State

Categories

Sub Categories

Click Here to Find Current Projects

List of Mining - Primary And Secondary Processing Projects


LADY ANNIE/MOUNT KELLY COPPER PROJECT - PROCESSING FACILITY
New project of Mining - Primary And Secondary Processing (Piping) project at Adjacent to Lady Loreta Mine 140 Km North West of, Mount Isa, QLD 4825. To construct a 1900 tpa copper SXEW plant and heap leach. Total copper recovery is expected to be 89% of the ore processed. Click for more details...

HISMELT EXPANSION PROJECT
Mining - Primary And Secondary Processing (Civil works at processing facilities) project In The Kwinana Council Area of Earthworks - Preliminary Works type. Concrete works and pipebridges. A vertical package comprising both civil and mechanical works. Includes earthworks, stone column foundations, 10,000 cu m of reinforced concrete foundations and 1,000 tonnes of structural steel pipe racks, associated pipes, ducting and accessories. Click for more details...

MIDDLEBACK RANGES OPERATIONS - PROJECT MAGNET - PROCESSING MODIFICATIONS
Mining - Primary And Secondary Processing (Minerals Processing) project In The Whyalla Council Area of Private ownership. Includes beneficiation facilities, construction of a desuplhurisation plant and conversion of Whyalla pellet plant. Click for more details...

GALONG LIMESTONE OPERATIONS
Eubinal Rd, Galong, NSW 2585 Has Galong Limestone Operations currently at Planning stage. Boral intends to expand the Galong lime operation by installing a 150,000 tonnes per annum vertical shaft lime kiln at the site, subject to regulatory approvals. The acquisition and the kiln installation will involve approximately $30 milliion. The upgrade is expected to be completed by June/July 2004. Click for more details...

WAGERUP ALUMINA REFINERY EXPANSION - THIRD PRODUCTION UNIT CNSTN
Third Production Unit project at Off South Western Hwy, Wagerup, WA 6215 in the Mining - Primary And Secondary Processing (Minerals Processing). A third production unit of over 2 million tonnes. Click for more details...

CUMNOCK NO 1 COLLIERY
Mining - Primary And Secondary Processing (Coal Processing) project In The Singleton Council Area of Mine - Coal type. The mine produces soft coking coal used in Asian steel mills. Coal is loaded at adjacent Ravensworth coal terminal and railed to Newcastle for export. Production for 2006 was 1,416,666 tonnes of raw coal. Click for more details...

DARTBROOK COAL OPERATIONS - KAYUGA
Mining - Primary And Secondary Processing (Coal Processing) project In The Muswellbrook Council Area of Reject Emplacement Works type. Tailings dewatering. Click for more details...

LAKE VERMONT COAL PROJECT - COAL PREPARATION PLANT
New project of Mining - Primary And Secondary Processing (Coal Processing) project at Approx 15 km northeast of, Dysart, QLD 4745. For a 4 Mtpa plant. Click for more details...

AVEBURY NICKEL PROJECT - PROCESSING FACILITY
Private ownership Mining - Primary And Secondary Processing (Minerals Processing) project In The West Coast Council Area for New development. Mill will be designed to process 900,000 tonnes of ore per year and to produce 7500-8500 tonnes of nickel metal per annum. Click for more details...

ROLLESTON COAL PROJECT - STAGE TWO/STAGE THREE
Mining - Primary And Secondary Processing (Coal Processing) project for New development. First production will of one million tonnes approx is expected in late 2005. Stage two to 8 mtpa will require only the purchase of an additional second hand dragline and some minor mobile plant. The crushing and mine site infrastructure for stage one will be sized to handle 8 mtpa.Stage two production levels are expected in 2008. The mine is expected to have a 20 year plus life and has further expansion potential to 12mtpa with additional minor capital. Click for more details...

DRAYTON COAL OPERATIONS
Coal Treatment Unit - Design project at Lot 6 DP 701496, Thomas Mitchell Dr, Muswellbrook, NSW 2333 in the Mining - Primary And Secondary Processing (Coal Processing). The coal treatment unit (CTU) will be a closed working circuit with coal being fed through the existing coal handling plant. The current operation of Drayton requires the CTU in order to produce saleable export quality product for an excess of unsaleable domestic quality production. Click for more details...

EASTERN RANGES PROJECT - PARABURDOO
Eastern Ranges Project - Paraburdoo is currently at the Construction stage, valued at about $ 1000000 it is Includes modifications to plant at existing facilities (brownfields) and new project area (greenfields). Conveyor work involved. Click for more details...

JAGUAR BASE METALS PROJECT - RESOURCE
Mining - Primary And Secondary Processing (Minerals Processing) project In The Leonora Council Area of Private ownership. RC/DC drilling program will undertaken with the intention of doubling the announced resource estimate. Resource estimate of 1,600,000 Mt @ 3.07% Cu, 11.73% Zn, 0.72% Pb, 120 g/t Ag. A proposed underground mining development employing long-hole open stoping techniques. The resource is high-grade copper, zinc and silver. The current mine plan sees the initial development phase of the mine being conducted over an 18 month period. During this time the box cut, decline, main ventilation rise and associated infrastructure will be installed and commissioned. Mine life on the current mine reserves is 6 years, at a design throughput of 350000 tpa of ore. Click for more details...

BENAMBRA BASE METALS PROJECT
18 km northeast from, Benambra, VIC 3900 Has Benambra Base Metals Project currently at Early Planning stage. The Benambra Mine Reopening Study is substantially complete; the principal outstanding matters relate to the Victorian Department of Natural Resources & Environment (DNRE) approval of the Company's Workplan & the level of environmental bonding. Click for more details...

FOSTERVILLE GOLD OPERATIONS
Mining - Primary And Secondary Processing (Minerals Processing) New project at Near Fosterville 20 km northeast of, Bendigo, VIC 3550. This type is Ccd Thickener with Private ownership. Design & suply of CCD thickener. Click for more details...

ILUKA RESOURCES
Mining - Primary And Secondary Processing (Computerised systems for processing equipment) project In The Various Council Area of Private ownership. Includes server management, database support, desktop support, help desk, remote site support, network management including microwave and radio links and full data centre services. Click for more details...

KOGAN CREEK POWER STATION PROJECT - CONCRETE & FINISHING WORKS
New project of Mining - Primary And Secondary Processing (Civil works at processing facilities) project at 9 km south of, Brigalow, QLD 4412. Procurement, (fabrication) and erection of: 36,500 m³ concrete for foundations, walls, columns, ceilings and turbine foundation. 3,500 to reinforcement, 49,000 m² formwork for foundations, walls, columns, ceilings and turbine foundation. 1,570 m³ Brickwork 17,5 cm to 36,5 cm thickness, 600 m² Brickwork 12 cm thickness, 8,770 m² Plastering of walls, columns, ceilings, 24,300 m² Painting of walls, columns, ceilings, 2,150 m² Ceramic tiles for walls and floors, 2,200 m² Carpet tiles / linoleum flexible sheets, 2,000 m² Suspended ceilings, 350 m² Raised floors, 210 No Toilets, washbasins, showers, urinal. Click for more details...

GOLDEN GROVE ZINC/COPPER OPERATIONS - RESOURCE
A project in the WA Within Yalgoo. Golden grove operations comprises the Gossan Hill copper, zinc, gold and silver underground mine, the Scuddles zinc and copper underground mine, a 1.3 million tpa treatment plant and a surrounding tenement package. Resource base totals 17 mt@5.9% zinc, 1.9% copper, 0.9% lead, 64g/t silver and 1.3g/t gold. Metal contained is 1,000,000 tonnes of zinc, 314,000 tonnes of copper, 155,000 tonnes of lead, 35 Moz of silver and 0.7 Moz of gold. Reserves are 4.8 Mt at 6.9% zinc, 2.1 copper, 0.9% lead, 75 g/t silver and 1.3 g/t gold. Click for more details...

TEXAS SILVER PROJECT - TWIN HILLS
Surface Infrastructure project at via, Texas, QLD 4385 in the Mining - Primary And Secondary Processing (Civil works at processing facilities). Likely to be small scale infrastructure requirements, including demountables. Some demountables are already in place for administration of exploration project. Only 1-2 additional demountables likely to be required. Likely to be sourced locally. NO accommodation requirements, as the project is located only 7 km from Texas. Heap leach operation will require earthworks to prepare leach pads. Likely to be part of mining operation. Click for more details...

PILBARA IRON ORE & INFRASTRUCTURE PROJECT - PORT HEDLAND PORT FACILITIES
Currently at the Construction stage In Port Hedland is a project estimated to be $ 689700000. This project Port facilities comprise a stockyard at 2.5 Mt capacity. Materials handling facility comprising a Train unloader, 22 Conveyors and transfer points, Rescreening plant , two Stackers (8000 tph each), a Reclaimer (10,000 tph), two 300,000 tonne stock piles and a bulk stockpile area. The Materials handling facility will use a rotary car dumping cell to simultaneously tip two ore carriages. Iron ore from each wagon will be dumped into individual surge hoppers and then onto conveyors located at the base of the structure which will deliver the ore through an upward sloping tunnel to the nearby stockpiling area. In order to house the the Train Loader a 22 metre high concrete vault will be constructed to allow ore carriages to be tipped in an efficient manner. Extensive excavation work will be required because approxiamtely 18 metres is below existing ground surface. An associated ramp and conveyor system will be constructed. During excavation construction a significant ammount of dewatering will be required. Port development will include a proposed 750m long single wharf, a Shiploader (10,000 tph), 3.3 million cubic metres of dredging with ongoing maintenance dredging, shipping berth to allow for two 250,000 DWT vessels to be berthed. One berth includes wharf and shiploader. The other includes a berth only. Supporting infrastructure includes a shift office, control room and amenities, wharf amenities, package treatment plant and substations. Click for more details...

MIDDLEBACK RANGES OPERATIONS - PROJECT MAGNET - CRUSHING/SCREENING EQUIPMENT
Crushing/Screening Equipment project at North west of, Whyalla, SA 5600 in the Mining - Primary And Secondary Processing (Minerals Processing). Project Magnet involves conversion of Whyalla steelworks to produce steel from magnetite rather than haematite ore. This will extend the life of the steelworks to at least 2027. Click for more details...

MANDALONG COAL OPERATIONS - METHANE GAS DRAINAGE PLANT
Methane Gas Drainage Plant - Construct/Operate project at 3 km south west of, Morisset, NSW 2264 In The Council Area Of Lake Macquarie of Private. The coal haulage is 1,000 tonnes by road to Eraring and/or Vales Point power stations contract is likely to be added to existing contractor. The likely method to be used for the Methane Gas Drainage Plant at the first stage is to purge the gas to atmosphere using one of two options. A decision will be made by mid February 2005 on which option is to be used. Click for more details...

DARWIN EAST ARM WHARF - BULK MATERIALS HANDLING INFRASTRUCTURE PROJECT
Mining - Primary And Secondary Processing (Civil works at processing facilities) project In The Darwin City Council Area of Private ownership. Expressions of interest are sought to design, procure and construct common user bulk materials handling facilities for the export of bulk ore. The package includes rail and road bottom dump facilities, including an associated conveyor system to a stockpile area and headworks and a ship loader and associated headworks. Click for more details...

NORTH WEST SHELF LNG TRAIN 5 PROJECT - SITE PREPARATION/TEMPORARY FACILITIES
Mining - Primary And Secondary Processing (Civil works at processing facilities) project at Burrup Peninsula north of, Dampier, WA 6713 of Site Preperation/Temporary Facilities Services Contract - Erect type of New development. The contract involves the re-routing of existing roads near the site, the construction of new roads, rundown and drainage culverts. The provision of bulk earthworks. Removal of redundant process plant and structures on the site, the relocation of plant services and utilities. Installation of temporary facilities including security and safety infrastructure, offices, crib rooms and ablution areas. Click for more details...

ENDEAVOR BASE METAL OPERATIONS - COPPER RECOVERY CIRCUIT
Mining - Primary And Secondary Processing (Minerals Processing) project at 40 Km North west of, Cobar, NSW 2835 for New. Copper recovery circuit is in design. Construction is expected to commence shortly. Testwork and detailed design has been completed. The circuit will treat the lead concentrate to extract a copper concentrate estimate to be 1000 tonnes of copper per annum. Click for more details...

YABULU NICKEL REFINERY EXTENSION - WATER TREATMENT/RETICULATION CONTRACT
Water Treatment & Reticulation Contract New project In The Townsville City Council Area. The existing standby turbine alternator will be changed to generate power as required in conjuction with other units on site. The low pressure steam exhausted from the turbine in addition to other steam supplies on site will be reticulated throughout the site to the new plant for heating and process requirements. The capacity of the existing cooler water systems will be expanded involving water treatment and reticulation. Click for more details...

BHP PORT HEADLANDS EXPANSION - RAPID GROWTH 2 - STRUCTURAL/MECHANICAL CONTRACT
Currently at the Planning stage In Port Hedland is a project estimated to be $ 65000000. This project Structural and mechanical work to be carried out at the existing Finucane Island and Nelson Point facilities. Click for more details...

RAVENSTHORPE NICKEL PROJECT - HIGH ALLOY ITEMS/PIPE SPOOLS
Currently at the Construction stage In Ravensthorpe is a project estimated to be $ 100000. This project Fabrication of high alloy items and pipe spools. Click for more details...

KALGOORLIE SUPERPIT GOLD MINE - CYANIDE PIPING UPGRADE
Mining - Primary And Secondary Processing (Minerals Processing) project at 15 Km North of, Kalgoorlie, WA 6430 of Fimiston Cil Plant/Gidji Roaster Upgrade type of New development. Fabrication and installation of 316l stainless steel piping, high quality diaphragm valves and flanges with suitable transparent flange covers for extra protection. Click for more details...

SARAJI COAL MINE THICKNER PLANT CONVERSION
Mining - Primary And Secondary Processing (Piping) project In The Isaac Regional Council Area of Private ownership. A 35m thickner plant was installed in 2004 and will be upgraded to improve efficiency of tailings disposal. Work comprises the design, removal of existing equipment, civil construction, installation of the high rate thickner. Associated works involve piping, pumps, structural and mechanical works. Electrical installation and recommissioning are also part of the work. Click for more details...

CAMBERWELL COAL OPERATIONS - FLOATATION CIRCUIT
Mining - Primary And Secondary Processing (Coal Processing) New project at Bridgeman Rd, Singleton, NSW 2330. This type is Floatation Circuit - Design/Supply/Commission with Private ownership. Long lead items have been ordered. Click for more details...

SONOMA COAL PROJECT - COAL HANDLING PREPERATION PLANT - STAGE 1
Mining - Primary And Secondary Processing (Coal Processing) New project at 7 Km South of, Collinsville, QLD 4804. This type is Coal Handling Preperation Plant - Stage 1 with Private ownership. Subcontract packages include: Train Loadout Bin - fab/install; ROM Hopper - fab/install; conveyor - fab/install; Motor Control Centre; Concrete Works; and, High Voltage Reticulation. Click for more details...

DAANDINE GAS PROJECT - POWER STATION CIVIL WORKS CONTRACT
Mining - Primary And Secondary Processing (Civil works at processing facilities) project In The Western Downs Regional Council Area of Civil Works Contract type. Civil works for a new power station. Click for more details...

TOM PRICE IRON ORE OPERATION - CIVIL WORKS CONTRACT
Mining - Primary And Secondary Processing (Civil works at processing facilities) project for New development. Work comprises civil and concrete works for the Vault, Rail Stacker and miscellaneous concrete works at the Tom Price mine. Click for more details...

DALRYMPLE BAY COAL TERMINAL EXPANSION - LAND RECLAIMATION
Private ownership Mining - Primary And Secondary Processing (Civil works at processing facilities) project In The Mackay Regional Council Area for New development. Reclaim land for a surge bin. Click for more details...

PROMINENT HILL GOLD/COPPER PROJECT - CONCENTRATE FILTER
Mining - Primary And Secondary Processing (Minerals Processing) project at 100 Km South East of, Coober Pedy, SA 5723 of Concentrate Filter type of New development. Supply of one automated pressure concentrate filter including supporting framework, hydraulic unit, control panel, load cells and ancillary equipment. Automatic operations include filtration, diaphragm pressing, air drying and cake discharge / cloth washing. Size - 132 m2 filter area, 22 plates 66tph instantaneous 12 min/cycle. Click for more details...

TAHMOOR COLLIERY - DRIFT CONVEYOR STAGE 3 UPGRADE - CIVIL WORKS - CONCRRETE FOR BUILDING & MEZZANINE FLOOR
Mining - Primary And Secondary Processing (Civil works at processing facilities) project In The Wollondilly Council Area of Civil Works - Concrete For Builing/Mezzanine Floor type. Work is to coincide with the next dry season longwall changeover in 2008. Click for more details...

PROMINENT HILL GOLD COPPER PROJECT - LINEAR SCREEN
100 Km South east of, Coober Pedy, SA 5723 Has Prominent Hill Gold Copper Project - Linear Screen currently at Construction stage. Linear Screen Click for more details...

MIDDLEMOUNT COAL PROJECT - CONSTRUCT & OPERATE COAL HANDLING & PREPARATION PLANT
Mining - Primary And Secondary Processing (Coal Processing) project In The Isaac Regional Council Area of Private ownership. Includes 10 year operations contract operating the coal handling & preparation plant at 400 tonnes per hour. Click for more details...

LAKE VERMONT COAL PROJECT - CONCRETE WORKS FOR COAL PREPARATION PLANT
A project in the QLD Within Isaac Regional. For a 4 Mtpa plant. Click for more details...

LAKE VERMONT COAL PROJECT - ELECTRICAL FOR COAL PREPARATION PLANT
Approx 15 km north east of, Dysart, QLD 4745 Has Lake Vermont Coal Project - Electrical For Coal Preparation Plant currently at Construction stage. For a 4 Mpta plant. Click for more details...

MOUNT GARNET TIN & IRON PROJECT
Private ownership Mining - Primary And Secondary Processing (Minerals Processing) project In The Tablelands Regional Council Area for New development. A project covering the Gillian, Pinnacles & Windermere localities on the historic Herberton tin field. A tin resource estimate of 7.3million tonnes (Mt) with iron estimates of 3Mt @ 30.8% at Gillian, 1.87Mt at Pinnacles (Wafer) & 400,000t at Deadmans Gully (Windermere). A fluorite estimate also for Pinnacles (Hartog, Llashram, Sniska, Wafer) of 0.96Mt @ 15%. A scoping study envisaged 7.5years life-of-mine (LoM) for operations in the project area at a rate of 700,000tpa producing 236,600tpa of magnetite concentrate grading 65%. Click for more details...

KWINANA TITANIUM DIOXIDE PIGMENT PLANT - PIPING CONTRACT
Mason Rd, Kwinana, WA 6966 Has Kwinana Titanium Dioxide Pigment Plant - Piping Contract currently at Planning stage. For the provision of piping services & associated works. Click for more details...

WEST CLIFF COLLIERY WASHERY UPGRADE
New project of Mining - Primary And Secondary Processing (Coal Processing) project at 4km southeast of, Appin, NSW 2560. Upgrade of the West Cliff Washery over the life of the Bulli Seam Operations Project to handle up to 105Mtpa throughput. To include installation of new components such as rotary breaker & screen house, coarse & fine coal storage bins, triple roll crusher, small coal circuit modules (eg desliming screens, primary & secondary cyclones, centrifuges), flotation cells & a teetered bed separator, coal & tailings thickeners, belt filters & tailings presses. Replacement of the existing Baum jig with a dense medium drum. Upgrades of existing conveyor systems, piping, pumps, sumps, safety & auxiliary systems. Upgrades of power supply systems to provide additional capacity & back up supply. Click for more details...

BARALABA COAL OPERATIONS EXPANSION MIA
Mining - Primary And Secondary Processing (Tankage, Silos) project at near, Baralaba, QLD 4702 for New. Construction of all infrastructure associated with 20 year expansion for central, south & north pits. To include workshops, wash down area, administration, fuel tanks, water & sewerage treatment & other civil infrastructure. Concrete, structural steel, civil/earthworks, hydraulics & drainage, piling & electrical works. Click for more details...

GREATER GORGON GAS PROJECT - LNG & CONDENSATE STORAGE TANKS - SS CABLE LABLES & FERRULES (MR-17100)
Mining - Primary And Secondary Processing (Tankage, Silos) project at On, Barrow Island, WA 6712 for New. For the provision of SS cable lables & ferrules heat shrinkable tubes. Click for more details...

KOOLAN ISLAND IRON ORE OPERATIONS EXPANSION - ACACIA EAST
Mining - Primary And Secondary Processing (Crushing, Screening, Quarrying) New project at Offshore island, 130km north of, Derby, WA 6728. This type is Operating Mine - Expn with Private ownership. Expansion of operations to 4 million tonnes per annum (Mtpa) through the Acacia East Pit Cutback project. The Acacia Pit, located between the existing Mullet & Barrumundi West/East pit, was previously mined as a bermless footwall and it will now involve deepening the existing pit & extending the pit to the east. The pit will be mined through mainly sandstone & schist on the hanging wall (south wall) & siltstone on the footwall (north wall) with waste to be used as backfill. Open pit mining of the ore bodies will be undertaken and the ore will be identified by blast hole sampling and in-pit grade control procedures before hauling direct to the processing area for crushing by existing plant. Click for more details...

NIMBUS VHMS PROJECT - LEACH TANK CIRCUIT WORKS CONTRACT
Mining - Primary And Secondary Processing (Minerals Processing) project for New development. For the provision of contract works. Click for more details...

WINDIMURRA BENEFICIATION PLANT
Mining - Primary And Secondary Processing (Minerals Processing) project In The Mount Magnet Council Area of Private ownership. Design & construction of a beneficiation plant at Windimurra. Click for more details...

PILGANGOORA LITHIUM TANTALUM PROJECT - EPC CONTRACT
Mining - Primary And Secondary Processing (Minerals Processing) project for New development. For the provision of engineering, procurements & construction for the Pilgangoora Lithium-Tantalum Project. Click for more details...

Copyright © CoreLogic. All rights reserved. Powered by Cordell Connect