coal preparation plant, nominally 1000 tph, per module; product coal stockpiles with mechanised stacking and reclaim facilities; train loadout to the north of the Peak Downs Highway, a conveyor will transport material crossing the highway; reject bin and handling system and ultrafine tailings dewatering system. Water supply to be a combination of site water reuse & a raw water supply via a new off take pipeline from existing bulk pipelines. Process plant water will be recycled to minimise raw water make-up requirements for the site. The product coal will be railed approximately 185km to the Hay Point and/or Dalrymple Bay coal terminals for shipment. Click for more details...

GROSVENOR COAL PROJECT - BULK EARTHWORKS PACKAGE
Mining - Primary And Secondary Processing (Civil works at processing facilities) project at via, Moranbah, QLD 4744 of Bulk Earthworks type of New development. Bulk earthworks for coal operations areas to include drift cut & cover and shotcrete soil stabilisation. Click for more details...

GREATER GORGON GAS PROJECT - LNG & CONDENSATE STORAGE TANKS - BULK PIPE SUPPORTS
Private ownership Mining - Primary And Secondary Processing (Tankage, Silos) project In The Ashburton Council Area for New development. For the provision of bulk pipe supports. Click for more details...

GREATER GORGON GAS PROJECT - LNG & CONDENSATE STORAGE TANKS - SS & CS PIPE & PIPE MATERIALS
Mining - Primary And Secondary Processing (Tankage, Silos) project at On, Barrow Island, WA 6712 of Ss/Cs Pipe/Materials type of New development. For the provision of SS & CS pipe & pipe materials. To include: pipe, flanges, fittings, gaskets & fasteners. Click for more details...

GREATER GORGON GAS PROJECT - CARBON DIOXIDE INJECTION PIPELINE & WELL SITE - SUPPLY OF HIRE VEHICLES
Supply Of Hire Vehicles New project In The Ashburton Council Area. For the supply of hire vehicles (4 x 4 light vehicles). Click for more details...

WHEATSTONE DEVELOPMENT PROJECT - STORAGE & FIELD ERECTED CONDENSATE TANKS - STAINLESS STEEL HEATING CONDUITS
Mining - Primary And Secondary Processing (Tankage, Silos) project In The Ashburton Council Area of Private ownership. For the provision of stainless steel heating conduits. Click for more details...

PILGANGOORA LITHIUM TANTALUM PROJECT - EPC CONTRACT
Mining - Primary And Secondary Processing (Minerals Processing) project for New development. For the provision of engineering, procurements & construction for the Pilgangoora Lithium-Tantalum Project. Click for more details...

Copyright © CoreLogic. All rights reserved. Powered by Cordell Connect