State

Categories

Sub Categories

Click Here to Find Current Projects

List of Mining - Primary And Secondary Processing Projects


ALCAN GOVE BAUXITE OPERATIONS - REFINERY EXPANSION - INFRASTRUCTURE
Mining - Primary And Secondary Processing (Tankage, Silos) New project at Gove Peninsula, North West Arnhem Land via, Nhulunbuy, NT 0880. This type is Infrastructure with Private ownership. Refinery expansion will increase production from a current 2 Mt/y to 3.8Mt/y in 2007. All new process areas will be concrete bunded with sumps installed. Stormwater drainage and utilities will be extended to all new areas and facilities. The existing sewerage treatment facility will be upgraded by the addition of seperate reticulation and package sewerage plants. Proposed expansion includes stockpiling and handling. Bauxite will not be exported from Gove anymore but will be directed to the refinery. Stockpile sizes will remain the same, but stacker and feed conveyor systems will be upgraded or replaced and the refinery reclaimer will also be replaced. Three new grinding mills will be installed to replace the old rod and ball mills. One new mill slurry tank and pump transfer system together with one train of indirect mill slurry equipment will be installed. The heated feed will now be processed in a new high temperature double digestion process. A third low temperature digestion plant will be installed, as well as deep-cone thickners and high pressure pumps. The mud and liquor residue will be seperated in pressure decanters and processed through a train of new high rate washers and a single train of five deep cone thickners. The existing washers and thickners will be used for storage of residue liquids. Some will be demolished. Six new vertical pressure filters will be installed in a new security filtation area to process most of the turbid liquor flow from the thickners. Agglomeration precipitators and growth precipitators will be added to increase capacity as well as two interstage cooling facilities will be installed on each growth precipitator train. Flash vessels and a barometric condenser will be installed using cooling water from new cooling towers. A new hydrocyclone classification system with three classification stages allowing three different sized hydrate streams to be produced will be installed. A new filtration area and equipment will be installed to conduct filtration of various hydrate streams. Equipment will include six drum filters, vacum pumps and air blowers. Three new stationary calciners will be installed in conjunction with new hydrate conveyors and upgraded aluminia transfer systems. A new evaporation plant will be installed as well as cooling towers for vapour removal in the last three flash stages. Lime plant capacity will be increased from 140 t/h to 200 t/h by installing a new burner system and modifying the kiln's internal geometry. A new burnt lime storage silo will be installed. The existing power station will be converted from fuel oil to gas that will involve a new boiler and associated turbine units. The neutralisation plant will include a mixing tank and two thickners in a bunded area. New liquor purification plant will be constructed involving two seperate plants for the mixing and drying stage. Click for more details...

PILBARA IRON ORE & INFRASTRUCTURE PROJECT - MOUNT NICHOLAS
Mining - Primary And Secondary Processing (Minerals Processing) New project at North east of, Newman, WA 6753. This type is Resource - Iron Ore with Private ownership. Resource estimate is 390 Mt. The ore at Mount Nicholas will be benificiated. Strip mining with progressive backfilling of the open pit will be the preferred mining method. Infrastructure to be constructed and shared at Mount Nicholas, Mount Lewin, Christmas Creek and Cloud Break will comprise a semi-mobile crusher; overland conveyors; haul road and or rail to benificiation plant; haul roads and access tracks; secondary crushers; screening plant; benificiation plant; iron ore product stockpile and train loading facilities; mobile plant and machinery workshop; construction of 132 kv transmission line to Newman with capcity upgrade at Newman or a 45 MW power station (to be provided and maintained by an external supplier); bulk hydrocarbon storage facility; explosive,detonater and magazines; Accommodation and camp facilities, administration and ancillary support facilities; concrete batching plant (during construction), 11 Glpa water supply from borefield supplemeted by mine dewatering; a reverse osmosis plant for portable water use. Click for more details...

WHIM CREEK COPPER PROJECT
Infrastructure project at Via, Whim Creek, WA 6718 In The Council Area Of City Of Karratha of Private. Crushing & stacking facilities, site layout, crusher area works. Surplus plant from Girilambone to be utilised. A conventional SX-EW operation. Click for more details...

NULLAGINE PROJECT - BULLFINCH CIP PLANT
Nullagine Project - Bullfinch Cip Plant is currently at the Early Planning stage, valued at about $ 500000 it is The former Bullfinch CIP plant is in working order. Conveyors are in good order. Leaching tanks were demolished and are likely to be replaced (a train of 6 leaching tanks). Some chutes will need to be ordered. Components required for refurbishment subject to scoping study. Click for more details...

COBURN MINERAL SANDS PROJECT - WET CONCENTRATOR
New project of Mining - Primary And Secondary Processing (Other processing including salt, sand etc) project at South of, Hamelin Pool, WA 6532. 2200 tonne per hour wet concentrator. Click for more details...

CUMNOCK NO 1 COLLIERY
Mining - Primary And Secondary Processing (Coal Processing) project In The Singleton Council Area of Mine - Coal type. The mine produces soft coking coal used in Asian steel mills. Coal is loaded at adjacent Ravensworth coal terminal and railed to Newcastle for export. Production for 2006 was 1,416,666 tonnes of raw coal. Click for more details...

YANDICOOGINA IRON ORE OPERATIONS
A project in the WA Within East Pilbara. Expansion to 36 million tpa .Some conveyor work involved. Flow modifications. A current project to increase output to 24 million tonnes per annum is nearing completion. Click for more details...

MOUNT OWEN COAL OPERATIONS - CHPP UPGRADE
Mining - Primary And Secondary Processing (Coal Processing) project In The Singleton Council Area of Private ownership. An upgrade of the Mount Owen CHPP to allow for increased throughput up to 14 Mtpa (likely to include coal from Ravensworth East and Glendell), and increase the approved capacity of the rail loading facility. Click for more details...

CHARIOT GOLD PROJECT - WARREGO TREATMENT PLANT
Mining - Primary And Secondary Processing (Minerals Processing) New project at West of, Tennant Creek, NT 0860. This type is Long Lead Equipment Items with Private ownership. Consep are supplying the concentrator. Orders for cyclones, silo and mill linings likely to be placed shortly. Click for more details...

MOUNT LYELL COPPER/GOLD OPERATIONS
Mining - Primary And Secondary Processing (Minerals Processing) project at 2 km northeast of, Queenstown, TAS 7467 of Ore Crushing Plant - Study/Install /Operate type of New development. The Mount Lyell mine utilizes the sub-level caving method for mining the ore. The ore is processed through a conventional crushing, grinding, flotation and filtration circuit to produce copper concentrates which are exported. Expressions of interest are invited from interested parties who can undertake a study to increase the ore crushing capacity to the desired level between 3.2 to 3.5 Mtpa, install the necessary plant & equipment to achieve the same and operate it for a period of 6 months to prove the new capacity. At the end of this period, the plant will be handed over to Copper Mines of Tasmania for an agreed consideration. Click for more details...

RAV 8 NICKEL OPERATIONS - RESOURCE
Mine - Nickel project at North east of, Ravensthorpe, WA 6346 In The Council Area Of Ravensthorpe of Private. A mining study has identified economic ore in close proximity to the existing mine infrastructure. A program of underground mining has commenced for 3 months and then an evaluation study will be conducted. Click for more details...

LEICHARDT COPPER OPERATIONS - MOUNT CUTHBERT- PROCESSING PLANT
Private ownership Mining - Primary And Secondary Processing (Minerals Processing) project In The Cloncurry Shire Council Area for New development. The plant is a 5500 tpa solvent extraction/electrowinning (SX/EW) facility with associated leach pad and pond system. Supporting infrastructure includes roads, airstrips, power station, water supply, environmental protection facilities and an accommodation village. Click for more details...

MONTO MINERALS INDUSTRIAL MINERALS PROJECT - WET SEPERATION PLANT
Mining - Primary And Secondary Processing (Other processing including salt, sand etc) project for New development. Wet Seperation Plant that will constructed next to the existing pilot plant. The plant will use non chemical seperation using gravity and magnetics. Plant is expected to process 142,000 tonnes in 2007 and 232,000 tonnes in 2008. Click for more details...

TRITTON COPPER PROJECT
Mining - Primary And Secondary Processing (Civil works at processing facilities) project In The Bogan Council Area of Private ownership. Includes a 660,000 tpa copper concentrator (expandable to 900,000 tpa), a tailings dam and surface infrastructure such as roads and bridges. Click for more details...

CSA COPPER OPERATIONS - CONCRETE REMOVAL
Mining - Primary And Secondary Processing (Minerals Processing) project In The Cobar Council Area of Concrete Removal type. This package may be combined with Steel Work contract ID: 2155418. Decision is yet to be made whether concrete may be replaced with steel flooring. Click for more details...

PINJARRA ALUMINA REFINERY EFFICIENCY UPGRADE
Pinjarra Alumina Refinery Efficiency Upgrade is currently at the Construction stage, valued at about $ 100000 it is Boxed bends. Click for more details...

FOSTERVILLE GOLD OPERATIONS
Fosterville Gold Operations is currently at the Tenders & Building stage, valued at about $ 500000 it is One package for dosing pumps and another for peristatic pumps (hose pumps) . Click for more details...

LAKE VERMONT COAL PROJECT - PREPARATION PLANT - OPERATION
Preparation Plant - Operation project at Approx 15 km north east of, Dysart, QLD 4745 In The Council Area Of Isaac Regional of Private. for a 4 Mtpa plant. Click for more details...

BROWNS OXIDE PROJECT - PROCESSING PLANT/ LEACHING FACILITIES
Processing Plant/Leaching Facilities project at South East of, Darwin, NT 0800 in the Mining - Primary And Secondary Processing (Minerals Processing). The plant will treat 1.3 million tonnes per year. All major items of equipment for the plant have been acquired including grinding and classification circuit, Cawse solvent extraction, electrowinning plant, thickners and tanks have also been acquired. Other equipment is being custom designed and fabricated offsite. Detailed engineering design works of the plant are in progress. Finalisation of processing plant flowsheet and confirmatory metallurgical testwork are also in progress. Testwork has already shown that the valuable copper, cobalt and nickel minerals are dissolved in acid. Once the metals are in the solution, the liquor is separated from the leached solids which are then washed and sent to the tailings storage facility. Testwork is confirming solvent extraction design criteria for concentrating metals in solution ahead of copper electrowinning of high purity cathode product. The facility will comprise a solvent extraction plant, electrowiring plant, tankage and product filtering equipment. Click for more details...

PARDOO IRON ORE PROJECT
Pardoo Iron Ore Project is currently at the Construction stage, valued at about $ 8300000 it is The project is based on an identified iron ore (hematite) resource of approximately 7.4Mt. The project proposes an ore production rate of 1.5 Mtpa, resulting in a mining life of 5 - 6 years. The project involves the open cut mining of eight small pits in five deposits to obtain direct-shipping quality iron ore. The ore will be crushed, screened and stockpiled on site prior to being loaded into rail trains for road haulage to the appropriate berth at Port Hedland. Ore will be stockpiled at the port until it is loaded onto ships for export to overseas customers. The major components of the Pardoo DSO Project are: minesite establishment, mining operations, product transport and export and decommissioning and closure. The minesite access road and temporary construction yard and administration area will be the first infrastructure constructed. The mining operations centre (MOC) will be located in the northern portion of the minesite and contains the following infrastructure: administration area including Atlas facilities, mining contractor's facilities, crushing and screening contractor's facilities, haulage contractors facilities, sewerage treatment and waste water storage, potable water storage, common parking area. The MOC will also contain a fuel storage and refuelling area, power station (diesel), crushing and screening plant, ROM ore pad and product stockpiling area, parking areas and portions of the access road and haul road, and combined contractor's laydown area. Haul roads will be constructed between the pits, waste rock dumps, stockpiles and ROM pad stockpile. Minor access roads will provide access to waste rock dumps and inspection points, dewatering equipment, water management structures, environmental discharge locations and other minesite management areas. The proposed mining operation will be a multiple, open pit mining operation, using conventional drill and blast and load and haul methods. Ore from the pits will be hauled directly to the ROM pad or temporarily stockpiled adjacent to the pits. The crushing and screening plant will provide primary and secondary crushing and screening. Click for more details...

BURNAKURA - UPGRADE/REFURBISHMENT GOLD PROCESSING PLANT
Mining - Primary And Secondary Processing (Minerals Processing) New project at 60 Km South East Of, Meekatharra, WA 6642. This type is Processing Plant - Upgrade/ Refurbishment with Private ownership. The plant will be upgraded to include milling capacity of the NOA2 ore. The refurbishment will include the electrical reticulation being replaced. Also various drives and ancillary equipment will be installed at the plant. Additional power generation will be supplied by a 3.5Mw Power station. Click for more details...

NORTH WEST SHELF LNG TRAIN 5 PROJECT - SITE PREPARATION/TEMPORARY FACILITIES
Mining - Primary And Secondary Processing (Civil works at processing facilities) project at Burrup Peninsula north of, Dampier, WA 6713 of Site Preperation/Temporary Facilities Services Contract - Erect type of New development. The contract involves the re-routing of existing roads near the site, the construction of new roads, rundown and drainage culverts. The provision of bulk earthworks. Removal of redundant process plant and structures on the site, the relocation of plant services and utilities. Installation of temporary facilities including security and safety infrastructure, offices, crib rooms and ablution areas. Click for more details...

YABULU NICKEL REFINERY EXTENSION - SITE WIDE CONCRETE CONTRACT
New project of Mining - Primary And Secondary Processing (Civil works at processing facilities) project at Refinery site at, Yabulu, QLD 4818. Scope of work involves concrete work to the entire refinery site. Click for more details...

MIDDLEBACK RANGES OPERATIONS - PROJECT MAGNET - EXPORT FACILITIES UPGRADE
Port of, Whyalla, SA 5600 Has Middleback Ranges Operations - Project Magnet - Export Facilities Upgrade currently at Construction stage. Construction and upgrade of a hematite export facilities at the Port of Whyalla. Click for more details...

MOUNT NORMA LEACH VAT NUMBER FIVE
Mining - Primary And Secondary Processing (Crushing, Screening, Quarrying) project In The Cloncurry Shire Council Area of Private ownership. Construction will comprise earthworks, lining of the vats, filters, electrical installation, crushing and loading of the vats. The vat is to contain 30,000 tonnes of high leach copper oxide. Click for more details...

AUGUSTA GOLD PROJECT - EARTH WORKS/BOX CUT CONTRACT
Heathcote Nagambie Road, Bendigo, VIC 3550 Has Augusta Gold Project - Earth Works/Box Cut Contract currently at Construction stage. Development option is to construct an underground portal on C Lode where approximately 5000 tonnes of ore can be extracted. As part of the earthworks component the contractor will will construct an evaporation pond and do the creek diversion work. Click for more details...

WORSLEY ALUMINA EFFICIENCY/GROWTH PROJECT - ELECTRICAL CONTRACT
Electrical Work For Temporary Facilities/Infrastructure/Process Plant project at 15 Km South east of, Collie, WA 6225 in the Mining - Primary And Secondary Processing (Minerals Processing). Work for the Electrical, Instrumentation & Control - Infrastructure package includes Power Distribution, Instrumentation and Control System Infrastructure to the Refinery, Mine and Port inclusive of materials handling facilities. Battery limits include the 132kV WPC tie-in, 11.5kV power distribution to EDCs and 415/240V Distribution Boards and MCCs as well as the control system from the Central Control Room to the Marshalling Panels within the EDCs. Work for the Electrical, Instrumentation & Control - Process Plant includes Power, Instrumentation and Control from the field side of the MCCs, Distribution Boards and Control Marshalling Panels within the EDCs to the Refinery, Mine and Port inclusive of materials handling facilities. Click for more details...

WORSLEY ALUMINA EFFICIENCY/GROWTH PROJECT - 415 V MOTOR CONTROL CENTRES & LOAD CENTRES
Mining - Primary And Secondary Processing (Minerals Processing) project at 15 Km South east of, Collie, WA 6225 of 415 V Motor Control Centres/Load Centres - Supply type of New development. 415 V Motor Control Centres (MCC) and Load Centres. Click for more details...

PROMINENT HILL GOLD/COPPER PROJECT - CYCLONE FEED PUMPS
100 Km South East of, Coober Pedy, SA 5723 Has Prominent Hill Gold/Copper Project - Cyclone Feed Pumps currently at Construction stage. Supply of one hard metal slurry pump complete with drive assembly, cooling fan, motor, couplings, in-line fabricated drive base plate, guards, base frame, lifting lugs and lifting chains for wet end assemble, packed gland seal with gland water flow restrictors, fan cooled oil cooler (including circulating pump and non return valve) for gear box, instrumentation, factory assembly, drive alignment, hydro-testing and acceptance testing. Size - 4310m3/h @ 43m TDH. Click for more details...

LIDDELL COAL OPERATIONS - COAL HANDLING PREPARATION PLANT
Coal Handling Preparation Plant project at 20 Km North West of, Singleton, NSW 2330 In The Council Area Of Singleton of Private. Construction of a new Coal Handling Preparation Plant. This will involve the construction of a new preparation section, upgrades to the ROM receival and product coal facilities. The new preparation area will be located next to the old CHPP and its capacity will be 1200 tonnes per hour. This will include new screening, cyclone and spiral components for the plant. Upgrades to the ROM receival equipment include shortening of the apron feeder, a new rotating star wheel, new sizers and an increase in the drive power and length of the ROM conveyor. Modifications to the product handling equipment will include a short product conveyor to collect coal from the new CHPP to be deposited at a new transfer station onto the existing product stockpile rising conveyor. The existing road truck type coarse rejects bin will be replaced by a larger bin capable of loading mining sized trucks. The exisiting CHPP will be dismantled and recycled or disposed of over a one year period. Click for more details...

PROMINENT HILL GOLD COPPER PROJECT - REGRIND MILL
Mining - Primary And Secondary Processing (Minerals Processing) project In The Coober Pedy Council Area of Private ownership. Regrind Mill. Click for more details...

BROKEN HILL SEPARATION PLANT UPGRADE
Currently at the Planning stage In Broken Hill is a project estimated to be $ 36000000. This project The upgrade of the separation plant is proposed to take into account the development of the nearby Snapper project. Upgrades will be undertaken for the plant itself and associated infrastructure. The plant upgrades planned are the additions of a rutile circuit and a zircon circuit. An option to locate a Wet High Intensity Magnetic Separator circuit from the mine site is also proposed. These addition will production to increase from 576,000 tpa to 650,000 tpa. The rutile, ilmenite and zircon circuit feed and rejects stockpiles will all be expanded. The non-magnetic concentrate heavy mineral concentrate receival area will also be expanded. The capacity of the two coal container storages will be expanded from 1000 tonnes to 1500 tonnes. Click for more details...

IRON ORE RAPID GROWTH 4 PROJECT - TRAIN LOAD OUT
Iron Ore Rapid Growth 4 Project - Train Load Out is currently at the Planning stage, valued at about $ 100000000 it is The new TLO facility will match the existing train load-out plant for through train capacity at 58Mtpa. The new TLO will comprise a new section of rail passing through a single tunnel that has two loading vaults. Each vault is located under a discrete stockpile, each with a minimum 25,000 live capacity. These stockpiles will be product specific, one for lump and one for fines, to eliminate product cross-contamination. Each stockpile will be built and maintained by a fixed stacker conveyor, fed from the diverter transfer station at the head of the stockyard reclaim conveyor (the transfer station and stacker conveyors are part of work pack 4N0). The conveyors will discharge from fixed cantilever booms. Dust suppression sprays will be mounted at the head of each conveyor discharge. The spray system will be complete with break tank and pumps for the high pressure for the spray canon. The TLO will have dedicated dust extraction/collection and ventilation systems for each of the vaults. Each of the dust systems will comprise dust hoods, ducting, wet scrubbers, extraction fans, seal tank, circulation pumps, sump tanks, pumps and associated pipe work. The complete tunnel with the vaults will have a vault ventilation system complete with fans, ducting, discharge registers and intake silencers. The stockpiles and stacker conveyors will have dust suppression sprays. Process water will be supplied for dust suppression and dust extraction scrubbers. The dust suppression spray system comprises piping, water cannon and controls. Click for more details...

IRON ORE RAPID GROWTH 4 PROJECT - JIMBELBAR - METAL DETECTOR
Currently at the Construction stage In East Pilbara is a project estimated to be $ 250000. This project For the supply of metal detector. Click for more details...

LAKE VERMONT COAL PROJECT - MECHANICAL FOR COAL PREPARATION PLANT
Mechanical - For Coal Preparation Plant project at Approx 15 km north east of, Dysart, QLD 4745 In The Council Area Of Isaac Regional of Private. For a 4 Mtpa plant. Click for more details...

LAKE VERMONT COAL PROJECT - PIPING FOR COAL PREPARATION PLANT
Piping - For Coal Preparation Plant project at Approx 15 km north east of, Dysart, QLD 4745 In The Council Area Of Isaac Regional of Private. For a 4 Mtpa plant. Click for more details...

MURRAY BASIN STAGE 2 - KWR MINERAL SANDS PROJECT - WHIMS MACHINES FOR PROCESSING PLANT
Whims Machines - For Processing Plant New project In The Mildura Council Area. For the provision of 7 wet high intensity magnetic separator (WHIMS) machines for the processing plant. Click for more details...

MURRAY BASIN STAGE 2 - KWR MINERAL SANDS PROJECT - ELECTRICAL FOR WET CONCENTRATOR
A project in the VIC Within Mildura. For the provision of electrical works for the wet concentrator. Click for more details...

CARBOROUGH DOWNS COAL MINE EXPANSION PROJECT - PIPING FOR MECHANICAL EQUIPMENT
Mining - Primary And Secondary Processing (Coal Processing) project In The Isaac Regional Council Area of Private ownership. For the provision of piping for mechanical equipment for the new 5Mpta CHPP. Click for more details...

SINO IRON ORE EXTENSION PROJECT - PROCESSING PLANT
Mining - Primary And Secondary Processing (Other processing including salt, sand etc) New project at Cape Preston 80 km Southeast of, Karratha, WA 6714. This type is Processing Plant - Iron Ore with Private ownership. Construction of a 54 Mtpa Iron Ore Processing Plant. Click for more details...

PINE DALE COAL OPERATIONS - YARRABOLDY EXTENSION
Currently at the Construction stage In Lithgow is a project estimated to be $ 1400000. This project Further operations at the former Yarraboldy open cut pit to extract 800,000t approx of coal over a 3 year period. To commence with construction of an amenity bund prior to 2 years of open cut mining followed by 6 months of final rehabilitation works (minimally backfill/ reshaping/ revegetating of 10.3ha). Construction also of internal roads & a new intersection with the existing private coal haul road crossing. Decommissioning of the existing crushing facility & construction of new plant along with a crushing, stockpiling & maintenance area in the Extension. Click for more details...

GREATER GORGON GAS PROJECT - LNG & CONDENSATE STORAGE TANKS - BULK PIPE SUPPORTS
Private ownership Mining - Primary And Secondary Processing (Tankage, Silos) project In The Ashburton Council Area for New development. For the provision of bulk pipe supports. Click for more details...

GREATER GORGON GAS PROJECT - LNG & CONDENSATE STORAGE TANKS - ROOF PLATE PIECE
Mining - Primary And Secondary Processing (Tankage, Silos) New project at On, Barrow Island, WA 6712. This type is Roof Plate Piece with Private ownership. For the provision of roof plate piece details. Click for more details...

GREATER GORGON GAS PROJECT - LNG & CONDENSATE STORAGE TANKS - SHELL NOZZLE REINFORCING
Mining - Primary And Secondary Processing (Tankage, Silos) project In The Ashburton Council Area of Shell Nozzle Reinforcing type. For the provision of shell nozzle reinforcing. Click for more details...

GREATER GORGON GAS PROJECT - CARBON DIOXIDE INJECTION PIPELINE & WELL SITE - HIRE OF CRANAGE
Hire Of Cranage project at On, Barrow Island, WA 6712 in the Mining - Primary And Secondary Processing (Piping). For the hire of cranage. Click for more details...

GREATER GORGON GAS PROJECT - CARBON DIOXIDE INJECTION PIPELINE & WELL SITE - PRECOMMISSIONING SERVICE
On, Barrow Island, WA 6712 Has Greater Gorgon Gas Project - Carbon Dioxide Injection Pipeline & Well Site - Precommissioning Service currently at Construction stage. For the provision of precommissioning service. Click for more details...

WHEATSTONE DEVELOPMENT PROJECT - STORAGE & FIELD ERECTED CONDENSATE TANKS - CELLULAR GLASS
Currently at the Construction stage In Ashburton is a project estimated to be $ 500000. This project For the provision of cellular glass. Click for more details...

WHEATSTONE DEVELOPMENT PROJECT - STORAGE & FIELD ERECTED CONDENSATE TANKS - WEAVE GLASS
A project in the WA Within Ashburton. For the provision of weave glass. Click for more details...

APLNG LNG PLANT - IT SOFTWARE
Mining - Primary And Secondary Processing (Computerised systems for processing equipment) project In The Gladstone Regional Council Area of It Software - Staff/Change type. For the provision of information technology software including for management of change & staff & shift rostering. Click for more details...

AUSTRALIAN MINES PROCESSING PLANT PERTH
Mining - Primary And Secondary Processing (Minerals Processing) project for New development. Construction of a demonstration size high pressure acid leach & solvent extraction plant to produce offtake samples of cobalt sulphate, nickel sulphate & scandium oxide. Click for more details...

Copyright © CoreLogic. All rights reserved. Powered by Cordell Connect