BAUHINIA REGIONAL RAIL PROJECT - ROLLESTON COAL PROJECT
A project in the QLD Within Central Highlands Regional. Queensland Rail will construct, own and operate a new 110 km spur to expand their existing rail network in the Blackwater system. The new spur will connect to the existing system near Kinrola. The Rolleston mine will be charged a fee under a 20 year contract to access the line. Click for more details...

ROLLESTON COAL PROJECT - COAL HANDLING/INFRASTRUCTURE
Mining - Support Facilities (Administration facilities) New project at 16km west of, Rolleston, QLD 4702. This type is Crushing & Mine Site Infrastructure with Private ownership. Initial development will be for 6mtpa. Expansion to 8 mtpa allowed for. Click for more details...

ROLLESTON COAL PROJECT - COAL HANDLING/INFRASTRUCTURE
Mining - Support Facilities (Bath houses, Amenities, Dressing rooms) New project at 16km west of, Rolleston, QLD 4702. This type is Crushing & Mine Site Infrastructure with Private ownership. Initial development will be for 6mtpa. Expansion to 8 mtpa allowed for. Click for more details...

ROLLESTON COAL PROJECT - COAL HANDLING/INFRASTRUCTURE
Mining - Support Facilities (Industrial buildings) New project at 16km west of, Rolleston, QLD 4702. This type is Crushing & Mine Site Infrastructure with Private ownership. Initial development will be for 6mtpa. Expansion to 8 mtpa allowed for. Click for more details...

PHOSPHATE HILL OPERATIONS
Mining - Support Facilities (Industrial buildings) project at Phosphate Hill approx 190 km south east of Mount Isa via, Cloncurry, QLD 4824 for New. Workshop, store & control building. Concrete slab & likely to be metal cladding. Click for more details...

CENTURY ZINC MINE
Buildings project at North west of, Mount Isa, QLD 4825 In The Council Area Of Mt Isa City of Private. Change-house, workshop, laboratory & administration. 36 week contract period. Click for more details...

PHOSPHATE HILL OPERATIONS
Phosphate Hill approx 190 km south east of Mount Isa via, Cloncurry, QLD 4824 Has Phosphate Hill Operations currently at Construction stage. Includes short-term accommodation and catering. Click for more details...

BALLERA GAS CENTRE - SOUTH WEST QUEENSLAND GAS PROJECT
Mining - Support Facilities (Administration facilities) project at Ballera, ., QLD 4999 of Electrical Installation For Operations Village/Workshops & Admin. Facilities type of Subcontract development. Includes workshop, offices for permanent camp Click for more details...

CRACOW GOLD PROJECT - KLONDYKE/ROYAL SHOOT/CROWN/ROSES PRIDE
Surface Works New project In The Banana Shire Council Area. Includes excavation of box cut. Click for more details...

KOGAN CREEK POWER PROJECT - ELECTRICAL INSTALLATION/WORKSHOP
South of, Brigalow, QLD 4412 Has Kogan Creek Power Project - Electrical Installation/Workshop currently at Construction stage. Erection of 1 Siemens Steam Turbine, 1 Siemens Generator THDF 125/67, Condenser, Tanks, Pumps, Compressors, Assembly of Workshop and Store, Electrical and I & C installation Click for more details...

GROSVENOR DOWNS HOUSING
New project of Mining - Support Facilities (Accommodation - units, housing, group accom.) project at Moranbah Access Rd (cnr Peak Downs Hwy), Moranbah, QLD 4744. Permanent housing for BMA employees. Click for more details...

COLLINGWOOD TIN PROJECT - PLANT/INFRASTRUCTURE
Mining - Support Facilities (Administration facilities) project at 35 km south of, Cooktown, QLD 4871 for New. Water only gravity concentration process. Click for more details...

TWIN HILLS GOLD PROJECT - PERMANENT CAMP
Twin Hills Gold Project - Permanent Camp is currently at the Construction stage, valued at about $ 2000000 it is 40 person camp and associated office building. Click for more details...

MORANBAH NORTH COAL OPERATIONS - WORK CAMP
Mining - Support Facilities (Accommodation - units, housing, group accom.) project In The Isaac Regional Council Area of Private ownership. Extension of 21 rooms in 7 portables to an existing 400 room camp site. Click for more details...

ENSHAM CENTRAL PROJECT EXPANSION - TEMPORARY ACCOMMODATION BUILDINGS
New project of Mining - Support Facilities (Accommodation - units, housing, group accom.) project at Lot 1 Adam Street (Rp886246), Comet, QLD 4702. Temporary accommodation building and mess hall. Click for more details...

ENSHAM CENTRAL EXPANSION PROJECT - DRAGLINE ASSEMBLY WORKSHOP
Mining - Support Facilities (Industrial buildings) project at (Lot 34 RP 864576) Duckponds Road, Emerald, QLD 4720 of Dragline Assembly Workshop type of New development. Construction comprises an assembly workshop (450 sqm), abultion block, crib room, office, 8 metre wide sealed road and 2 buses & 15 vehicle parking spaces. Click for more details...

COPPABELLA ACCOMMODATION CENTRE - CENTRAL FACILITIES BUILDING - STAGE 1
Coppabella Accommodation Centre - Central Facilities Building - Stage 1 is currently at the Construction stage, valued at about $ 5000000 it is To include bar, recreation facilities, meeting rooms & swimming pool. Concrete slab, structural steel frame, external cladding & metal roof. Loading dock. Click for more details...

QSN LINK GAS PIPELINE
Private ownership Mining - Support Facilities (Industrial buildings) project In The Not Yet Determined Council Area for New development. The QSN Link pipeline will extend south-west from the Ballera Gas facility in Queensland. It will pass approximately 7km to the south of Innamincka in South Australia and terminate at the Moomba plant. The pipeline will be some 180km in length, with approximately 90km in Queensland and 91.5km in South Australia. The pipeline will be typical of a modern, small to medium diameter gas transmission pipeline. Final design parameters are yet to be determined, but it is likely to involve the following infrastructure: a buried, high pressure, steel, natural gas pipeline, with a diameter in the order of 400mm, an inlet station at Ballera, above ground facilities at intervals along the pipeline include a mid-line mainline valve, cathodic protection systems and marker signs and an outlet delivery station at Moomba. The construction workforce will be accommodated in temporary camps and at local accommodation. two preliminary campsite locations have been selected which will accommodate a single camp that will be mobilised from one location to the other during the construction phase of the project. construction depots will be used primarily for equipment storage and will typically be co-located with the construction camps. Facilities and equipment stored at the construction depots may include: site office and administration centre, construction vehicles, diesel fuel and lubricants, vehicle maintenance equipment, sand bags, sediment fencing, star droppers and wooden stakes and pipe wrapping and joint coating materials. When the utility is no longer required, the pipeline will be decommissioned in accordance with the regulatory requirements and accepted environmental best practices at the time. currently decommissioning procedures require the removal of all above ground infrastructure and the restoration of associated disturbed areas. Click for more details...

CHINCHILLA COAL SEAM GAS & UNDERGROUND COAL GASIFICATION PROJECT - STAGE 2 - MECHANICAL FOR LABORATORY
Mining - Support Facilities (Labs, Testing facilities, Hazardous materials, Storage) project In The Western Downs Regional Council Area of Mechanical - For Laboratory type. For the larger mine site laboratory. Click for more details...

CHINCHILLA COAL SEAM GAS & UNDERGROUND COAL GASIFICATION PROJECT - STAGE 1 - STRUCTURAL STEEL FOR LABORATORY
Mining - Support Facilities (Labs, Testing facilities, Hazardous materials, Storage) project In The Western Downs Regional Council Area of Private ownership. For the mine site laboratory. Click for more details...

ANTHILL COPPER PROJECT
via McNamara's Hwy 100km northwest of, Mount Isa, QLD 4825 Has Anthill Copper Project currently at Construction stage. A project based on a resource estimate (inferred, indicated) of 2.4 million tonnes (Mt) containing 27,000t of copper. Conventional drill & blast open cut operations to develop a pit 500 x 800m & 120m deep. After removal by hydraulic excavators, ore to be trucked to an interim run-of-mine (ROM) stockpile prior to haulage along McNamara Road to the existing processing plant at Mt Kelly. A mine infrastructure area (office building, first aid room, crib room, ablutions). Also heavy vehicle workshop with down pad & oil water separator, storage (explosives, fuel, scrap steel, stores, waste hydrocarbon). Diversion of Johnson Creek. Dewatering bores. Bunded waste rock dumps up to 40-50m high. Sediment dams. Haulage & access roads. Sewerage treatment plant. Click for more details...

NEWLANDS SOUTHERN UNDERGROUND COAL OPERATIONS - DISMANTLE & REMOVAL OF OFFICES & WORKSHOP
Offices/Workshop - Dismantle/Removal New project In The Isaac Regional Council Area. For the dismantling & removal of: 1 x office building & change house (approx 55m x 25m), 1 x office building & fittings (approx 20m x 15m), and, 1 x workshop building & fittings (approx 35m x 25 m), all located at the Southern Underground area of the Newlands Coal Mine. Buildings & associated items to be removed from site within agreed time of notification. Click for more details...

BLACKWATER MINE WORKERS ACCOMODATION STAGE 1
Mining - Support Facilities (Accommodation - units, housing, group accom.) project for New development. Stage 1 is 136 rooms, further stage ID 1051231 of 94 rooms now to be constructed progressively as one project. Click for more details...

AUSTRALIA PACIFIC LNG (APLNG) PROJECT - GAS PIPELINE
Mining - Support Facilities (Accommodation - units, housing, group accom.) project at From south of MILES to, Curtis Island, QLD 4680 for New. Part of a coal seam gas (CSG) to liquefied natural gas (LNG) project with Origin Energy responsible for developing CSG gas fields & transmission pipeline, ConocoPhillips responsible for developing a LNG processing plant & their joint venture company Australia Pacific LNG responsible for the export facilities. A 42 inch (1070mm) diameter, high pressure main pipeline to commence east of Wandoan at its junction with a 44km lateral pipeline from gas developments at Condabri & a 38km lateral from Woleebee gas developments south of Miles. To travel 362km underground with a marine crossing at The Narrows between Kangaroo Island & Port Curtis Island to finish at the LNG plant near Laird Point. Inlet stations to allow for insertion of cleaning & inspection equipment to be constructed at the start of the Condabri & Woleebee laterals & at their intersection a 0.5ha APLNG hub comprising the inlet station for the main pipeline, isolation valves & connections for future compression to also be constructed. Development of up to 5 x 15-20ha laydown areas to receive materials (Miles, Wandoan, Theodore, Biloela, Gladstone areas). 3 temporary accommodation camps each up to 15ha & operating for 3-7 months to be relocated along the pipeline route as required. Camps to include sleeping quarters for up to 1100 personnel, laundries, catering, medical centre, recreational facilities (eg gymnasium, cinema, reading room, sports grounds), diesel generators for power & package sewerage plants. Click for more details...

CURTIS ISLAND LNG (QCLNG) PROJECT
Mining - Support Facilities (Accommodation - units, housing, group accom.) project for New development. QCLNG is a project to develop coal seam gas (CSG) fields in the Surat & Bowen Basins, pipe gas to a processing plant to be built on Curtis Island & then export product liquefied natural gas (LNG) by ship. Phase 1 to be constructed to include 2 LNG processing trains with a combined capacity of up to 8.5million tonnes per annum (Mtpa) along with associated gas wells, field facilities & pipelines. Some 820 operational personnel & over 5000 construction personnel expected. Workers accommodation to be required in the Gladstone region (250 approx dwellings) & Western Downs area (280 approx dwellings). Click for more details...

ROLLESTON ACCOMMODATION VILLAGE EXPANSION
Mining - Support Facilities (Accommodation - units, housing, group accom.) project at via Dawson Hwy 10km northwest of, Rolleston, QLD 4702 of Bedrooms/Dining Hall/Parking/Water Treatment/Dam Relocation type of New development. Doubling of the existing 350 person accommodation village with another 200 rooms in stage 1 & 150 rooms in stage 2. New mess hall. Upgrades to the existing sewerage & water treatment facilities. Expansion of car parks. Relocation of existing silt retention dam. Click for more details...

MORANBAH REGION EXPANSION PROJECT - CIVIL WORKS PACKAGES
Private ownership Mining - Support Facilities (Canteens, Messes, Crib room) project In The Isaac Regional Council Area for New development. Packages to include site wide pioneering earthworks, road, drainage & civil works (C001). Bulk earthworks (cut & cover) from the mining infrastructure area (MIA) to the run-of-mine (ROM) area (C002) & from the ROM area to the train load out (C003). The co-disposal dam wall (C004). Supply of gravel (C005); crush rock backfill (C006); precast concrete pipes, boxes & headwalls (C007); high density polyethylene (HDPE) liners (C008) & geogrids (C009). Construction of warehouse & workshop building (C010); bathhouse & administration building (C011) & roadways & carparks in the MIA (C013). Spillway (C014). Supply of concrete (C015); fuel handling equipment (C016); lube handling equipment (C017); tanks (C020); hydrants & hose reels (C021); sewage treatment plant (C022); potable water treatment plant (C023) & fencing (C024). Design & construction of gas drainage plant & booster station (C025) along with supply of vacuum pumps (C029); surface reticulation piping (C030); underground reticulation piping (C031) & installation of the surface & underground reticulation system (C032). Mine cooling system (C026); stone dust system (C027) & diesel & lubrication supply (C028). Click for more details...

GLNG WALLUMBILLA GAS TREATMENT FACILITY (WGTF)
New project of Mining - Support Facilities (Industrial buildings) project at Walumbilla South Rd Iona Bardlomey Rd (Lot 33 SP 212840) 12km south of, Wallumbilla, QLD 4428. Staged development adjacent the existing Santos compressor (WCS) & metering (WMS) stations of a gas treatment facility of 2 trains each with a capacity of 250TJ/day. Each train to consist of gas compression, natural gas liquid removal & cryogenic gas treatment units & a gas turbine power generator using non-methane gas liquids & distributing power through alternators. Ancillary infrastructure to include condensate storage, hot oil system, air compression system, nitrogen generation plant, fire water system, flare & vent system, oily water system along with potable & service water system. Plant control room & workforce amenities. Click for more details...

BMA MORANBAH TEMPORARY ACCOMMODATION VILLAGE EXTENSION STAGES 1 & 2
Workers Accommodation - Extn - Stages 1 & 2 project at Belyando Ave, Curtin St, Goonyella Rd, Moranbah, QLD 4744 in the Mining - Support Facilities (Accommodation - units, housing, group accom.). Expansion of temporary accommodation village to provide additional 96 rooms in modular buildings. Each building to provide 4 x single rooms. Stage 1 - 64 rooms. Stage 2 - 32 rooms. Click for more details...

BOWEN BASIN ACCOMMODATION VILLAGE PACKAGES
Currently at the Tenders & Building stage In Various is a project estimated to be $ 10000000. This project Packages for supplier & construction involvement in The Mac's Developed-Owned-Operated accommodation village projects in the Bowen Basin (non-mining sites). To include civil site & road works, accommodation village transportable buildings as well as on site construction of kitchen/dining rooms, taverns, administration & retail facilities. Click for more details...

LADY LORETTA BASE METALS OPERATIONS- ACCELERATED DEVELOPMENT
Private ownership Mining - Support Facilities (Accommodation - units, housing, group accom.) project In The Mt Isa City Council Area for New development. A project to increase ore production at Lady Loretta to 1.6 million tonnes (Mtpa) by developing the upper ore bodies independently of the deeper underground resources. To include larger ore handling facilities, increased mobile & fixed plant equipment with associated expanded ventilation system. Upgraded or expanded infrastructure including concrete batch plant, paste plant, warehouse, fuel farm & power station. Increased village accommodation & utility upgrades. Click for more details...

FISHER STREET ACCOMMODATION VILLAGE
Accommodation Modules project at Fisher St, Dysart, QLD 4745 In The Council Area Of Isaac Regional of Private. Construction of an accommodation village for 400 persons. Click for more details...

DUGALD RIVER BASE METAL PROJECT - PERMANENT ACCOMMODATION VILLAGE
Accommodation Modules/Ancillary Buildings/Services project at Off the Burke Developmental Rd 85km NE of, Mount Isa, QLD 4825 In The Council Area Of Mt Isa City of Private. Construction of a 500 bed permanent accommodation village for the 25 year life-of-mine. Single storey modules with 3 bedrooms each. Associated kitchen, dining, laundry, recreation facilities. Parking. Click for more details...

MORANBAH VILLAGE STYLE ACCOMMODATION CONTRACT
Moranbah Village Style Accommodation Contract is currently at the Planning stage, valued at about $ 3000000 it is Provision in stages of 250-300 beds in new or existing village style accommodation to support the Moranbah Gas Project. Click for more details...

BARALABA COAL OPERATIONS EXPANSION MIA
Mining - Support Facilities (Administration facilities) project at near, Baralaba, QLD 4702 for New. Construction of all infrastructure associated with 20 year expansion for central, south & north pits. To include workshops, wash down area, administration, fuel tanks, water & sewerage treatment & other civil infrastructure. Concrete, structural steel, civil/earthworks, hydraulics & drainage, piling & electrical works. Click for more details...

BARALABA COAL OPERATIONS EXPANSION MIA
Mining - Support Facilities (Industrial buildings) project at near, Baralaba, QLD 4702 for New. Construction of all infrastructure associated with 20 year expansion for central, south & north pits. To include workshops, wash down area, administration, fuel tanks, water & sewerage treatment & other civil infrastructure. Concrete, structural steel, civil/earthworks, hydraulics & drainage, piling & electrical works. Click for more details...

GROSVENOR COAL PROJECT - MINE INFRASTRUCTURE AREA (MIA)
Support Buildings New project In The Isaac Regional Council Area. Construction of 7 separate buildings to provide support infrastructure. To include workshops, training room, administration buildings, amenities buildings & truck wash area. Concrete slab, steel portal frame, lightweight cladding, metal roof. Click for more details...

AUSTRALIA PACIFIC LNG (APLNG) PROJECT - GAS FIELD DEVELOPMENT - GAS PROCESSING PLANTS
Private ownership Mining - Support Facilities (Labs, Testing facilities, Hazardous materials, Storage) project In The Various Council Area for New development. A contract for the construction of 7 gas processing plants at Condabri, Orana (east of Talinga), Reedy Creek, Combabula & Eurombah Creek. Associated integrated operations centres, warehouses, workshops & internal roadways. Click for more details...

DUGALD RIVER BASE METAL PROJECT - MINE INDUSTRIAL AREA & PLANT BUILDINGS
Private ownership Mining - Support Facilities (Administration facilities) project In The Mt Isa City Council Area for New development. Construction of Plant & Industrial buildings. Click for more details...

YARRABEE ACCOMMODATION FACILITY
Currently at the Construction stage In Central Highlands Regional is a project estimated to be $ 20000000. This project Build, own & operate a 250 man accommodation facility at Yarrabee. Click for more details...

BAUXITE HILLS BAUXITE DSO PROJECT - ACCOMMODATION CAMP
A project in the QLD Within Mapoon Shire. Accommodation camp/village for the Bauxite Hills DSO Project. Click for more details...

BAUXITE HILLS BAUXITE DSO PROJECT - MINE & BARGE LOADING INFRASTRUCTURE
35km North of, Mapoon, QLD 4876 Has Bauxite Hills Bauxite Dso Project - Mine & Barge Loading Infrastructure currently at Construction stage. Barge loading facility on the Skardon River for the Bauxite Hills DSO Project. Vessels of between 60,000 to 80,000 t each will be loaded at the transhipment anchorage site. Vessels will be loaded in approximately four to six days with barges having a capacity of between 3500 - 6500t. Mine infrastructure Area (MIA) to include the run of mine (ROM) stockpile, bauxite stockpiles, barge loading, conveyor load point, earthmoving equipment hard park, administration offices, workshops & fuelling facilities. Raw & potable water supply from great artesian basin & shallow alluvial aquifers. Sewage treatment plant. Power requirements sourced from onsite generators located within the MIA. Click for more details...

BAUXITE HILLS BAUXITE DSO PROJECT - WORKSHOPS
Mining - Support Facilities (Industrial buildings) project In The Mapoon Shire Council Area of Private ownership. For the provision of workshops. Click for more details...