State

Categories

Sub Categories

Click Here to Find Current Projects

List of Mining - Primary And Secondary Processing Projects in QLD


CRACOW GOLD PROJECT - KLONDYKE/ROYAL SHOOT/CROWN/ROSES PRIDE
Currently at the Construction stage In Banana Shire is a project estimated to be $ 500000. This project CIL tankage. Click for more details...

KUNWARARA MAGNESITE OPERATIONS - KG2 EXTN
A project in the QLD Within Rockhampton Regional. Installation of a new crushing and screening circuit. Click for more details...

LADY ANNIE/MOUNT KELLY COPPER PROJECT - PROCESSING FACILITY
New project of Mining - Primary And Secondary Processing (Civil works at processing facilities) project at Adjacent to Lady Loreta Mine 140 Km North West of, Mount Isa, QLD 4825. To construct a 1900 tpa copper SXEW plant and heap leach. Total copper recovery is expected to be 89% of the ore processed. Click for more details...

LADY ANNIE/MOUNT KELLY COPPER PROJECT - PROCESSING FACILITY
New project of Mining - Primary And Secondary Processing (Minerals Processing) project at Adjacent to Lady Loreta Mine 140 Km North West of, Mount Isa, QLD 4825. To construct a 1900 tpa copper SXEW plant and heap leach. Total copper recovery is expected to be 89% of the ore processed. Click for more details...

ROSEBY COPPER PROJECT - PROCESSING FACILITY
New project of Mining - Primary And Secondary Processing (Civil works at processing facilities) project at North west of, Cloncurry, QLD 4824. The process plant is to be located immediately adjacent the Blackard Pit. The basic processes include: primary crushing, comprising feed bin, apron feeder, crusher and dust suppression, grinding in a single stage SAG mill and classification in cyclones, optional stockpiling of primary crushed or to de-couple the grinding and flotation processes for the crushing operations, rougher and scavenger flotations, rougher concentrate regrinding to improve final concentrate grade, two stages of cleaner flotation, concentrate thickening and filtration and filter cake storage before transportation, tailings thickening and disposal storage facility and reagents preparation and services. The process plant has been designed to treat approximately 3 Mtpa of sulphide feed, as this will be the case for the initial 4 years of production. Following this, the processing plant may require adaptation to process oxide ores, as the style of ore mineralisation vary. These throughputs are based on a 24 hour per day, 7 days per week operations. The flotation concentrate would be saleable for smelter feed. The proposed process plant comprises the following: Run of Mine (ROM) ore bin fed by either a front end loader or by trucks direct tipping ore, grizzly feeder to remove fines less than 150mm, conveyor feeding combined grizzly and crusher products to the mill, a SAG mill with single 3 MW drives, a ball miss with single 3MW drive, two sets of rougher/scavenger flotation cells (2x7x160 cubic metres), concentrate regrind mill with 550kW drive, cleaner flotation cells (6x50 cubic metres cells), recleaner flotation (4x20 cubic metres cells), concentrate thickening and filtration, reagents, air and water services and pumps, service cranes and hoists. Click for more details...

ROSEBY COPPER PROJECT - EXPLORATION JOINT VENTURE
Mining - Primary And Secondary Processing (Minerals Processing) project at North west of, Cloncurry, QLD 4824 of Processing - Sulphide Mineralisation type of New development. Likely to involve modifications to circuits at the Oxide processing facility, which incorporates grinding and flotation. To be developed at a later date. Click for more details...

MOUNT GARNET ZINC PROJECT TREATMENT FACILITY EXPANSION
Mining - Primary And Secondary Processing (Minerals Processing) Addition project at Via, Mount Garnet, QLD 4872. This type is Treatment Facility - Expansion/Dedicated Copper Circuit with Private ownership. An upgrade to increase plant capacity from the current 90,000 tonnes of concentrate per annum to 148,000 tonnes per annum. The zinc concentrate output will increase from 70,000 tonnes per annum to 110-120,000 tonnes per annum. A dedicated copper circuit will be installed as part of the upgrade. Click for more details...

BLACKWATER/COMET CHPP PROJECT
Via, Blackwater, QLD 4717 Has Blackwater/Comet Chpp Project currently at Planning stage. The project manager's role will include design work for earthworks and related services (ensuring no mismatches between earthworks construction and CHPP construction), construction and related managment and contract administration for CHPP design construct package, once awarded (contract superintendent). Click for more details...

BAJOOL SALT OPERATIONS - PORT ALMA
New project of Mining - Primary And Secondary Processing (Other processing including salt, sand etc) project at At, Bajool, QLD 4699. One new shed/warehouse. One replacement. Click for more details...

AURUKUN ALUMINA PROJECT - BAUXITE RESOURCE
A project in the QLD Within Weipa Shire. Preferred development is a mine based on the Aurukun bauxite resource, a washing plant at the mine site, and a new alumina refinery of at least 600,000 tonnes per annum output located in either Bowen, Townsville or Gladstone and all necessary supporting infrastructure and associated facilities. A resource of 480 Mt of dry beneficiated bauxite. Click for more details...

MOUNT MOSS PROJECT - MAGNETITE/COPPER/ZINC RESOURCE
Resource - Magnetite/Copper/Zinc project at Ewan Road via, Greenvale, QLD 4816 In The Council Area Of Charters Towers Regional of Private. Resource estimate is 3.5 Mt of magnetite ore and 600,000 tonnes of copper oxide ore. The operation comprises of open cut mining of magnetite, copper and zinc in one to three pits. Processing facility for the crushing and magnetic separation/enrichment of magnetite, stockpile area and loadout facilities and vat leaching processing facility for the production of copper concentrate. Other infrastructure included the upgrade of a 30 km haul road, waste rock dumps, ore stockpiles and the upgrade of an accommodation camp for 60 persons. Click for more details...

KESTREL COAL OPERATIONS
New project of Mining - Primary And Secondary Processing (Coal Processing) project at 49 km north east of, Emerald, QLD 4720. The mine is capable of annual production of up to five million tonnes of high quality metallurgical coal and high energy thermal coal for export markets in Asia and Europe. The lease contains 190 million tonnes of recoverable reserves, part of total coal resources of 289 million tonnes. The purchase includes the nearby Gordonstone West property, which has additional recoverable resources of 126 million tonnes. Click for more details...

MONTO MINERALS INDUSTRIAL MINERALS PROJECT - WET SEPERATION PLANT
Mining - Primary And Secondary Processing (Other processing including salt, sand etc) project for New development. Wet Seperation Plant that will constructed next to the existing pilot plant. The plant will use non chemical seperation using gravity and magnetics. Plant is expected to process 142,000 tonnes in 2007 and 232,000 tonnes in 2008. Click for more details...

KOGAN CREEK COAL/POWER STATION PROJECT
Mining - Primary And Secondary Processing (Coal Processing) project In The Western Downs Regional Council Area of Private ownership. Proposed open cut coal mine and associated power station Click for more details...

CRACOW GOLD PROJECT - KLONDYKE/ROYAL SHOOT/CROWN/ROSES PRIDE
Surface Works New project In The Banana Shire Council Area. Includes excavation of box cut. Click for more details...

TEXAS SILVER PROJECT - TWIN HILLS
Surface Infrastructure project at via, Texas, QLD 4385 in the Mining - Primary And Secondary Processing (Civil works at processing facilities). Likely to be small scale infrastructure requirements, including demountables. Some demountables are already in place for administration of exploration project. Only 1-2 additional demountables likely to be required. Likely to be sourced locally. NO accommodation requirements, as the project is located only 7 km from Texas. Heap leach operation will require earthworks to prepare leach pads. Likely to be part of mining operation. Click for more details...

YABULU NICKEL REFINERY EXTENSION - BOILER REFURBISHMENT
Mining - Primary And Secondary Processing (Minerals Processing) project In The Townsville City Council Area of Boiler No 3 Refurbishment Contract type. An existing boiler will be refurbished to generate high-pressure steam for power generation and process requirements. This boiler will be converted from oil firing to gas firing, utilising coal seam methane gas to be delivered by the new Moranbah to Townsville gas pipeline. A new boiler feedwater plant will also be installed. Click for more details...

GLADSTONE ALUMINA PLANT
Mining - Primary And Secondary Processing (Minerals Processing) project In The Gladstone Regional Council Area of Private ownership. Three new calciners. Includes design, installation, commissioning and testing. The Calciners will be used for the calcination process which involves using extremely high temperatures to remove chemically bonded water from the alumina hydrate, ultimately producing the dry alumina powder from which aluminium is made. The new calciners will reduce dust emissions by around 90%, decrease gas usage by a quarter and cut greenhouse emissions by 245,000 tonnes per year. Click for more details...

MOUNT ISA MINES COPPER SMELTER
Mining - Primary And Secondary Processing (Minerals Processing) project at At, Mount Isa, QLD 4825 for New. A leaching project to recover around 2,500 tonnes of additional copper per annum from electrostatic precipitator dust in the Mount Isa copper smelter. Click for more details...

KOGAN CREEK POWER PROJECT - COMMUNICATION SYSTEM
A project in the QLD Within Western Downs Regional. Includes telephone system with PABX and hardwired and cordless telephones (cordless telephones must operate in the complete power plant area). Also includes an alarm response pocket pager system with on- and off-site pagers Click for more details...

TEXAS SILVER PROJECT - TWIN HILLS
Mining - Primary And Secondary Processing (Minerals Processing) project at Via, Texas, QLD 4385 for New. Mobile Crushing Plant comprising jaw crusher, screens and core crusher and will be on site early April 2005. Click for more details...

TEXAS SILVER PROJECT - SILVER SPUR SLAG DUMP
Private ownership Mining - Primary And Secondary Processing (Minerals Processing) project In The Goondiwindi Regional Council Area for New development. The slag heap at Silver Spur is a potentially valuable resource. Click for more details...

MOUNT NORMA COPPER OPERATIONS
Mining - Primary And Secondary Processing (Crushing, Screening, Quarrying) project for New development. 20,000 tonnes of copper ore initially. More to come. Click for more details...

CHARTERS TOWERS GOLD OPERATIONS - UNDERGROUND MINING
Mining - Primary And Secondary Processing (Minerals Processing) project at Via, Charters Towers, QLD 4820 of Underground Mining type of New development. Company personnel are currently undertaking development to the ore zone. A contract is likely to be repriced involving further development work. Company personnel will then concentrate on production. Click for more details...

FOXLEIGH COAL OPERATIONS - PIPING FOR TRAIN LOADOUT
Mining - Primary And Secondary Processing (Coal Processing) New project at 10 km south of, Middlemount, QLD 4746. This type is Piping - For Train Loadout with Private ownership. Poly piping & steel piping will be required. Click for more details...

YABULU NICKEL REFINERY EXTENSION - WATER TREATMENT/RETICULATION CONTRACT
Water Treatment & Reticulation Contract New project In The Townsville City Council Area. The existing standby turbine alternator will be changed to generate power as required in conjuction with other units on site. The low pressure steam exhausted from the turbine in addition to other steam supplies on site will be reticulated throughout the site to the new plant for heating and process requirements. The capacity of the existing cooler water systems will be expanded involving water treatment and reticulation. Click for more details...

MOUNT ISA MINE COPPER SMELTER - EXPANSION STAGE TWO
Mining - Primary And Secondary Processing (Minerals Processing) New project at At, Mount Isa, QLD 4825. This type is Smelter Expansion - Stage 2 with Private ownership. The copper smelter's capacity will be upgraded from 280,000 to 300,000 kt anode. This will involve the installation of a slag clearing furnance, converter slag crushing plant and two new oxygen plants. As part of the upgrade, the Townsville copper refinery capacity will be upgraded from 280,000 to 300,000 kt cathode. Click for more details...

TWIN HILLS GOLD PROJECT - LONE SISTER - RESOURCE
Private ownership Mining - Primary And Secondary Processing (Minerals Processing) project In The Charters Towers Regional Council Area for New development. Resource estimate is 435,000 tonnes @ 7.3 g/t containing 102,000 ounces of Au. Part of the mine planning involves the feasibility of processing high grade ore through a conventional CIP treatment plant and low grade material for heap leach recovery of gold. The plant is proposed to be located at the mine site to save transporting 280 Km to the Rishton treatment plant. Click for more details...

DALRYMPLE BAY COAL TERMINAL EXPANSION - BUND 4A CIVIL WORKS
Bund 4a Civil Works New project In The Mackay Regional Council Area. To construct Bund 4A. Click for more details...

LAKE VERMONT COAL PROJECT - EARTHWORKS FOR COAL PREPARATION PLANT
Currently at the Construction stage In Isaac Regional is a project estimated to be $ 1200000. This project For a 4 Mtpa facility. Click for more details...

LAKE VERMONT COAL PROJECT - CONCRETE WORKS FOR COAL PREPARATION PLANT
A project in the QLD Within Isaac Regional. For a 4 Mtpa plant. Click for more details...

BLOODWOOD CREEK UCG POWER PROJECT
Mining - Primary And Secondary Processing (Coal Processing) project In The Western Downs Regional Council Area of Private ownership. A power plant project based on underground coal gas (UCG) with late 2009 certified syngas reserves of 11PJ at 1P (proven) level of certainty, 743.9PJ at 2P (proven + probable) & 1042.8PJ at 3P (proven + probable + possible). The 5MW proof-of-concept power station powered by 4 GEC Alsthom Ruston low emission engines to be connected via a 12.6km overhead line to the power grid in October 2011. Development of a commercial scale 20-25MW power station to follow. Click for more details...

MOUNT GARNET TIN & IRON PROJECT
Private ownership Mining - Primary And Secondary Processing (Minerals Processing) project In The Tablelands Regional Council Area for New development. A project covering the Gillian, Pinnacles & Windermere localities on the historic Herberton tin field. A tin resource estimate of 7.3million tonnes (Mt) with iron estimates of 3Mt @ 30.8% at Gillian, 1.87Mt at Pinnacles (Wafer) & 400,000t at Deadmans Gully (Windermere). A fluorite estimate also for Pinnacles (Hartog, Llashram, Sniska, Wafer) of 0.96Mt @ 15%. A scoping study envisaged 7.5years life-of-mine (LoM) for operations in the project area at a rate of 700,000tpa producing 236,600tpa of magnetite concentrate grading 65%. Click for more details...

CARBOROUGH DOWNS COAL MINE EXPANSION PROJECT - VALVES FOR MECHANICAL EQUIPMENT
New project of Mining - Primary And Secondary Processing (Coal Processing) project at 15 km east of, Moranbah, QLD 4744. For the provision of valves for the mechanical equipment for the new 5Mpta CHPP. Click for more details...

CARBOROUGH DOWNS COAL MINE EXPANSION PROJECT - MAGNETIC SEPARATORS FOR THE CHPP
Currently at the Tenders & Building stage In Isaac Regional is a project estimated to be $ 1000000. This project For the provision of magnetic separators for the new 5Mpta CHPP. Click for more details...

TALINGA DEVELOPMENT PROJECT STAGE 1 - CIVIL WORKS
Mining - Primary And Secondary Processing (Civil works at processing facilities) project In The Western Downs Regional Council Area of Private ownership. Stage 1 - Civil Works involves earthmoving, hydraulic & civil works up to the completion of the slab & sub-structure. The pipe-laying & superstructure of the facility will be further stages with the pipework to be completed by a specialist company. Click for more details...

SOUTHERN CROSS/IMPEL LNG PROJECT
Private ownership Mining - Primary And Secondary Processing (Tankage, Silos) project In The Gladstone Regional Council Area for New development. Proposed staged construction of a liquefied natural gas (LNG) plant with up to 3 trains ranging from 0.07-1.3million tonnes per annum (Mtpa) capacity. Associated facilities expected to include a construction jetty; an LNG dock & jetty to handle vessels up to 200,000cu m; cryogenic pipelines; LNG storage tanks up to 210,000cu m capacity & 400km approx pipeline with spur lines. The project is expected to generate 300-350 jobs during construction & 80-90 when fully operational. Click for more details...

MOUNT CARBINE TUNGSTEN PROJECT - TAILINGS RETREATMENT PROJECT
Private ownership Mining - Primary And Secondary Processing (Minerals Processing) project In The Cairns Regional Council Area for New development. A project to produce concentrates from waste dump fines & tailings dam materials. Click for more details...

CAVAL RIDGE COAL PROJECT - SUMP PUMPS
Sump Pumps - For Coal Processing Plant project at 16km south of, Moranbah, QLD 4744 In The Council Area Of Isaac Regional of Private. Electric water pumps. To include both end suction & split case types. Click for more details...

GEORGINA BASIN PHOSPHATE PROJECT - FERTILISER COMPLEX
Mining - Primary And Secondary Processing (Minerals Processing) project at MICA CREEK 10km south of, Gunpowder, QLD 4825 for New. Chemical processing including a 1600ktpa sulphuric acid plant, a 600ktpa phosphoric acid plant, a 1200ktpa Di/Mono Ammonium Phosphate (DAP/MAP) plant & a 30ktpa aluminium fluoride plant. Associated utilities & facilities. Click for more details...

GROSVENOR COAL PROJECT - BULK EARTHWORKS PACKAGE
Mining - Primary And Secondary Processing (Civil works at processing facilities) project at via, Moranbah, QLD 4744 of Bulk Earthworks type of New development. Bulk earthworks for coal operations areas to include drift cut & cover and shotcrete soil stabilisation. Click for more details...

ROCKLANDS GROUP JOINT VENTURE COPPER PROJECT - PROCESSING PLANT INSTALLATION
Structural/Mechanical/Piping Installation New project In The Cloncurry Shire Council Area. Installation of a fully computerised & automated 3 million tonne per annum (Mtpa) processing plant for copper/gold, cobaltic-pyrite, native copper & magnetite concentrate production. Click for more details...

CURTIS ISLAND LNG (QCLNG) PROJECT - GAS FIELD DEVELOPMENT - QUARRY MANAGEMENT & GRAVEL SUPPLY
Mining - Primary And Secondary Processing (Crushing, Screening, Quarrying) project at West of WANDAON, east of TARA & west of, Chinchilla, QLD 4413 for New. A 3 year contract for management of a quarry stockpile & associated works to ensure continuous gravel supply. To include establishment of a quarry pit with access roads. Operate & maintain a surface crushing plant. Manage crushed & uncrushed ore stockpiles in various locations including blending & tramming of material. Click for more details...

DUGALD RIVER BASE METAL PROJECT CRUSHING & SCREENING PLANT
A project in the QLD Within Mt Isa City. Crushing & screening plant for an underground mining operation of 2million tonnes per annum (Mtpa) of zinc/lead/silver plus 1Mtpa of copper for 200,000tpa zinc concentrate. Click for more details...

BARALABA COAL OPERATIONS EXPANSION MIA
Mining - Primary And Secondary Processing (Tankage, Silos) project at near, Baralaba, QLD 4702 for New. Construction of all infrastructure associated with 20 year expansion for central, south & north pits. To include workshops, wash down area, administration, fuel tanks, water & sewerage treatment & other civil infrastructure. Concrete, structural steel, civil/earthworks, hydraulics & drainage, piling & electrical works. Click for more details...

CURTIS ISLAND LNG (QCLNG) PROJECT - GAS FIELD DEVELOPMENT - COMPRESSION STATIONS & CENTRAL PROCESSING PLANTS
Compression Stations/Central Processing Plants New project In The Western Downs Regional Council Area. Construction & fabrication of 5 x compression stations & a central processing plant at the Woleebee Creek block southwest of Wandoan & 3 field compression stations & a central processing plant at the Bellevue block east of Miles. Click for more details...

INJUNE TAROOM ROAD QUARRY
3187 Injune Taroom Rd (Lot 11 WT15) BEILBA via, Roma, QLD 4455 Has Injune Taroom Road Quarry currently at Construction stage. Proposed development of a gravel quarry. Click for more details...

MOUNT ISA MINES OPERATIONS - SILICA CONTRACT
Currently at the Tenders & Building stage In Mt Isa City is a project estimated to be $ 2000000. This project A 3 year contract for the supply of fine silica for smelter flux. Glencore to organise drill & blast in an area between no.5 tailings dam & 5/7 West Wall (ML 8058). Transportation of broken rock to a run-of-mine (ROM) pad prior to going to a designated processing site. Pre-screening if necessary prior to crushing, size separation through screening & if required washing. Haulage of the silica to the fine & coarse stockpiles near the lead smelter (Rowles Reserve) & copper smelter sites (Barnes Boulevard - North & South, Stacker). The contractor to supply primary & secondary crushers, mobile stack & screening plant conveyors as well as 45t excavators with bucket/hammer attachments, 980 wheel leaders, 25t dump trucks & a water truck, Click for more details...

LORENA JOINT VENTURE GOLD OPERATIONS RECOMMENCEMENT - MOBILE MINERAL PROCESSING PLANT
Mining - Primary And Secondary Processing (Minerals Processing) project for New development. For the supply, commissioning & operation of a mobile mineral processing plant. Units to be constructed off-site & transported to site fully commissioned. Click for more details...

Copyright © CoreLogic. All rights reserved. Powered by Cordell Connect