State

Categories

Sub Categories

Click Here to Find Current Projects

List of Mining - Primary And Secondary Processing Projects in QLD


GOONDICUM CRATER PROJECT
Private ownership Mining - Primary And Secondary Processing (Minerals Processing) project In The North Burnett Regional Council Area for New development. Consultants are to review the plans for the Demonstration Plant utilising the natural slope of the land to reduce construction costs. A design throughput rate of 20 tonnes per hour remains and the plant is planned to run for 75 days to produce a minimum of 1000 tonnes ilmenite, 2400 tonnes feldspar, 300 tonnes apatite and 600 tonnes titano-magnetite. Click for more details...

CRACOW GOLD PROJECT - KLONDYKE/ROYAL SHOOT/CROWN/ROSES PRIDE
Currently at the Construction stage In Banana Shire is a project estimated to be $ 500000. This project CIL tankage. Click for more details...

LADY ANNIE/MOUNT KELLY COPPER PROJECT - PROCESSING FACILITY
New project of Mining - Primary And Secondary Processing (Civil works at processing facilities) project at Adjacent to Lady Loreta Mine 140 Km North West of, Mount Isa, QLD 4825. To construct a 1900 tpa copper SXEW plant and heap leach. Total copper recovery is expected to be 89% of the ore processed. Click for more details...

BLACKWATER COMET CHPP PROJECT
Mining - Primary And Secondary Processing (Coal Processing) project In The Central Highlands Regional Council Area of Prep Plant/Raw Coal Area/Loadout/High Voltage - Design/Const Package (Combined) type. Now includes the Comet CPP Project (Preparation Plant), and all coal handling facilities, as well a high voltage electrical package. Click for more details...

MOUNT GARNET ZINC PROJECT TREATMENT FACILITY EXPANSION
Mining - Primary And Secondary Processing (Minerals Processing) Addition project at Via, Mount Garnet, QLD 4872. This type is Treatment Facility - Expansion/Dedicated Copper Circuit with Private ownership. An upgrade to increase plant capacity from the current 90,000 tonnes of concentrate per annum to 148,000 tonnes per annum. The zinc concentrate output will increase from 70,000 tonnes per annum to 110-120,000 tonnes per annum. A dedicated copper circuit will be installed as part of the upgrade. Click for more details...

YABULU NICKEL REFINERY EXTENSION - COOLING WATER TOWER CONTRACT
Mining - Primary And Secondary Processing (Minerals Processing) project at Refinery site at, Yabulu, QLD 4818 for New. The existing standby turbine alternator will be changed to generate power as required in conjuction with other units on site. The low pressure steam exhausted from the turbine in addition to other steam supplies on site will be reticulated throughout the site to the new plant for heating and process requirements. The capacity of the existing cooler water systems will be augmented by the addition of a new cooling tower to cater for the additional heat loadings. Click for more details...

YABULU NICKEL REFINERY EXTENSION - MHP RECEIVAL/TREATMENT FACILITIES CONTRACT
New project of Mining - Primary And Secondary Processing (Minerals Processing) project at Refinery site at, Yabulu, QLD 4818. Contract package 4 involves a MHP leach area, ammonical solvent extraction area and a stripping stills and gas absorption area. This package involves construction on top of concrete, structural, mechanical, piping, electrical, instrumentation and controls for what are generally hydrometallurgical facilities. The contract involves both greenfield and brownfield work. The MHP Receival & Treatment Facilities include container storage and unloading and primary and secondary leaching facilities. The intermediate product (MHP) from Ravensthorpe will be received at Yabulu where it will be stockpiled in a weatherproof environment prior to feeding into a two stage leaching process. New material handling equipment will be constructed to process the additional MHP. Extension of the existing utilities plant will be required to provide additional power, steam and process gases. This includes a package plant for nitrogen generation by the pressure swing absorption process. Anhydrous ammonia will be imported to supplement ammonia currently produced on site. Click for more details...

KESTREL COAL OPERATIONS
New project of Mining - Primary And Secondary Processing (Coal Processing) project at 49 km north east of, Emerald, QLD 4720. The mine is capable of annual production of up to five million tonnes of high quality metallurgical coal and high energy thermal coal for export markets in Asia and Europe. The lease contains 190 million tonnes of recoverable reserves, part of total coal resources of 289 million tonnes. The purchase includes the nearby Gordonstone West property, which has additional recoverable resources of 126 million tonnes. Click for more details...

GLADSTONE INTERNATIONAL NICKEL PROJECT - MARLBOROUGH
Mining - Primary And Secondary Processing (Minerals Processing) project In The Gladstone Regional Council Area of Processing Plant type. Processing of laterite ore. Ore likely to be sourced from New Caledonia via Cape size shipping through Gladstone's deepwater port, supplemented by ore from the deposits at Marlborough. This is likely to be a two stage development. Stage one to 65,000 tpa producing nickel cobalt suplhide will involve a 4 autoclave plant. Stage two would be likely to involve doubling of capacity. Click for more details...

KOGAN CREEK COAL/POWER STATION PROJECT
Mining - Primary And Secondary Processing (Coal Processing) project In The Western Downs Regional Council Area of Private ownership. Proposed open cut coal mine and associated power station Click for more details...

CRACOW GOLD PROJECT - KLONDYKE/ROYAL SHOOT/CROWN/ROSES PRIDE
Surface Works New project In The Banana Shire Council Area. Includes excavation of box cut. Click for more details...

WILKIE CREEK COAL OPERATIONS
A project in the QLD Within Western Downs Regional. To upgrade the wash plant from 2 to 2.5 mtpa. Click for more details...

TEXAS SILVER PROJECT - TWIN HILLS
Surface Infrastructure project at via, Texas, QLD 4385 in the Mining - Primary And Secondary Processing (Civil works at processing facilities). Likely to be small scale infrastructure requirements, including demountables. Some demountables are already in place for administration of exploration project. Only 1-2 additional demountables likely to be required. Likely to be sourced locally. NO accommodation requirements, as the project is located only 7 km from Texas. Heap leach operation will require earthworks to prepare leach pads. Likely to be part of mining operation. Click for more details...

YABULU NICKEL REFINERY EXTENSION - BOILER REFURBISHMENT
Mining - Primary And Secondary Processing (Minerals Processing) project In The Townsville City Council Area of Boiler No 3 Refurbishment Contract type. An existing boiler will be refurbished to generate high-pressure steam for power generation and process requirements. This boiler will be converted from oil firing to gas firing, utilising coal seam methane gas to be delivered by the new Moranbah to Townsville gas pipeline. A new boiler feedwater plant will also be installed. Click for more details...

YABULU NICKEL REFINERY
Mining - Primary And Secondary Processing (Minerals Processing) project In The Townsville City Council Area of Private ownership. Gas scrubbing system to recover ammonia for re-use. Part of project to increase prodcution of cobalt. Click for more details...

KOGAN CREEK POWER PROJECT
Mining - Primary And Secondary Processing (Tankage, Silos) New project at South of, Brigalow, QLD 4412. This type is Feedwater Tank & Deaerator with Private ownership. High & Low Pressure Preheater: 4 Low Pressure Preheaters, 1 Low Pressure Drains Cooler, 2 High Pressure Feedwater Heaters, 1 Deaerator with Feedwater Storage Tank approx 250m3, 3 Plate Type Heat Exchanger (13MW each). Click for more details...

TEXAS SILVER PROJECT - TWIN HILLS
Mining - Primary And Secondary Processing (Minerals Processing) project at Via, Texas, QLD 4385 for New. Mobile Crushing Plant comprising jaw crusher, screens and core crusher and will be on site early April 2005. Click for more details...

LAKE VERMONT COAL PROJECT - PREPARATION PLANT - OPERATION
Preparation Plant - Operation project at Approx 15 km north east of, Dysart, QLD 4745 In The Council Area Of Isaac Regional of Private. for a 4 Mtpa plant. Click for more details...

COLLINGWOOD TIN PROJECT - PLANT/INFRASTRUCTURE
Mining - Primary And Secondary Processing (Minerals Processing) project at 35 km south of, Cooktown, QLD 4871 for New. Water only gravity concentration process. Click for more details...

YABULU NICKEL REFINERY EXTENSION - CARBONATE FACILITY
Mining - Primary And Secondary Processing (Minerals Processing) project at Refinery site at, Yabulu, QLD 4818 of Basic Nickel Carbonate Facility Contract type of New development. Scope of work involves the construction of two large tanks, a thickner and associated pipework. Click for more details...

YABULU NICKEL REFINERY EXTENSION - SITE WIDE CONCRETE CONTRACT
New project of Mining - Primary And Secondary Processing (Minerals Processing) project at Refinery site at, Yabulu, QLD 4818. Scope of work involves concrete work to the entire refinery site. Click for more details...

YABULU NICKEL REFINERY EXTENSION - AIR COMPRESSORS CONTRACT
Currently at the Construction stage In Townsville City is a project estimated to be $ 5000000. This project The existing standby turbine alternator will be changed to generate power as required in conjuction with other units on site. The low pressure steam exhausted from the turbine in addition to other steam supplies on site will be reticulated throughout the site to the new plant for heating and process requirements. The capacity of the existing cooler water systems will be augmented by the addition of a new cooling tower to cater for the additional heat loadings. Plant and instrument air sustems will be upgraded with the provision of additional air compressor units. Click for more details...

MOUNT NORMA LEACH VAT NUMBER FIVE
Mining - Primary And Secondary Processing (Civil works at processing facilities) project In The Cloncurry Shire Council Area of Private ownership. Construction will comprise earthworks, lining of the vats, filters, electrical installation, crushing and loading of the vats. The vat is to contain 30,000 tonnes of high leach copper oxide. Click for more details...

GOONYELLA RIVERSIDE BROADMEADOW COAL OPERATIONS EXPANSION
A project in the QLD Within Isaac Regional. The project involves an expansion of the existing Goonyella Riverside open cut and the underground operations at Broadmeadow to increase the capacity from 16 Mt/a to 24 Mt/a. Mining and processing will yield a Hard Coking Coal product for the export market. The open cut expansion and underground expansions will result in an additional 5Mt/a and 3Mt/a of product coal respectively. The surface expansion will use the current open cut mining methods, which involve truck and shovel fleets and draglines exposing coal. Most of the open cut spoil from the expanded operations will be disposed of within mined out pits as is the current practice. However, it is expected that some of the spoil will need to be disposed of in out-of-pit spoil dumps. The existing Broadmeadow Mine, which extracts the Goonyella Middle Seam (GMS), will be expanded eastwards using either the conventional longwall mining practices currently being used for its operations or see the introduction of Longwall Top Coal Caving (LTCC) technology once its feasibility is proven as a means to improve the levels of resource recovery compared to conventional longwall mining methods. A second longwall mine is currently under investigation using either conventional longwall methods or LTCC method. The existing mine has much of the necessary infrastructure in place, however, there are infrastructure upgrades required for the expansion of the mine including: a new CHPP and upgrade to the existing CHPP; construction of an additional 66kV feeder adjacent to the present Goonyella 66kV line; expansion of the existing tailings storage facilities to accommodate increased tailings volumes; improvements to the existing mine water management system, including clean water diversion, disturbed area runoff collection and treatment, pit water management, water reuse and water disposal if there is surplus water at any time that cannot be reused on site. The expansion element of the project requires an additional coal preparation capacity of approximately 2 370 tonnes per hour (t/h) to achieve a production rate of 24 Mt/a. The options to achieve this throughput are to expand the existing CHPP's and/or build a new plant to supplement one or both existing plants. The new CHPP is likely to be tied into the existing product handling system. Alternatively a separate train load-out will be constructed on one of the existing rail loops. The product coal will be railed approximately 190km to the Hay Point and/or Dalrymple Bay coal terminals. Click for more details...

DAWSON SOUTH STAGE TWO PROJECT - COAL HANDLING PREPARATION PLANT
Dawson South Stage Two Project - Coal Handling Preparation Plant is currently at the Construction stage, valued at about $ 400000000 it is Development comprises the development of a Coal handling Preparation Plant (CHPP) to process 5 Mtpa. Coal will be delivered by an overland conveyor with the CHPP processing at 2000 tonnes per hour in two stage mode and 3400 tonnes per hour in single stage mode. The plant will comprise six fully automated stacker and reclaimer machines, dense medium cyclones, spirals and flotation circuits. Coal will then be loaded by a high capacity automated reclaimers to a new rail load out facility. Click for more details...

MUNGANA PROJECT PROCESSING PLANT
Private ownership Mining - Primary And Secondary Processing (Minerals Processing) project In The Tablelands Regional Council Area for New development. A polymetallic plant would be constructed to treat lead, zinc and molybdenum sourced from the surrounding deposits at Red Dome and Mungana. The treatment facility will more than double zinc production to 100 000 tonnes of contained zinc resulting in a significant reduction in costs. Click for more details...

MONTO MINERALS INDUSTRIAL MINERALS PROJECT - FELDSPAR WASH PLANT
Feldspar Wash Plant New project In The North Burnett Regional Council Area. Development comprises the construction of a treatment facility that will comprise a hot acid leach plant and associated equipment. The ore will be shipped from the mine to the feldspar plant at Dakiel Railroad Station where it will be loaded and sent to Gladstone and then be shipped to Brisbane. Click for more details...

QUEENSLAND ALUMINA RED MUD DAM REDEVELOPMENT
Dam/Pipeline/Roadworks/Processing Plant project at ., Boyne Island, QLD 4680 in the Mining - Primary And Secondary Processing (Civil works at processing facilities). Containment walls, processing plant, roads & pipes. Click for more details...

DALRYMPLE BAY COAL TERMINAL EXPANSION - LAND RECLAIMATION
Private ownership Mining - Primary And Secondary Processing (Civil works at processing facilities) project In The Mackay Regional Council Area for New development. Reclaim land for a surge bin. Click for more details...

WOLFRAM CAMP PROJECT - PROCESSING PLANT
15 Km North west of, Dimbulah, QLD 4872 Has Wolfram Camp Project - Processing Plant currently at Construction stage. Construction of a 150,000 tpa treatment plant. The developer has sourced a suitable second hand ball mill and is inspecting a second hand front end crushing and screening facility. Click for more details...

DALRYMPLE BAY COAL TERMINAL EXPANSION - MINOR CIVIL/MECHANICAL/STRUCTURAL WORKS
Private ownership Mining - Primary And Secondary Processing (Civil works at processing facilities) project In The Mackay Regional Council Area for New development. Work comprises the contractor to do minor civil, mechanical and structural works on site when needed. Click for more details...

KESTREL COAL UNDERGROUND EXTENSION PROJECT - COAL HANDLING & PREPARATION PLANT UPGRADE
Mining - Primary And Secondary Processing (Coal Processing) project for Addition development. Upgrade to existing coal wash plant to increase production from 1000t/h to 1400t/h. Click for more details...

DALRYMPLE BAY COAL TERMINAL EXPANSION - BUND 4A CIVIL WORKS
Bund 4a Civil Works New project In The Mackay Regional Council Area. To construct Bund 4A. Click for more details...

YARWUN ALUMINA REFINERY EXPANSION
Mining - Primary And Secondary Processing (Minerals Processing) project In The Gladstone Regional Council Area of Private ownership. Expansion of the existing refinery to increase its capacity by 2million tonnes per annum (Mtpa) to 3.4Mtpa. Includes construction of a 160MW, gas-fired cogeneration plant to improve energy efficiency while reducing greenhouse gas emissions. About half the electricity generated by the plant will be used to power the existing & new refinery facilities with the remainder exported to the national electricity grid. By mid 2010 the cogeneration plant had been handed over & the wharf extension & major tank builds had been completed. Click for more details...

LAKE VERMONT COAL PROJECT - CONCRETE WORKS FOR COAL PREPARATION PLANT
A project in the QLD Within Isaac Regional. For a 4 Mtpa plant. Click for more details...

CLERMONT COAL PROJECT - COAL HANDLING PREPARATION PLANT
Private ownership Mining - Primary And Secondary Processing (Piping) project In The Isaac Regional Council Area for New development. Off site fabrication & installation of 2 major (2500tph) & 3 minor (300tph) conveyors, a dump hopper, a wash plant (300tph). Associated process piping. Click for more details...

MT COOLON CENTRAL TREATMENT PLANT
Mining - Primary And Secondary Processing (Minerals Processing) project at Via, Mount Coolon, QLD 4804 for New. For the construction of a central treatment plant and related infrastructure. Click for more details...

MOUNT GARNET TIN & IRON PROJECT
Private ownership Mining - Primary And Secondary Processing (Minerals Processing) project In The Tablelands Regional Council Area for New development. A project covering the Gillian, Pinnacles & Windermere localities on the historic Herberton tin field. A tin resource estimate of 7.3million tonnes (Mt) with iron estimates of 3Mt @ 30.8% at Gillian, 1.87Mt at Pinnacles (Wafer) & 400,000t at Deadmans Gully (Windermere). A fluorite estimate also for Pinnacles (Hartog, Llashram, Sniska, Wafer) of 0.96Mt @ 15%. A scoping study envisaged 7.5years life-of-mine (LoM) for operations in the project area at a rate of 700,000tpa producing 236,600tpa of magnetite concentrate grading 65%. Click for more details...

CARBOROUGH DOWNS COAL MINE EXPANSION PROJECT - PIPING FOR MECHANICAL EQUIPMENT
Mining - Primary And Secondary Processing (Piping) project In The Isaac Regional Council Area of Private ownership. For the provision of piping for mechanical equipment for the new 5Mpta CHPP. Click for more details...

DAUNIA COAL PROJECT - COAL HANDLING PREPARATION PLANT
Approximately 25km Southeast of, Moranbah, QLD 4744 Has Daunia Coal Project - Coal Handling Preparation Plant currently at Construction stage. The contract involves detailed design and procurement of a CHPP, with all key components scheduled for delivery during calendar 2009. Click for more details...

MILLENNIUM COAL OPERATIONS EXPANSION
via Peak Downs Hwy 16km southwest of, Coppabella, QLD 4741 Has Millennium Coal Operations Expansion currently at Construction stage. A project to expand the 2million tonnes per annum (Mtpa) operations to 5.5Mtpa Run-of-Mine (ROM) coal for 3.6Mtpa product coal for up to 16 years. Development of the new Mavis Pit by contract mining comprising conventional open-cut truck & excavator terrace mining. Possibility of minor upgrade & a new ROM stockpile at the existing coal handling & preparation plant (CHPP). Temporary waste rock emplacements prior to likely ultimate disposal in the Millennium Pit void. Construction of haul roads across New Chum Creek & possible alteration of the Millennium/Poitrel access road. Establishment of a 2km long drainage system along the northern boundary of the new pit as well as 15 new sediment dams. The expansion project to involve 160 employees & contractors in addition to the existing 220 person workforce. Click for more details...

CURTIS ISLAND LNG (QCLNG) PROJECT - SOCIAL IMPACT CONSULTANTS PANEL
Mining - Primary And Secondary Processing (Coal Processing) New project at Between Bowen Basin &, Curtis Island, QLD 4680. This type is Consultants Panel - Social Impact Management Plan with Private ownership. QCLNG is a project to develop coal seam gas wells in the Surat & Bowen Basins, pipe gas to a processing plant to be built on Curtis Island & then export product LNG by ship. A panel of providers is being sought to undertake contracted social performance services in the course of compiling a Social Impact Management Plan for the project. Click for more details...

MOUNT CARBINE TUNGSTEN PROJECT - TAILINGS RETREATMENT PROJECT
Private ownership Mining - Primary And Secondary Processing (Minerals Processing) project In The Cairns Regional Council Area for New development. A project to produce concentrates from waste dump fines & tailings dam materials. Click for more details...

OAKY CREEK COAL OPERATIONS - LONGWALL PROJECT STAGE 4
Mining - Primary And Secondary Processing (Coal Processing) project for New development. A project to increase production over 5 years by expanding into additional sections of the mine tenement. To include a new longwall mining system & associated development suite. Expansion of the existing coal handling & preparation plant (CHPP). Upgrade of the electrical system. Click for more details...

GEORGINA BASIN PHOSPHATE PROJECT - PARADISE BENEFICIATION PLANT
Mining - Primary And Secondary Processing (Minerals Processing) New project at 120km north of MT ISA near, Gunpowder, QLD 4825. This type is Beneficiation Plant with Private ownership. Construction of a 1 million tonne per annum (Mtpa) beneficiation plant. To include rotary screen, rod mill, hydro-cyclone, feed filters, flotation cells, tailing & concentrate thickeners. Click for more details...

ROCKLANDS GROUP JOINT VENTURE COPPER PROJECT - PROCESSING PLANT INSTALLATION
Structural/Mechanical/Piping Installation New project In The Cloncurry Shire Council Area. Installation of a fully computerised & automated 3 million tonne per annum (Mtpa) processing plant for copper/gold, cobaltic-pyrite, native copper & magnetite concentrate production. Click for more details...

BARALABA COAL OPERATIONS EXPANSION MIA
Mining - Primary And Secondary Processing (Tankage, Silos) project at near, Baralaba, QLD 4702 for New. Construction of all infrastructure associated with 20 year expansion for central, south & north pits. To include workshops, wash down area, administration, fuel tanks, water & sewerage treatment & other civil infrastructure. Concrete, structural steel, civil/earthworks, hydraulics & drainage, piling & electrical works. Click for more details...

DUGALD RIVER BASE METAL PROJECT - CONCENTRATOR
Concentrator Plant/Associated Plant New project In The Mt Isa City Council Area. The concentrator will have an annual production of approximately 160,000 tonnes of zinc in zinc concentrate, plus by-products, over an estimated 28 year mine life. Click for more details...

AMRUN (SOUTH OF EMBLEY) BAUXITE PROJECT - PROCESS FACILITY
Mining - Primary And Secondary Processing (Minerals Processing) project for New development. For the provision of a process plant. The package will be issued for bid as one package with the following separable parts. Part A: Off-site Assembly of modules including, but not limited to: Modularised bauxite beneficiation plant (including concrete foundations), Modules are nominally 15m(W) x 25m(L) x 20m(H) & up to 1,200 metric tonnes, Primary & secondary sizer structures, Tertiary crushing structure, Transfer stations, Conveyor galleries, Conveyor ground modules. The expectation is that the Tenderer will utilise to the maximum extent possible, modularised structures to reduce manning levels required on-site. Part B: Installation of the modules on Site, Supply of all labour, tools, supervision, quality assurance, temporary storage & workshop facilities, construction plant & equipment, materials, services, ancillary equipment, utilities, consumables & perform all installation & testing necessary. Click for more details...

APLNG LNG PLANT - HOSES & FITTINGS SUPPLY
Hoses & Fittings Supply project at At, Curtis Island, QLD 4680 in the Mining - Primary And Secondary Processing (Piping). For the provision of hoses & fittings. Click for more details...

Copyright © CoreLogic. All rights reserved. Powered by Cordell Connect