GRANTVILLE SEWERAGE SCHEME
A project in the VIC Within Bass Coast. Approx 3,850 m of 225 & 150 mm dia sewers & manholes & 400 m of 150 mm dia rising main. Click for more details...

STANHOPE WATER SUPPLY PUMP STATION
Stanhope Water Supply Pump Station is currently at the Tenders & Building stage, valued at about $ 200000 it is Work to include supply and installation of 2 no submersible pump stations, approximately 200 m of 200DN & 300DN pipework, chemical dosing systems, controls and electrics and a small building. Click for more details...

WIMMERA MALLEE PIPELINE PROJECT SUPPLY SYSTEM 1 & 7
A project in the VIC Within Horsham. The Wimmera Mallee Pipeline Project is one of the largest water infrastructure projects in Australia. The project will provide a reliable, higher quality water supply to farms and towns across the Grampians Wimmera Mallee Regions and return up to 83,000ML of water savings to government for environmental purposes. Click for more details...

CRANBOURNE TERMINAL STATION
Currently at the Construction stage In Casey is a project estimated to be $ 49500000. This project Proposed construction of two new terminal stations. Click for more details...

RAINBOW WATER TREATMENT PLANT
Rainbow Water Treatment Plant is currently at the Construction stage, valued at about $ 1400000 it is Design and Construction of Rainbow Water Treatment Plant and Associated Works. Click for more details...

SUNSET STRIP SEWER SCHEME
Public Utilities (Treatment plants, Sewerage reticulation) project, Phillip Island, VIC 3922 of Sewer - Rehabilitation type of New development. 4.8 km 225mm & 150mm sewer Click for more details...

SIMPSON WASTEWATER TREATMENT PLANT RE-USE SCHEME
Local Govt ownership Public Utilities (Water distribution systems, Drainage) project In The Colac-Otway Council Area for New development. Design and construction of the Simpson Water Treatment Plant, comprising a 1ML/day DAFF plant, 395kL capacity clearwater storage, a chlorination system and associated works. Click for more details...

BARNAWARTHA NORTH WATER STORAGE TANK
Currently at the Construction stage In Indigo is a project estimated to be $ 200000. This project Works include construction of a gravel access track and associated table drains and culverts, bulk earthworks and construction of a crushed rock pad for a tank site, cyclone mesh security fencing and gates, and miscellaneous site works. Click for more details...

MARSHALL TOWN ROAD SEWER EXTENSION
Public Utilities (Treatment plants, Sewerage reticulation) project In The Greater Geelong Council Area of Sewer - Extension type. Proposed sewer extension work. Click for more details...

MCDONALD AVENUE CATCHMENT DRAINAGE IMPROVEMENTS
New project of Public Utilities (Water distribution systems, Drainage) project at McDonald Avenue, Templestowe, VIC 3106. The construction of the McDonald Avenue Catchment drainage improvements. This works includes the construction of 400 linear metres of RC pipe drains up to 675mm diameter by open excavation up to a depth of 4.0m. Click for more details...

JAYCO DEVELOPMENT SITE SEWER RETICULATION PROJECT
Public Utilities (Treatment plants, Sewerage reticulation) project In The Greater Dandenong Council Area of Private ownership. Expressions of Interests are invited from suitably qualified contractors for construction of approximately 1600 linear meters of deep sewer reticulation, incorporating 225,375,450 & 600 DIA pipe and associated structures. Click for more details...

LILYDALE & MOUNT EVELYN WATERMAINS, VALVES AND HYDRANTS
Local Govt ownership Public Utilities (Water distribution systems, Drainage) project In The Yarra Ranges Council Area for New development. Installation/replacement of all watermains, valves and hydrants required in two Pressure Management Areas. Click for more details...

WONTHAGGI DESALINATION PLANT
Wonthaggi Desalination Plant is currently at the Construction stage, valued at about $ 3500000000 it is Construction & operation of one of the largest reverse-osmosis desalination plants in the world. To be located near Wonthaggi in the Bass Coast Region of Victoria, to facilitate the production and supply of desalinated water to Melbourne and potentially parts of the Westernport and South Gippsland regions. The desalination plant will be required to be capable of supplying 150 billion litres of desalinated water a year with the capacity to increase production to 200 billion litres if required. Commitment to renewable energy projects to offset the plants use of energy. Work towards minimising the impact on the invironment with an environmentally friendly and sensitive development encompassing green design from natural landscape to a constructed dune formation, with a living green roof. The development is expected to have minimal visual impact. This will be possible due to the power line being placed underground. Delivery of fibre optic cable to the local community. Click for more details...

CYANAMID STREET RECONSTRUCTION WORKS
Public Utilities (Water distribution systems, Drainage) project for New development. The scope of the works includes the construction of a 9.1m wide deep-strength asphalt pavement (approx 800m), concrete kerb & channel. underground drainage and ancilliary works. Click for more details...

MELBOURNE WATER CAPITAL WORKS PROGRAM
Public Utilities (Water distribution systems, Drainage) project In The Melbourne Council Area of Water Supply Program, Waterways And Stormwater Quality Program type. Melbourne Water is seeking proposals for the provision of Water Supply Program (Ref No. 2242) & Waterways and Stormwater Quality Program (Ref No 2243). Click for more details...

EVANS ROAD BRANCH SEWER CONSTRUCTION
Evans Road Branch Sewer Construction is currently at the Construction stage, valued at about $ 180000 it is Construction of a branch sewer in Evans Road, Cranbourne South. Works involve approximately 430m of 300 diameter sewer. Click for more details...

CAMP JUNGAI SEWAGE SYSTEM UPGRADE/REPLACEMENT
Public Utilities (Treatment plants, Sewerage reticulation) project In The Murrindindi Council Area of Sewage System - Upgrade type. Registrations of Interest are invited from suitably qualified contractors for the proposed Upgrade/Replacement and all associated siteworks at Camp Jungai, Rubicon. Click for more details...

NORTHERN VICTORIA IRRIGATION RENEWAL PROJECT (NVIRP) STAGE 1
A project in the VIC Within Various. The Northern Victoria Irrigation Renewal Project (NVIRP) program of works is to modernise the Goulburn-Murray region's ageing infrastructure, much of which is almost 100 years old. the upgrade is expected to return water savings of 225 billion litres per year on a long term basis average. The works will include the installation and upgrade of automated channel regulators, channel lining, channel remodeling, pipeline construction and installation of new metres along the 6,300 km channel network. Click for more details...

SHORE GROVE DIVERSION DRAIN CONSTRUCTION
Public Utilities (Water distribution systems, Drainage) New project at Shore Grove to Golf Road, Coburg North, VIC 3058. This type is Diversion Drain with Local Govt ownership. Council is seeking tenders from suitable contractors for the construction of a diversion drain in Coburg North. Click for more details...

MONT ALBERT DRAINAGE REHABILITATION WORKS
Local Govt ownership Public Utilities (Water distribution systems, Drainage) project In The Whitehorse Council Area for New development. Rehabilitation of brick drains in Mont Albert (217 metres). The work includes, grouting, pipe lining and minor civil works. Click for more details...

WYNDHAM CITY COUNCIL SPORTS RESERVES CIVIL INFRASTRUCTURE WORKS
Public Utilities (Water distribution systems, Drainage) project at Kookaburra Av, Werribee; off Sneydes Rd, Point Cook & off Ballan Rd, Wyndham Vale, VIC 3024 for New. Civil infrastructure works associated with sports reserves at Glen Orden Primary School (Kookaburra Avenue, Werribee), Innisfail Reserve (off Sneydes Road, Point Cook) and Manor Lakes Reserve (off Ballan Road, Wyndham Vale). Works will include bulk earthworks, construction of utility services, drainage, sewer, sports field construction, irrigation, fencing and associated works. Click for more details...

CORRYONG DISSOLVED AIR AND FLOTATION WATER TREATMENT PLANT
Off Greenwattle Gap Rd, Corryong, VIC 3707 Has Corryong Dissolved Air And Flotation Water Treatment Plant currently at Construction stage. Design and construction of a dissolved air and flotation water treatment plant located at Corryong, Victoria. The scope of works shall comprise a single contract incorporating all necessary process, chemical, mechanical civil, structural and automation related works, including the detail design, manufacture, installation, trials, verification and proof of performance testing. Click for more details...

GLENROWAN SEWERAGE SCHEME
State ownership Public Utilities (Treatment plants, Sewerage reticulation) project In The Wangaratta Council Area for New development. Supply and installation of the sewerage reticulation network, pump stations, transfer mains and associated works for the Glenrowan sewerage scheme. Click for more details...

ROAD RESERVE EASEMENT CONSTRUCTION AND WATER MAIN EXTENSION
Easement Construction & Water Main Extension project at Adjacent to 525 Stud Rd, Wantirna South, VIC 3152 In The Council Area Of Knox of Local Govt. Construction of easement in Road Reserve (High Street Road and Stud Road) and extension of water main to service harvest. Click for more details...

MOUNT MARTHA SEWERAGE TREATMENT PLANT
Public Utilities (Treatment plants, Sewerage reticulation) project at 390 Craigie Rd, Mount Martha, VIC 3934 of Solar Dryer Facility type of New development. Construct buildings for a new solar dryer to augment the existing drying pans for the sewerage waste treatment plant. Click for more details...

CHURCH STREET STREETSCAPE REDEVELOPMENT STAGE 1
Public Utilities (Water distribution systems, Drainage) project at Church St, Whittlesea, VIC 3757 of Streetscape Works - Stage 1 type of New development. Streetscape works to Church Street, Whittlesea, with works to include major sub surface storm water drainage rectifications to alleviate the continual flooding at the southern section of Church Street, traffic calming treatment at the intersection of Laurel Street and Church Street, rectification of pedestrian paving areas from Laurel Street to Walnut Street on the western side of Church Street, rectification of pedestrian paving areas from Laurel Street to Lime Street including the public toilet and social gathering space at Lime Street on the eastern side of Church Street, rectification of all road pavement works associated with storm water works, installation of furniture, way-finding and associated landscape works. Click for more details...

BALLARAT SOUTH WASTEWATER TREATMENT PLANT AUGMENTATION
Ballarat South Wastewater Treatment Plant Augmentation is currently at the Construction stage, valued at about $ 1000000 it is Augmentation works - boiler and heat exchanger at the Ballarat South Wastewater Treatment Plant. The works involve detailed design, procurement of all equipment and materials, including a new hot water boiler, a new heat exchanger and new pipework, electrical works and systems integration, decommissioning, removal and disposal of existing equipment and materials, and installation and commissioning of the new equipment and materials. Click for more details...

HAZELDENE'S FARM WASTEWATER PIPELINE
Wastewater Pipeline project at 74 Hazeldenes Rd, Lockwood, VIC 3539 in the Public Utilities (Water distribution systems, Drainage). Construction of water main & wastewater pipeline, including the supply, delivery, installation, testing & commissioning, remedying of defects, guarantees & all other obligations. It includes 3 separable portions made up of: augmentation of CW water main, upgrade to Hazeldene's water main & new private wastewater pipeline. Click for more details...

YARRA STREET BACKLOG SEWER PROJECT
Sewer Project project at 227 Yarra St, Warrandyte, VIC 3113 in the Public Utilities (Treatment plants, Sewerage reticulation). Construction of backlog sewer works at 227 Yarra St, Warrandyte. Click for more details...

ROYAL MELBOURNE GOLF CLUB MAINTENANCE FACILITIES UPGRADE
Maintenance Workshop/Vehicle Wash Bay/Pumping Station - Upgrade project at 32 Cheltenham Rd, Black Rock, VIC 3193 in the Public Utilities (Pumping Stations). Demolition of existing buildings, removal of vegetation and buildings and works associated with the upgrade of the existing maintenance facilities. Click for more details...

GOULBURN VALLEY WATER WATER SUPPLY DEMAND STRATEGY 2017 - 2067
Water Supply Consultants New project In The Greater Shepparton Council Area. Consultants required for the Water Supply Demand Strategy 2017-2067. Click for more details...

MONOMEITH STREET STORMWATER DRAINAGE STAGE 2
Currently at the Construction stage In Casey is a project estimated to be $ 300000. This project Construction of stormwater drainage upgrade works in Monomeith Street Tooradin. Work to include minor existing stormwater removal, earthworks, reinstatement of unsealed crossovers, laying of 320m of underground pipe (up to 600mm in diameter) & construction of 15 pits. Click for more details...

LOWER MURRAY WATER ANNUAL SEWER REHABILITATION PROGRAM 2015/16 - 2017/18
Public Utilities (Treatment plants, Sewerage reticulation) project at Various locations within the region of, Mildura, VIC 3500 for New. Lower Murray Water (LMW) continually monitors & evaluates the condition of the reticulated sewer networks in its various Sewerage Districts as part of its commitment to service delivery. The sewer networks maintained by LMW consist of main line sewers (SMN's), attached sewer maintenance structures including sewer maintenance holes (SMH's) & house branch connections on the sewer main. SMN's & SMH's identified as being in need of rehabilitation are included in an annual sewer rehabilitation program based on a criticality rating & a history that may include breakages, root infestation, infiltration, a condition that has caused a blockage &/or spill, exhibits structural damage due to corrosion or ground movement or if in the opinion of LMW, the potential risk of collapse of the sewer & its overburden needs to be eliminated to protect public safety & avoid property damage etc. Click for more details...

SALE LIVESTOCK EXCHANGE CIVIL WORKS
Public Utilities (Water distribution systems, Drainage) New project at Saleyards Rd, Sale, VIC 3850. This type is Civil Works with Local Govt ownership. The upgrade of civil infrastructure for the Sale Livestock Exchange. Work includes construction of new concrete crossovers, kerb & channel replacement, drainage pit modifications & installation of traffic control bollards. Click for more details...

LAANECOORIE WATER TREATMENT PLANT UPGRADES
Currently at the Construction stage In Greater Bendigo is a project estimated to be $ 750000. This project Upgrades to Laanecoorie Water Treatment Plant. Works include: upgrade of filters, supply, installation & commissioning of UV, PAC dosing system; design & construction of PAC contact tanks, UV shed & chlorine tank. Click for more details...

HOPKINS AVENUE SEWER PUMP STATION ODOUR CONTROL BIOFILTER
Currently at the Construction stage In Greater Bendigo is a project estimated to be $ 250000. This project Construction of an Odour Control Biofilter at Hopkins Avenue SPS. The works include: a new vent stack, containment bund & associated PLC, SCADA & electrical works. Click for more details...

TATURA WMF RECLAIMED WATER TRANSFER MAIN
Public Utilities (Water distribution systems, Drainage) project In The Greater Shepparton Council Area of Water Transfer Main type. Tatura Wastewater Management Facility reclaimed water transfer main. Click for more details...

GREGORY COURT DRAINAGE UPGRADE WORKS STAGE 2
Public Utilities (Water distribution systems, Drainage) project In The Manningham Council Area of Local Govt ownership. Drainage Improvement Works, Stage 2, Gregory Court, Doncaster. Click for more details...

DEFENCE DEPARTMENT RIVERINA MINOR NEW WORKS
Public Utilities (Water distribution systems, Drainage) New project at RAAF Wagga, Albury/Wodonga Military area &, Echuca, VIC 3564. This type is Military with Federal ownership. General building maintenance & minor construction tasks to buildings at RAAF Base Wagga, Albury/Wodonga Military Area & Echuca. Irrigation maintenance works at Albury/Wodonga Military area Click for more details...

VIOLET STREET ROAD RECONSTRUCTION
Roadworks New project In The Frankston Council Area. Violet Street Reconstruction. Scope of works include kerb & channel replacement, layback reconstruction, drainage installation, asphalt overlay & other associated works. Click for more details...

BONDI ROAD DRAINAGE UPGRADE
Public Utilities (Water distribution systems, Drainage) project for New development. Construction of 500 metres of street pipe drainage & associated pits, asphalt re-sheeting of road pavement, replacement of footpaths & reinstatement of nature strips. Click for more details...

MAINTONGOON ROAD SAFETY IMPROVEMENTS
Public Utilities (Water distribution systems, Drainage) project at Maintongoon Rd, Bonnie Doon, VIC 3720 for New. Safety improvements to Maintongoon Road, Bonnie Doon. Works includes - traffic management, trimming of batters, shoulder widening & drainage improvements. Click for more details...

SHEPPARTON REGIONAL SPORTS PRECINCT EAST WEST LINK BOULEVARD
Public Utilities (Water distribution systems, Drainage) project at Brauman & Wyndham Sts, Shepparton, VIC 3630 for New. Balance of Precinct East West Links Boulevard. Construction will consist of, roads, roundabouts, car parks, stormwater drainage, sewer & water, footpaths, street lighting & other associated civil works at the Greater Shepparton Regional Sports Precinct. Click for more details...

MOUNT ELIZA WAY ROAD RECONSTRUCTION
Roadworks project at Mount Eliza Way, Mount Eliza, VIC 3930 In The Council Area Of Mornington Peninsula of Local Govt. Road reconstruction, widening & drainage upgrade of Mount Eliza Way in Mount Eliza. Construction works include tree removal, excavation of existing unsealed shoulders, placement of new pavement, concrete kerb & asphalt seal. A main underground drainage line is to be installed, in addition to road rehabilitation works including a full width asphalt overlay. Click for more details...

LOIS STREET ROAD REHABILITATION WORKS
Public Utilities (Water distribution systems, Drainage) New project at Lois St, St Albans, VIC 3021. This type is Road - Rehabilitation with Local Govt ownership. Rehabilitate 1308 sqm of road pavement, including 778 sqm of concrete footpath & vehicle crossings, 393 lin m of kerb & channel, 244 tonnes of asphalt, drainage & other associated road works at Lois St, St Albans. Click for more details...

WHYTES ROAD SEWER RISING MAIN CONSTRUCTION
A project in the VIC Within Wodonga. Construction of a 1,936 m, 300 mm sewer rising main, along Whyte?s Road, from the Riverside Estate Pump Station to Baranduda Waste Water Treatment Plant. Click for more details...

MEADOWGLEN INTERNATIONAL ATHLETICS STADIUM
Public Utilities (Water distribution systems, Drainage) Renovations, Refurbishments etc. project at 146 - 156 McDonalds Rd, Epping, VIC 3076. This type is Athletics Track with Local Govt ownership. Renewal of Athletics Track. Works include removal of existing synthetic track surface, drainage upgrades & installation of new polyurethane synthetic surface, new hammer throw cage & all associated works at the Meadowglen International Athletics Stadium. Click for more details...

SWANSTON STREET DRAINAGE WORKS
Drainage Works project at 59 Swanston St, Heidelberg Heights, VIC 3081 In The Council Area Of Banyule of Local Govt. Drainage Works at 59 Swanston Street, Heidelberg Heights. Click for more details...

GVW MAINS RELOCATION WELSFORD STREET STAGES 1 & 2
A project in the VIC Within Greater Shepparton. Excavation, supply, laying & backfilling of approximately 24 metres of 100mm diameter DICL (PN35), 90m metres of 150mm diameter DICL (PN35) water main & re-establish connections to existing property & fire services as shown on plans. Click for more details...

THE AVENUE FLINDERS FLOOD MITIGATION STAGE 1
Public Utilities (Water distribution systems, Drainage) project In The Mornington Peninsula Council Area of Flood Mitigation Works - Stage 1 type. Stage 1 includes installing a main underground drainage line along Cove Lane between the Avenue & The Esplanade. Works include installing large pipes, junction pits, surcharge pits as well as reconstructing the road pavement with full width asphalt overlay. Click for more details...